Elevasi Jembatan Rencana : Perhitungan kelandaian memanjang Penghitungan lengkung vertikal

commit to user Sambungan dari Tabel 3.3 Elevasi Muka Tanah Asli Stationing Elevasi Stationing Elevasi 3+300 1400.000 3+900 1450.806 3+350 1401.705 3+950 1450.752 3+400 1405.682 4+000 1450.926 3+450 1411.110 4+050 1450.446 3+500 1416.667 4+100 1453.819 3+550 1419.444 4+150 1458.681 3+600 1423.077 4+200 1463.333 3+650 1425.000 4+250 1467.083 3+700 1434.091 4+300 1471.875 3+750 1438.889 4+350 1475.000 3+800 1445.833 4+400 1482.639 3+850 1450.000 4+450 1487.500

3.5.1. Elevasi Jembatan Rencana :

• Jembatan 1 Elevasi dasar sungai = +1225 Elevasi muka air sungai = +1228 Elevasi muka air sungai saat banjir = +1230 Ruang bebas = 3 m Tebal plat jembatan = 1,5 m Elevasi rencana jembatan minimum = +1233,5 • Jembatan 2 Elevasi dasar sungai = +1421,5 Elevasi muka air sungai = +1424 Elevasi muka air sungai saat banjir = +1426 Ruang bebas = 3 m Tebal plat jembatan = 1,5 m Elevasi rencana jembatan minimum = +1432,5 commit to user commit to user

3.5.2. Perhitungan kelandaian memanjang

Tabel 3.4 Data Titik PVI No Titik STA Elevasi Beda Tinggi m Jarak Datar m Kelandaian Memanjang 1 A 0+000 1112,5 2 PVI 1 0+300 1138 3 PVI 2 0+900 1197 4 PVI 3 1+100 1208 5 PVI 4 1+375 1235 6 PVI 5 1+500 1235 7 PVI 6 2+000 1280 8 PVI 7 2+375 1317 9 PVI 8 3+000 1370 10 PVI 9 3+500 1416 11 PVI 10 3+625 1435 12 PVI 11 3+750 1435 13 PVI 12 3+950 1450 14 PVI 13 4+150 1457,6 15 B 4+450 1487 Kelandaian Memanjang Dapat Dihitung Dengan Menggunakan Rumus : 100 × ∆ = jarak elevasi g n Contoh Penghitungan : 8,5 100 300 1112,5 - 138 1 100 A - 1 PVI Jarak A Elevasi 1 PVI Elevasi 1 = × = × − = g Perhitungan kelandaian memanjang selanjutnya dapat dilihat pada tabel 3.4 di atas 25,5 300 8,50 59 11 27 45 37 53 46 11,5 15 7,6 29,4 600 200 275 125 500 375 620 500 125 125 200 200 300 9,83 5,50 9,82 0,00 9,00 9,87 8,55 9,10 9,20 0,00 7,50 3,80 9,80 commit to user

3.5.3. Penghitungan lengkung vertikal

3.4.2.1 PVI 1 Gambar 3.11 Lengkung Vertikal PV 1 Perhitungan Lv: 33 , 1 50 , 8 83 , 9 1 2 = − = − = ∆ g g Syarat keluwesan bentuk m V Lv 24 40 6 , 6 , = × = × = Syarat drainase m Lv 2 , 53 33 , 1 40 40 = × = ∆ × = Syarat kenyamanan m ik jam km t V Lv 33 , 33 det 3 40 = × = × = Pengurangan goncangan m V Lv 911 , 5 360 33 , 1 40 360 2 2 = × = ∆ × = PVI 1 g2=9,83 g1=8,50 a b c d e x x Lv commit to user Diambil Lv terbesar, yaitu = 53,2 m ~ dibulatkan 54 m m Lv Ev 196 , 800 54 91 , 2 800 = × = × ∆ = m Lv x y 022 , 54 200 54 33 , 1 200 2 4 1 2 = × × = × × ∆ = Stationing lengkung vertikal PVI 1 Sta A = Sta PVI 1 – 1 2 Lv = 0 + 300 - 1 2 54 = 0 + 273 m Sta B = Sta PVI 1 – 1 4 Lv = 0 + 300 - 1 4 54 = 0 + 286,5 