PEKERJAAN PERSIAPAN PEKERJAAN BETO N STRUKTUR PRAKTIS A PEK. PASANGAN DINDING A PEK. ATAP C

I. PEKERJAAN PERSIAPAN

1 Pek. Pembersihan Lokasi M2 123.25 3,900.00 480,675.00 2 Pek. Pengukuran dan pasang Bouwplank M 46.00 48,330.00 2,223,180.00 2,703,855.00 II. PEKERJAAN PO NDASI BATU KALI A Pondasi Batu Kali 1P c:4Psr 1 Pek. Galian T anah Pondasi M3 52.14 35,500.00 1,850,792.50 2 Pek. Urugan T anah Bekas Galian M3 17.38 11,833.33 205,643.61 3 Pasangan Aanstamping + Pasir M3 6.85 173,400.00 1,187,356.50 4 Pasangan P ondasi Bat u Kali 1Pc:4P sr M3 30.95 452,180.00 13,994,971.00 17,238,763.61

III. PEKERJAAN BETO N STRUKTUR PRAKTIS A

Beton Praktis 1pc:2ps:3krl 1 Beton Praktis 1pc:2ps:3krl a Sloof M3 2.42 3,072,030.00 7,418,952.45 b Kolom M3 2.22 3,072,030.00 6,815,298.56 c Ring M3 2.16 3,072,030.00 6,635,584.80 d Latai M3 0.66 3,072,030.00 2,039,059.91 22,908,895.72

IV. PEK. PASANGAN DINDING A

Pasangan dinding bata merah 1P c:6Psr, 12 Bata dan T rasram 1P c:3Psr, 12 Bata 1 Dinding Batu Merah T rasram 1Pc:3Psr, 12 Bat a M2 27.00 77,531.00 2,093,337.00 2 Dinding Batu Merah 1Pc:6P sr, 12 Bat a M2 247.82 70,251.00 17,409,673.07 3 Plest. Dinding Batu Merah T rasram 1Pc:3Psr M2 54.00 48,433.40 2,615,403.60 4 Plest. Dinding Batu Merah 1Pc:6Psr M2 495.64 42,934.40 21,280,091.88 5 Acian Dinding M2 534.44 19,780.00 10,571,262.76 6 Cat Dinding M2 534.44 21,186.00 11,322,688.21 65,292,456.53 V. PEK. PINTU JENDELA A Pintu, jendela dan kusen dari kayu jati + kaca 1 Pekerjaan P int u a PUT Bh 1.00 2,135,935.60 2,135,935.60 b PL Bh 1.00 3,591,034.47 3,591,034.47 c P1 Bh 3.00 1,553,548.00 4,660,644.00 d P2 Bh 2.00 1,487,354.80 2,974,709.60 2 Pekerjaan Jendela a J1a Bh 1.00 810,501.01 810,501.01 b J2b Bh 3.00 2,050,455.62 6,151,366.87 c J3 Bh 2.00 1,104,291.91 2,208,583.82 d BV Bh 1.00 360,830.15 360,830.15 3 Cat Pintu Jendela Kayu M2 70.38 38,740.00 2,726,559.94 25,620,165.46

VI. PEK. ATAP C

Rangka atap kuda-kuda baja ringan dan kombinasi gunung-gunung, genteng beton + plat talang cor 1 Dinding Batu Merah 1Pc:6P sr, 12 Bat a M2 6.10 70,251.00 428,250.10 2 Plest. Dinding Batu Merah 1Pc:6Psr M2 12.19 42,934.40 523,456.20 3 Acian Dinding M2 12.19 19,780.00 241,157.76 4 Cat Dinding M2 12.19 21,186.00 258,299.71 5 Kolom M3 0.09 3,072,030.00 265,423.39 6 Ring M3 0.17 3,072,030.00 522,552.30 7 Pekerjaan Kuda-kuda dan Rangka Baja Ringan At aM2 80.24 206,610.00 16,578,047.19 8 Pekerjaan Atap Genteng Beton M2 80.24 40,580.00 3,256,072.58 9 Pekerjaan T alangJurai Gent eng Bet on M 27.48 58,020.00 1,594,238.85 10 Kolom Beton T alang M2 0.06 3,072,030.00 176,257.72 11 Ring Bet on T alang M3 0.20 3,072,030.00 622,086.08 12 Plat Beton T alang M3 0.68 3,270,345.00 2,207,482.88 13 Pekerjaan List Plang M 25.73 72,238.00 1,858,683.74 14 Cat List Plang M2 5.15 38,740.00 199,356.04 28,731,364.54 JUMLAH I JUMLAH II JUMLAH III JUMLAH IV JUMLAH V A JUMLAH VI B RENCANA ANGGARAN BIAYA TIPE 60 NT No Uraian Pe ke rjaan Sat Vol Harga S atuan RP Jumlah Harga Rp LAMPIRAN II-7 D Rangka atap kuda-kuda baja ringan, genteng beton + plat talang cor 1 Pekerjaan Kuda-kuda dan Rangka Baja Ringan At a M2 80.24 206,610.00 16,578,047.19 2 Pekerjaan Atap Genteng Beton M2 80.24 40,580.00 3,256,072.58 3 Pekerjaan T alangJurai Gent eng Bet on M 27.48 58,020.00 1,594,238.85 4 Kolom Beton T alang M2 0.13 3,072,030.00 411,268.02 5 Ring Bet on T alang M3 0.50 3,072,030.00 1,520,654.85 6 Plat Beton T alang M3 1.65 3,270,345.00 5,396,069.25 7 Pekerjaan List Plang M 25.73 72,238.00 1,858,683.74 8 Cat List Plang M2 5.15 38,740.00 199,356.04 30,814,390.52

VII. PEK. PLAFO N A