PEKERJAAN PENGEC ETAN PEKERJAAN SANITER DAN INSTALAS I AIR 8,045,505.85 PEKERJAAN PERSIAPAN PEKERJAAN TANAH DAN URUGAN

No Urai an Pe ke rjaan Sat Vol Harga Satuan Ju mlah Su b Total IX. PEKERJAAN PINTU JENDELA DAN KAC A 21,053,886.85 a. Kusen PUT jati perubahan total M3 0.00 9,146,470.00 0.00 b. Kusen P.1 jati M3 0.00 9,146,470.00 0.00 c. Kusen P.2 jati M3 0.00 9,146,470.00 0.00 d. Kusen PL jati M3 0.00 9,146,470.00 0.00 e. Kusen J.1a jat i M3 0.00 9,146,470.00 0.00 f. Kusen J.2b jat i M3 0.00 9,146,470.00 0.00 g. Kusen J.3 jati M3 0.00 9,146,470.00 0.00 h. Kusen BV jati M3 0.00 9,146,470.00 0.00 i. Daun Pintu PUT jati M2 0.00 459,320.00 0.00 j. Daun Pintu P.1 jat i M2 0.00 459,320.00 0.00 k. Daun Pintu P.2 jat i M2 0.00 459,320.00 0.00 l. Daun Pintu PL jati M2 0.00 459,320.00 0.00 m. Daun Jendela J.1a jati M2 0.00 459,320.00 0.00 n. Daun Jendela J.2b jati M2 0.00 459,320.00 0.00 o. Daun Jendela J.3 jati M2 0.00 459,320.00 0.00 p. Daun BV Jat i M2 0.00 459,320.00 0.00 q. Kaca Jendela J.1a bening 5mm M2 0.00 82,919.80 0.00 r. Kaca Jendela J.2b bening 5mm M2 0.00 82,919.80 0.00 s. Kaca Jendela J.3 bening 5mm M2 0.00 82,919.80 0.00 t . Kaca BV bening 5mm M2 0.00 82,919.80 0.00 Pekerjaan Pintu sesuai gambar PUT Bh 1.00 1,959,639.98 1,959,639.98 PL Bh 1.00 3,256,822.99 3,256,822.99 P1 Bh 3.00 1,432,856.38 4,298,569.15 P2 Bh 2.00 1,369,034.09 2,738,068.17 Pekerjaan Jendela sesuai gambar J1a Bh 1.00 756,635.55 756,635.55 J2b Bh 3.00 1,887,832.50 5,663,497.51 J3 Bh 2.00 1,020,148.44 2,040,296.88 BV Bh 1.00 340,356.61 340,356.61

X. PEKERJAAN PENGEC ETAN

9,066,389.70 a. Pek. Cat Dinding Baru perubahan volume M2 534.44 11,397.20 6,091,142.36 b. Pek. Cat Plafon Baru perubahan volume M2 56.70 11,397.20 646,221.24 c. Cat Kayu bidang baru perubahan volume dan harga sat uan M2 70.38 30,837.00 2,170,338.90 Cat List Plang penambahan total M2 5.15 30,837.00 158,687.20 XI. PEKERJAAAN INSTALAS I LIS TRIK 3,664,075.00 a. Lampu Gantung Dengan Instalasi T it ik 12.00 101,300.00 1,215,600.00 b. Sakelar T unggal T it ik 6.00 27,500.00 165,000.00 c. Sakelar Dobel T it ik 3.00 31,500.00 94,500.00 d. Stop Kontak Dengan Instalasi T it ik 4.00 31,500.00 126,000.00 e. Meteran Listrik T it ik 1.00 2,000,000.00 2,000,000.00 f. Panel T it ik 1.00 62,975.00 62,975.00

XII. PEKERJAAN SANITER DAN INSTALAS I AIR 8,045,505.85

Closet Duduk Unit 2.00 194,312.00 388,624.00 Floor Drain Unit 2.00 15,640.00 31,280.00 Kran Air Biasa perubahan volume Unit 4.00 20,690.00 82,760.00 Kran Air Stainless perubahan volume Unit 1.00 39,690.00 39,690.00 Bak cuci stainless steel diganti jadi satu Unit 0.00 150,000.00 0.00 Saluran air Bersih D. 1 PVC M 5.47 17,775.02 97,229.36 Saluran air Bersih D. 34 P VC M 14.00 14,907.52 208,705.28 Saluran air Bersih D. 12 P VC M 6.00 13,008.77 78,052.62 Saluran Air Kotor D. 3 PVC M 8.00 76,866.94 614,935.52 Saluran Kotoran tinja D.4 PVC M 13.00 107,479.44 1,397,232.72 Pipa Hawa D.2 GI M 2.00 173,915.06 347,830.12 Meja Bet on Bak Cuci, Kompor Kelengkapan t ambah Unit 1.00 729,166.23 729,166.23 Sept ic T ank Unit 1.00 2,000,000.00 2,000,000.00 Resapan Unit 1.00 2,000,000.00 2,000,000.00 Bak Kontrol Unit 3.00 10,000.00 30,000.00 TO TAL JUMLAH 159,498,473.10 LAMPIRAN II-17 No Urai an Pe ke rjaan Vol Sat Harga Satu an Juml ah Harga Total Harga

I. PEKERJAAN PERSIAPAN

4,250,230.00 1 Pembersihan lokasi perubahan volume 130.00 m2 7,500.00 975,000.00 2 Pemasangan Bouwplank perubahan volume 49.70 m1 65,900.00 3,275,230.00

II. PEKERJAAN TANAH DAN URUGAN

3,438,608.25 1 Galian tanah biasa sedalam 1 meter perubahan volume 32.75 m3 31,750.00 1,039,939.50 2 Urugan pasir bawah pondasi perubahan volume 0.00 m3 105,590.00 0.00 Urugan tanah timbunan pilihan penambahan Total 19.94 m3 105,590.00 2,105,966.15 3 Urugan pasir bwh lantai perubahan volume 1.33 m3 110,680.00 147,165.66 4 Urugan tanah kembali perubahan volume 10.92 m3 13,330.00 145,536.94

III. PEKERJAAN PASANGAN