m Sta C = Sta PVI 1 = 0 + 300 m Sta D = Sta PVI 1 + 1 4 Lv = 0 + 300 + 1 4 54 = 0 + 313,5 m Sta E = Sta PVI 1 + 1 2 Lv = 0 + 300 + 1 2 54 = 0 + 327 m commit to user Elevasi Lengkung vertikal: Elevasi a = Elevasi PVI 1 - ½Lv x g1 = 1038 - ½ 54 x 8,50 = 1035,705 m Elevasi b = Elevasi PVI 1 - ¼ Lv x g1 + y = 1038 - ¼ 54 x 8,5 + 0,022 = 1036,831 m Elevasi c = Elevasi PVI 1 + Ev = 1038 + 0,196 = 1038,196 m Elevasi d = Elevasi PVI 1 + ¼ Lv x g2 + y = 1038 + ¼ 54 x 9,83 + 0,022 = 1039,349 m Elevasi e = Elevasi PVI 1 + ½Lv x g2 = 1038 + ½ 54 x 9,83 = 1040,654 commit to user 3.4.2.2 PVI 2 I . Gambar 3.12 Lengkng Vertikal PVI 2 Perhitungan Lv: 33 , 4 83 , 9 50 , 5 2 3 = − = − = ∆ g g Syarat keluwesan bentuk m V Lv 24 40 6 , 6 , = × = × = Syarat drainase m Lv 2 , 173 33 , 4 40 40 = × = ∆ × = Syarat kenyamanan m ik jam km t V Lv 33 , 33 det 3 40 = × = × = Pengurangan goncangan m V Lv 24 , 19 360 33 , 4 40 360 2 2 = × = ∆ × = Diambil Lv yang terbesar,yaitu = 173,2 m ~ dibulatkan 174 m a PVI 2 b c d e g2=9,83 g3=5,50 x x Lv commit to user m Lv Ev 942 , 800 174 33 , 4 800 = × = × ∆ = m Lv x y 235 , 174 200 174 33 , 4 200 2 4 1 2 = × × = × × ∆ = Stationing lengkung vertikal PVI 2 Sta A = Sta PVI 2 – 1 2 Lv = 0+900 - 1 2 174 = 0+813 m Sta B = Sta PVI 2 – 1 4 Lv = 0+900 - 1 4 174 = 0+856,5 m Sta C = Sta PVI 2 = 0+900m Sta D = Sta PVI 2 + 1 4 Lv = 0+900 + 1 4 174 = 0+943,5 m Sta E = Sta PVI 2 + 1 2 Lv = 0+900 + 1 2 174 = 0+987 m commit to user Elevasi Lengkung vertikal: Elevasi a = Elevasi PVI 2 - ½Lv x g2 = 1197 - ½ 174 x 9,83 = 1188,448 m Elevasi b = Elevasi PVI 2 - ¼ Lv x g2 - y = 1197 - ¼ 174 x 9,83 - 0,235 = 1192,959 m Elevasi c = Elevasi PVI 2 - Ev = 1197 – 0,942 = 1196,058 m Elevasi d = Elevasi PVI 2 + ¼ Lv x g3 - y = 1197 + ¼ 174 x 5,50 - 0,235 = 1199,158 m Elevasi e = Elevasi PVI 2 + ½Lv x g3 = 1197 + ½ 174 x 5,50 = 1201,785 m commit to user 3.4.2.3 PVI 3 Gambar 3.13 Lengkung Vertikal PV 3 Perhitungan Lv: 32 , 4 50 , 5 82 , 9 3 4 = − = − = ∆ g g Syarat keluwesan bentuk m V Lv 24 40 6 , 6 , = × = × = Syarat drainase m Lv 8 , 172 32 , 4 40 40 = × = ∆ × = Syarat kenyamanan m ik jam km t V Lv 33 , 33 det 3 40 = × = × = Pengurangan goncangan m V Lv 2 , 19 360 32 , 4 40 360 2 2 = × = ∆ × = Diambil Lv terbesar, yaitu = 172,8 m ~ dibulatkan 173 m PVI 3 g4=9,82 g3=5,50 a b c d e x x Lv commit to user m Lv Ev 934 , 800 173 32 , 4 800 = × = × ∆ = m Lv x y 234 , 173 200 173 32 , 4 200 2 4 1 2 = × × = × × ∆ = Stationing lengkung vertikal PVI 3 Sta A = Sta PVI 3 – 1 2 Lv = 1 + 100 - 1 2 173 = 1 + 013,5 m Sta B = Sta PVI 3 – 1 4 Lv = 1 + 100 - 1 4 173 = 1 + 056,75 m Sta C = Sta PVI 3 = 1 + 100 m Sta D = Sta PVI 3 + 1 4 Lv = 1 + 100 + 1 4 173 = 1 + 143,25 