PEKERJAAN PERS IAPAN PEKERJAAN BETO N STRUKTUR PRAKTIS A PEK. PASANGAN DINDING A PEK. PINTU JENDELA PEK. ATAP C

I. PEKERJAAN PERS IAPAN

1 Pek. Pembersihan Lokasi M2 126.00 3,900.00 491,400.00 2 Pek. Pengukuran dan pasang Bouwplank M 43.80 48,330.00 2,116,854.00 2,608,254.00 II. PEKERJAAN PO NDASI BATU KALI A Pondasi Bat u Kali 1Pc:4Psr 1 Pek. Galian T anah P ondasi M3 51.34 35,500.00 1,822,587.75 2 Pek. Urugan T anah Bekas Galian M3 17.11 11,833.33 202,509.75 3 Pasangan Aanstamping + Pasir M3 6.66 173,400.00 1,155,364.20 4 Pasangan Pondasi Batu Kali 1Pc:4P sr M3 30.79 452,180.00 13,924,430.92 17,104,892.62

III. PEKERJAAN BETO N STRUKTUR PRAKTIS A

Beton Praktis 1pc:2ps:3krl 1 Beton Praktis 1pc:2ps:3krl a Sloof M3 2.52 3,072,030.00 7,746,123.65 b Kolom M3 2.33 3,072,030.00 7,153,989.86 c Ring M3 1.32 3,072,030.00 4,067,751.72 d Latai M3 0.70 3,072,030.00 2,156,565.06 21,124,430.29

IV. PEK. PASANGAN DINDING A

Pasangan dinding bat a merah 1P c:6Psr, 12 Bata dan T rasram 1Pc:3Psr, 12 Bata 1 Dinding Bat u Merah T rasram 1Pc:3Psr, 12 Bata M2 26.73 77,531.00 2,072,015.98 2 Dinding Bat u Merah 1Pc:6Psr, 12 Bat a M2 183.58 70,251.00 12,896,678.58 3 Plest . Dinding Batu Merah T rasram 1Pc:3Psr M2 53.45 48,433.40 2,588,765.23 4 Plest . Dinding Batu Merah 1Pc:6P sr M2 367.16 42,934.40 15,763,794.30 5 Acian Dinding M2 411.51 19,780.00 8,139,667.80 6 Cat Dinding M2 411.51 21,186.00 8,718,250.86 50,179,172.75

V. PEK. PINTU JENDELA

A Pint u, jendela dan kusen dari kayu jati + kaca 1 Pekerjaan Pintu a PUT Bh 1.00 2,520,852.00 2,520,852.00 b P1 Bh 3.00 1,899,112.80 5,697,338.40 c P2 Bh 2.00 1,899,112.80 3,798,225.60 d P3 PVC Bh 1.00 363,000.00 363,000.00 2 Pekerjaan Jendela a JT 1 Bh 2.00 282,659.20 565,318.40 b JT 2 Bh 1.00 225,506.20 225,506.20 c J1a Bh 3.00 1,212,574.66 3,637,723.98 d J2a Bh 2.00 2,116,206.66 4,232,413.31 e J3a Bh 1.00 3,093,407.19 3,093,407.19 3 Cat Pint u Jendela Kayu M2 74.12 38,740.00 2,871,408.80 27,005,193.88

VI. PEK. ATAP C

Rangka atap kuda-kuda baja ringan dan kombinasi gunung-gunung, genteng beton + plat talang cor 1 Dinding Bat u Merah 1Pc:6Psr, 12 Bat a M2 7.28 70,251.00 511,251.65 2 Plest . Dinding Batu Merah 1Pc:6P sr M2 14.56 42,934.40 624,910.19 3 Acian Dinding M2 14.56 19,780.00 287,897.90 4 Cat Dinding M2 14.56 21,186.00 308,362.23 5 Kolom M3 0.05 3,072,030.00 141,697.38 6 Ring M3 0.18 3,072,030.00 566,789.54 7 Pekerjaan Kuda-kuda dan Rangka Baja Ringan Ata M2 95.00 206,610.00 19,627,377.12 8 Pekerjaan At ap Genteng Beton M2 95.00 40,580.00 3,854,987.48 9 Pekerjaan T alangJurai Genteng Bet on M 54.08 58,020.00 3,137,862.22 10 Kolom Beton T alang M2 0.04 3,072,030.00 124,417.22 11 Ring Beton T alang M3 0.21 3,072,030.00 649,734.35 12 Plat Beton T alang M3 0.33 3,270,345.00 1,075,943.51 13 Pekerjaan List P lang M 38.35 72,238.00 2,770,327.30 14 Cat List Plang M2 7.67 38,740.00 297,135.80 33,978,693.88 JUMLAH I JUMLAH II JUMLAH III JUMLAH IV JUMLAH V A JUMLAH VI B RENC ANA ANGGARAN BIAYA TIPE 60 GA No Uraian Pe k e rjaan Sat Vol Harga Satuan RP Jum lah Harga Rp LAMPIRAN II-5 D Rangka atap kuda-kuda baja ringan, genteng beton + plat talang cor 1 Pekerjaan Kuda-kuda dan Rangka Baja Ringan Ata M2 95.00 206,610.00 19,627,377.12 2 Pekerjaan At ap Genteng Beton M2 95.00 40,580.00 3,854,987.48 3 Pekerjaan T alangJurai Genteng Bet on M 54.08 58,020.00 3,137,862.22 4 Kolom Beton T alang M2 0.09 3,072,030.00 290,306.84 5 Ring Beton T alang M3 0.53 3,072,030.00 1,631,247.93 6 Plat Beton T alang M3 0.83 3,270,345.00 2,701,304.97 7 Pekerjaan List P lang M 38.35 72,238.00 2,770,327.30 8 Cat List Plang M2 7.67 38,740.00 297,135.80 34,310,549.66

VII. PEK. PLAFO N A