m Sta E = Sta PVI 3 + 1 2 Lv = 1 + 100 + 1 2 173 = 1 + 186,50 m commit to user Elevasi Lengkung vertikal: Elevasi a = Elevasi PVI 3 - ½Lv x g3 = 1208 - ½ 173 x 5,50 = 1203,243 m Elevasi b = Elevasi PVI 3 - ¼ Lv x g3 + y = 1208 - ¼ 173 x 5,50 + 0,234 = 1205,387 m Elevasi c = Elevasi PVI 3 + Ev = 1208 + 0,934 = 1208,934 m Elevasi d = Elevasi PVI 3 + ¼ Lv x g4 + y = 1208 + ¼ 173 x 9,82 + 0,234 = 1212,481 m Elevasi e = Elevasi PVI 3 + ½Lv x g4 = 1208 + ½ 173 x 9,82 = 1216,494 m commit to user 3.4.2.4 PVI 4 Gambar 3.14 Lengkung Vertikal PVI 4 Perhitungan Lv: 82 , 9 82 , 9 4 5 = − = − = ∆ g g Syarat keluwesan bentuk m V Lv 24 40 6 , 6 , = × = × = Syarat drainase m Lv 8 , 392 82 , 9 40 40 = × = ∆ × = Syarat kenyamanan m ik jam km t V Lv 33 , 33 det 3 40 = × = × = Pengurangan goncangan m V Lv 64 , 43 360 82 , 9 40 360 2 2 = × = ∆ × = Diambil Lv yang terbesar,yaitu = 43,64 m ~ dibulatkan 44 m a b c d e g 5 = 0 g 4 = 9,82 PVI 4 x x Lv commit to user m Lv Ev 540 , 800 44 82 , 9 800 = × = × ∆ = m Lv x y 135 , 44 200 44 82 , 9 200 2 4 1 2 = × × = × × ∆ = Stationing lengkung vertikal PVI 4 Sta A = Sta PVI 4 – 1 2 Lv = 1+375 - 1 2 44 = 1+353 m Sta B = Sta PVI 4 – 1 4 Lv = 1+375 - 1 4 44 = 1+364 m Sta C = Sta PVI 4 = 1+375 m Sta D = Sta PVI 4 + 1 4 Lv = 1+375 + 1 4 44 = 1+386 m Sta E = Sta PVI 4 + 1 2 Lv = 1+375 + 1 2 44 = 1+397 m commit to user Elevasi Lengkung vertikal: Elevasi a = Elevasi PVI 4 - ½Lv x g4 = 1235 - ½ 44 x 9,82 = 1232,840 m Elevasi b = Elevasi PVI 4 - ¼ Lv x g4 - y = 1235 - ¼ 44 x 9,82 - 0,135 = 1234,055 m Elevasi c = Elevasi PVI 4 - Ev = 1235 – 0,540 = 1234,460 m Elevasi d = Elevasi PVI 4 − ¼ Lv x g5 - y = 1235 − ¼ 44 x 0,00 - 0,135 = 1234,865 m Elevasi e = Elevasi PVI 4 − ½Lv x g5 = 1235 − ½ 44 x 0,00 = 1235 m commit to user 3.4.2.5 PVI 5 PVI 5 Gambar 3.15 Lengkung Vertikal PVI 5 Perhitungan Lv: 00 , 9 00 , 9 5 6 = − = − = ∆ g g Syarat keluwesan bentuk m V Lv 24 40 6 , 6 , = × = × = Syarat drainase m Lv 360 00 , 9 40 40 = × = ∆ × = Syarat kenyamanan m ik jam km t V Lv 33 , 33 det 3 40 = × = × = Pengurangan goncangan m V Lv 40 360 00 , 9 40 360 2 2 = × = ∆ × = Diambil Lv yang terbesar,yaitu = 40 m a b c d g 5 = 0 g 6 = 9,00 e x x Lv commit to user m Lv Ev 450 , 800 40 00 , 9 800 = × = × ∆ = m Lv x y 113 , 40 200 40 00 , 9 200 2 4 1 2 = × × = × × ∆ = Stationing lengkung vertikal PVI 5 Sta A = Sta PVI 5 – 1 2 Lv = 1+500 - 1 2 40 = 1+480 m Sta B = Sta PVI 5 – 1 4 Lv = 1+500 - 1 4 40 = 1+490 m Sta C = Sta PVI 5 = 1+500 m Sta D = Sta PVI 5 + 1 4 Lv = 1+500 + 1 4 40 = 1+510 m Sta E = Sta PVI 5 + 1 2 Lv = 1+500 + 1 2 40 = 1+520 m commit to user Elevasi Lengkung vertikal: Elevasi a = Elevasi PVI 5 - ½Lv x g5 = 1235 - ½ 40 x 0 = 1235 m Elevasi b = Elevasi PVI 5 - ¼ Lv x g5 + y = 1235 - ¼ 40x 0 + 0,113 = 1235,113 m Elevasi c = Elevasi PVI 5 + Ev = 1235 + 0,450 = 1235,450 m Elevasi d = Elevasi PVI 5 + ¼ Lv x g6 + y = 1235 + ¼ 40 x 9,00 + 0,113 = 1236,013 m Elevasi e = Elevasi PVI 5 + ½Lv x g6 = 1235 + ½ 40 x 9,00 = 1236,800 m commit to user 3.4.2.6 PVI 6 Gambar 3.16 Lengkung Vertikal PV 6 Perhitungan Lv: 87 , 00 , 9 87 , 9 6 7 = − = − = ∆ g g Syarat keluwesan bentuk m V Lv 24 40 6 , 6 , = × = × = Syarat drainase m Lv 8 , 34 87 , 40 40 = × = ∆ × = Syarat kenyamanan m ik jam km t V Lv 33 , 33 det 3 40 = × = × = Pengurangan goncangan m V Lv 867 , 3 360 87 , 40 360 2 2 = × = ∆ × = Diambil Lv terbesar, yaitu = 34,8 m ~ dibulatkan 35 m PVI 6 g7=9,87 g6=9,00 a b c d e x x Lv commit to user m Lv Ev 038 , 800 35 87 , 800 = × = × ∆ = m Lv x y 009 , 35 200 35 87 , 200 2 4 1 2 = × × = × × ∆ = Stationing lengkung vertikal PVI 6 Sta A = Sta PVI 6 – 1 2 Lv = 2 + 000 - 1 2 35 = 1 + 982,5 m Sta B = Sta PVI 6 – 1 4 Lv = 2 + 000 - 1 4 35 = 1 + 991,25 m Sta C = Sta PVI 6 = 2 + 000 m Sta D = Sta PVI 6 + 1 4 Lv = 2 + 000 + 1 4 35 = 2 + 008,75 m Sta E = Sta PVI 6 + 1 2 Lv = 2 + 000 + 1 2 35 = 2 + 017,5 m commit to user Elevasi Lengkung vertikal: Elevasi a = Elevasi PVI 6 - ½Lv x g6 = 1280 - ½ 35 x 9,00 = 1278,425 m Elevasi b = Elevasi PVI 6 - ¼ Lv x g6 + y = 1280 - ¼ 35 x 9,00 + 0,009 = 1279,204 m Elevasi c = Elevasi PVI 6 + Ev = 1280 + 0,038 = 1280,038 m Elevasi d = Elevasi PVI 6 + ¼ Lv x g7 + y = 1280 + ¼ 35 x 9,87 + 0,009 = 1280,873 m Elevasi e = Elevasi PVI 6 + ½Lv x g7 = 1280 + ½ 35 x 9,87 = 1281,727 m commit to user 3.4.2.7 PVI 7 I . Gambar 3.12 Lengkng Vertikal PVI 7 Perhitungan Lv: 81 , 1 87 , 9 06 , 8 7 8 = − = − = ∆ g g Syarat keluwesan bentuk m V Lv 24 40 6 , 6 , = × = × = Syarat drainase m Lv 4 , 72 81 , 1 40 40 = × = ∆ × = Syarat kenyamanan m ik jam km t V Lv 33 , 33 det 3 40 = × = × = Pengurangan goncangan m V Lv 04 , 8 360 81 , 1 40 360 2 2 = × = ∆ × = Diambil Lv yang terbesar,yaitu = 72,4 m ~ dibulatkan 73 m a PVI 7 b c d e g7=9,87 g8=8,06 x x Lv commit to user m Lv Ev 165 , 800 73 81 , 1 800 = × = × ∆ = m Lv x y 041 , 73 200 73 81 , 1 200 2 4 1 2 = × × = × × ∆ = Stationing lengkung vertikal PVI 7 Sta A = Sta PVI 7 – 1 2 Lv = 2+375 - 1 2 73 = 2+338,50 m Sta B = Sta PVI 7 – 1 4 Lv = 2+375 - 1 4 73 = 2+356,75 m Sta C = Sta PVI 7 = 2+375 m Sta D = Sta PVI 7 + 1 4 Lv = 2+375 + 1 4 73 = 2+393,25 m Sta E = Sta PVI 7 + 1 2 Lv = 2+375 + 1 2 73 = 2+411,50 m commit to user Elevasi Lengkung vertikal: Elevasi a = Elevasi PVI 7 - ½Lv x g7 = 1317 - ½ 73 x 9,87 = 1313,397 m Elevasi b = Elevasi PVI 7 - ¼ Lv x g7 - y = 1317 - ¼ 73 x 9,87 - 0,041 = 1315,240 m Elevasi c = Elevasi PVI 7 - Ev = 1317 – 0,165 = 1316,835 m Elevasi d = Elevasi PVI 7 + ¼ Lv x g8 - y = 1317 + ¼ 73 x 8,06 - 0,041 = 1318,430 m Elevasi e = Elevasi PVI 7 + ½Lv x g8 = 1317 + ½ 73 x 8,06 = 1319,942 m commit to user 3.4.2.8 PVI 8 Gambar 3.18 Lengkung Vertikal PV 8 Perhitungan Lv: 04 , 1 06 , 8 10 , 9 8 9 = − = − = ∆ g g Syarat keluwesan bentuk m V Lv 24 40 6 , 6 , = × = × = Syarat drainase m Lv 6 , 45 04 , 1 40 40 = × = ∆ × = Syarat kenyamanan m ik jam km t V Lv 33 , 33 det 3 40 = × = × = Pengurangan goncangan m V Lv 067 , 5 360 04 , 1 40 360 2 2 = × = ∆ × = Diambil Lv terbesar, yaitu = 45,6 m ~ dibulatkan 46 m PVI 8 g9=9,10 g8=8,06 a b c d e x x Lv commit to user m Lv Ev 060 , 800 46 04 , 1 800 = × = × ∆ = m Lv x y 016 , 46 200 46 04 , 1 200 2 4 1 2 = × × = × × ∆ = Stationing lengkung vertikal PVI 8 Sta A = Sta PVI 8 – 1 2 Lv = 3 + 000 - 1 2 46 = 2 + 977 m Sta B = Sta PVI 8 – 1 4 Lv = 3 + 000 - 1 4 46 = 2 + 988,5 m Sta C = Sta PVI 8 = 3 + 000 m Sta D = Sta PVI 8 + 1 4 Lv = 3 + 000 + 1 4 46 = 3 + 011,5 m Sta E = Sta PVI 8 + 1 2 Lv = 3 + 000 + 1 2 46 = 3 + 023 m commit to user Elevasi Lengkung vertikal: Elevasi a = Elevasi PVI 8 - ½Lv x g8 = 1370 - ½ 46 x 8,06 = 1368,146 m Elevasi b = Elevasi PVI 8 - ¼ Lv x g8 + y = 1370 - ¼ 46 x 8,06 + 0,016 = 1369,057 m Elevasi c = Elevasi PVI 8 + Ev = 1370 + 0,066 = 1370,066 m Elevasi d = Elevasi PVI 8 + ¼ Lv x g9 + y = 1370 + ¼ 46 x 9,10 + 0,016 = 1371,074 m Elevasi e = Elevasi PVI 8 + ½Lv x g9 = 1370 + ½ 46 x 9,10 = 1372,116 m commit to user 3.4.2.9 PVI 9 Gambar 3.19 Lengkung Vertikal PV 9 Perhitungan Lv: 10 , 10 , 9 20 , 9 9 10 = − = − = ∆ g g Syarat keluwesan bentuk m V Lv 24 40 6 , 6 , = × = × = Syarat drainase m Lv 4 10 , 40 40 = × = ∆ × = Syarat kenyamanan m ik jam km t V Lv 33 , 33 det 3 40 = × = × = Pengurangan goncangan m V Lv 44 , 360 10 , 40 360 2 2 = × = ∆ × = Diambil Lv terbesar, yaitu = 33,33 m ~ dibulatkan 34 m PVI 9 g10=9,20 g9=9,10 a b c d e x x Lv commit to user m Lv Ev 004 , 800 34 1 , 800 = × = × ∆ = m Lv x y 001 , 34 200 34 1 , 200 2 4 1 2 = × × = × × ∆ = Stationing lengkung vertikal PVI 9 Sta A = Sta PVI 9 – 1 2 Lv = 3 + 500 - 1 2 34 = 3 + 483 m Sta B = Sta PVI 9 – 1 4 Lv = 3 + 500 - 1 4 34 = 3 + 491,5 m Sta C = Sta PVI 9 = 3 + 500 m Sta D = Sta PVI 9 + 1 4 Lv = 3 + 500 + 1 4 34 = 3 + 508,5 m Sta E = Sta PVI 9 + 1 2 Lv = 3 + 500 + 1 2 34 = 3 + 517 m commit to user Elevasi Lengkung vertikal: Elevasi a = Elevasi PVI 9 - ½Lv x g9 = 1416 - ½ 34 x 9,10 = 1414,436 m Elevasi b = Elevasi PVI 9 - ¼ Lv x g9 + y = 1416 - ¼ 34 x 9,10 + 0,001 = 1415,218 m Elevasi c = Elevasi PVI 9 + Ev = 1416 + 0,004 = 1416 m Elevasi d = Elevasi PVI 9 + ¼ Lv x g10 + y = 1416 + ¼ 34 x 9,20 + 0,001 = 1416,782 m Elevasi e = Elevasi PVI 9 + ½Lv x g10 = 1416 + ½ 34 x 9,20 = 1417,564 m commit to user 3.4.2.10 PVI 10 Gambar 3.20 Lengkung Vertikal PVI 10 Perhitungan Lv: 20 , 9 20 , 9 10 11 = − = − = ∆ g g Syarat keluwesan bentuk m V Lv 24 40 6 , 6 , = × = × = Syarat drainase m Lv 368 20 , 9 40 40 = × = ∆ × = Syarat kenyamanan m ik jam km t V Lv 33 , 33 det 3 40 = × = × = Pengurangan goncangan m V Lv 89 , 40 360 20 , 9 40 360 2 2 = × = ∆ × = Diambil Lv yang terbesar,yaitu = 40,89 m ~ dibulatkan 41 m a b c d e g 11 = 0 g 10 = 9,20 PVI 10 x x Lv commit to user m Lv Ev 472 , 800 41 20 , 9 800 = × = × ∆ = m Lv x y 118 , 41 200 41 20 , 9 200 2 4 1 2 = × × = × × ∆ = Stationing lengkung vertikal PVI 10 Sta A = Sta PVI 10 – 1 2 Lv = 3+625 - 1 2 41 = 3+604,5 m Sta B = Sta PVI 10 – 1 4 Lv = 3+625 - 1 4 41 = 3+614,75 m Sta C = Sta PVI 10 = 3+625m Sta D = Sta PVI 10 + 1 4 Lv = 3+625 + 1 4 41 = 3+635,25 m Sta E = Sta PVI 10 + 1 2 Lv = 3+625 + 1 2 41 = 3+645,5 m commit to user Elevasi Lengkung vertikal: Elevasi a = Elevasi PVI 10 - ½Lv x g10 = 1435 - ½ 41 x 9,20 = 1433,11m Elevasi b = Elevasi PVI 10 - ¼ Lv x g10 - y = 1435 - ¼ 41 x 9,20 - 0,118 = 1434,18 m Elevasi c = Elevasi PVI 10 - Ev = 1435 – 0,472 = 1434,53m Elevasi d = Elevasi PVI 10 − ¼ Lv x g11 - y = 1435 − ¼ 41 x 0 - 0,118 = 1434,88 m Elevasi e = Elevasi PVI 10 − ½Lv x g11 = 1435 − ½ 41 x 0 = 1435 m commit to user 3.4.2.11 PVI 11 PVI 11 Gambar 3.21 Lengkung Vertikal PVI 11 Perhitungan Lv: 5 , 7 5 , 7 11 12 = − = − = ∆ g g Syarat keluwesan bentuk m V Lv 24 40 6 , 6 , = × = × = Syarat drainase m Lv 300 5 , 7 40 40 = × = ∆ × = Syarat kenyamanan m ik jam km t V Lv 33 , 33 det 3 40 = × = × = Pengurangan goncangan m V Lv 33 , 33 360 5 , 7 40 360 2 2 = × = ∆ × = Diambil Lv yang terbesar,yaitu = 33,33 m ~ dibulatkan 34 m a b c d g 11 = 0 g 12 = 7,5 x x Lv commit to user m Lv Ev 319 , 800 34 5 , 7 800 = × = × ∆ = m Lv x y 080 , 34 200 34 5 , 7 200 2 4 1 2 = × × = × × ∆ = Stationing lengkung vertikal PVI 11 Sta A = Sta PVI 11 – 1 2 Lv = 3+750 - 1 2 34 = 3+733 m Sta B = Sta PVI 11 – 1 4 Lv = 3+750 - 1 4 34 = 3+741,5 m Sta C = Sta PVI 11 = 3+750m Sta D = Sta PVI 11 + 1 4 Lv = 3+750 + 1 4 34 = 3+758,5 m Sta E = Sta PVI 11 + 1 2 Lv = 3+750 + 1 2 34 = 3+767 m commit to user Elevasi Lengkung vertikal: Elevasi a = Elevasi PVI 11 - ½Lv x g11 = 1435 - ½ 34 x 0 = 1435,000 m Elevasi b = Elevasi PVI 11 - ¼ Lv x g11 + y = 1435 - ¼ 34x 0 + 0,080 = 1434,92 m Elevasi c = Elevasi PVI 11 + Ev = 1435 + 0,319 = 1435,319 m Elevasi d = Elevasi PVI 11 + ¼ Lv x g12 + y = 1435 + ¼ 34 x 7,5 + 0,080 = 1441,455 m Elevasi e = Elevasi PVI 11 + ½Lv x g12 = 1435 + ½ 34 x 7,5 = 1447,75 m commit to user 3.4.2.12 PVI 12 I . Gambar 3.22 Lengkng Vertikal PVI 12 Perhitungan Lv: 7 , 3 5 , 7 8 , 3 12 13 = − = − = ∆ g g Syarat keluwesan bentuk m V Lv 24 40 6 , 6 , = × = × = Syarat drainase m Lv 148 7 , 3 40 40 = × = ∆ × = Syarat kenyamanan m ik jam km t V Lv 33 , 33 det 3 40 = × = × = Pengurangan goncangan m V Lv 44 , 16 360 7 , 3 40 360 2 2 = × = ∆ × = Diambil Lv yang terbesar,yaitu = 33,33 m dibulatkan = 34 m a PVI 12 b c d e g 12 =7,5 g 13 =3,80 x x Lv commit to user m Lv Ev 157 , 800 34 7 , 3 800 = × = × ∆ = m Lv x y 039 , 34 200 34 7 , 3 200 2 4 1 2 = × × = × × ∆ = Stationing lengkung vertikal PVI 12 Sta A = Sta PVI 12 – 1 2 Lv = 3+950 - 1 2 34 = 3+933 m Sta B = Sta PVI 12 – 1 4 Lv = 3+950 - 1 4 34 = 3+941,5 m Sta C = Sta PVI 12 = 3+950 m Sta D = Sta PVI 12 + 1 4 Lv = 3+950 + 1 4 34 = 3+958,5 m Sta E = Sta PVI 12 + 1 2 Lv = 3+950 + 1 2 34 = 3+967 m commit to user Elevasi Lengkung vertikal: Elevasi a = Elevasi PVI 12 - ½Lv x g12 = 1450 - ½ 34 x 7,5 = 1437,25 m Elevasi b = Elevasi PVI 12 - ¼ Lv x g12 - y = 1450 - ¼ 34 x 7,5 - 0,039 = 1443,664 m Elevasi c = Elevasi PVI 12 - Ev = 1450 – 0,157 = 1449,843 m Elevasi d = Elevasi PVI 12 + ¼ Lv x g13 - y = 1450 + ¼ 34 x 3,8 - 0,039 = 1450,004 m Elevasi e = Elevasi PVI 12 + ½Lv x g13 = 1450 + ½ 34 x 3,8 = 1450,646 m commit to user 3.4.2.13 PVI 13 Gambar 3.23 Lengkung Vertikal PV 13 Perhitungan Lv: 6 8 , 3 8 , 9 13 14 = − = − = ∆ g g Syarat keluwesan bentuk m V Lv 24 40 6 , 6 , = × = × = Syarat drainase m Lv 240 00 , 6 40 40 = × = ∆ × = Syarat kenyamanan Pengurangan goncangan m V Lv 67 , 26 360 00 , 6 40 360 2 2 = × = ∆ × = PVI 13 g 14 =9,8 g 13 =3,8 a b c d e m ik jam km t V Lv 33 , 33 det 3 40 = × = × = x x Lv commit to user Diambil Lv terbesar, yaitu = 26,67 m dibulatkan = 27 m m Lv Ev 203 , 800 27 00 , 6 800 = × = × ∆ = m Lv x y 051 , 27 200 27 00 , 6 200 2 4 1 2 = × × = × × ∆ = Stationing lengkung vertikal PVI 13 Sta A = Sta PVI 13 – 1 2 Lv = 4+150 - 1 2 27 = 4 + 136,5 m Sta B = Sta PVI 13 – 1 4 Lv = 4+150 - 1 4 27 = 4 + 143,25m Sta C = Sta PVI 13 = 4+150m Sta D = Sta PVI 13 + 1 4 Lv = 4+150 + 1 4 27 = 4 + 156,75 m Sta E = Sta PVI 13 + 1 2 Lv = 4+150 + 1 2 27 = 4 +163,5 m commit to user Elevasi Lengkung vertikal: Elevasi a = Elevasi PVI 13 - ½Lv x g13 = 1457,6 - ½ 27 x 3,80 = 1457,09 m Elevasi b = Elevasi PVI 13 - ¼ Lv x g13 + y = 1457,6 - ¼ 27 x 3,80 +0,051 = 1457,29 m Elevasi c = Elevasi PVI 13 + Ev = 1457,6 + 0,203 = 1457,80 m Elevasi d = Elevasi PVI 13 + ¼ Lv x g14 + y = 1457,6 + ¼ 27 x 9,80 + 0,051 = 1458,31 m Elevasi e = Elevasi PVI 13 + ½Lv x g14 = 1457,6 + ½ 27 x 9,80 = 1458,92 m commit to user Tabel 3.5 Elevasi Tanah Asli dan Elevasi Tanah Rencana NO STA Elevasi Tanah Asli Elevasi Tanah Rencana NO STA Elevasi Tanah Asli Elevasi Tanah Rencana 1 0+000 1112.500 1112.500 b 1+364 1230.926 1234.055 2 0+050 1117.500 1116.750 25 c 1+375 1229.234 1234.460 3 0+100 1123.106 1121.000 d 2+398,25 1325.000 1318.430 4 0+150 1125.000 1125.250 e 2+416,5 1326.665 1319.942 5 0+200 1126.316 1129.500 46 2+450 1330.000 1323.360 6 0+250 1129.167 1133.750 47 2+500 1336.250 1327.600 a 0+273 1133.515 1035.705 48 2+550 1335.119 1331.840 b 0+286,5 1135.506 1036.831 49 2+600 1335.294 1336.080 7 c 0+300 1137.500 1038.196 50 2+650 1339.527 1340.320 d 0+313,5 1137.806 1039.349 51 2+700 1342.650 1344.560 e 0+327 1140.601 1040.054 52 2+750 1347.297 1348.693 8 0+350 1142.500 1142.917 53 2+800 1350.000 1353.040 9 0+400 1149.138 1147.833 54 2+850 1354.167 1357.271 10 0+450 1154.044 1152.750 55 2+900 1362.500 1361.520 11 0+500 1159.868 1157.667 56 2+950 1367.391 1365.760 12 0+550 1164.674 1162.583 a 2+977 1370.852 1368.146 13 0+600 1169.565 1167.500 b 2+988,5 1372.395 1369.057 14 0+650 1174.405 1172.417 57 c 3+000 1373.750 1370.066 15 0+700 1179.902 1177.333 d 3+011,5 1375.000 1371.074 16 0+750 1184.375 1182.250 e 3+023 1375.846 1372.116 17 0+800 1188.859 1187.167 58 3+050 1377.885 1374.600 a 0+813 1190.000 1188.448 59 3+100 1381.250 1379.200 b 0+856,5 1193.883 1192.959 60 3+150 1383.654 1383.800 18 c 0+900 1197.500 1196.058 61 3+200 1387.500 1388.391 d 0+943,5 1197.526 1199.158 62 3+250 1392.279 1393.000 e 0+987 1197.122 1201.785 63 3+300 1400.000 1397.600 19 1+000 1197.360 1202.491 64 3+350 1401.705 1402.200 a 1+013,5 1197.977 1203.243 65 3+400 1405.682 1406.791 b 1+056,75 1202.309 1205.387 66 3+450 1411.110 1411.382 20 c 1+100 1207.622 1208.934 a 3+483 1415.000 1414.436 d 1+143,25 1212.291 1212.481 b 3+491,5 1415.630 1415.218 e 1+186,5 1216.706 1216.494 67 c 3+500 1416.667 1416.000 21 1+200 1218.137 1217.818 d 3+508,5 1417.116 1416.782 22 1+250 1223.039 1222.727 e 3+517 1417.297 1417.564 23 1+300 1226.758 1227.636 68 3+550 1425.000 1425.218 24 1+350 1230.603 1232.545 69 3+600 1431.728 1434.431 a 1+353 1231.909 1232.840 a 3+604,5 1432.551 1433.110 commit to user Sambungan Tabel 3.5 Elevasi Tanah Asli dan Elevasi Tanah Rencana NO STA Elevasi Tanah Asli Elevasi Tanah Rencana b 3+614,75 1430.416 1434.180 70 c 3+625 1427.958 1434.530 d 3+635,25 1425.663 1434.880 e 3+645,5 1423.970 1435.000 71 3+650 1436.176 1434.431 72 3+700 1434.091 1434.431 a 3+733 1437.450 1435.000 b 3+741,5 1437.961 1434.920 73 c 3+750 1438.889 1435.319 d 3+758,5 1440.000 1441.455 e 3+767 1440.936 1447.750 74 3+800 1445.833 1441.365 75 3+850 1450.000 1445.381 76 3+900 1450.806 1449.401 a 3+933 1450.739 1437.250 b 3+941,5 1450.736 1443.664 77 c 3+950 1450.752 1449.843 d 3+958,5 1450.804 1450.004 e 3+967 1450.869 1450.646 78 4+000 1450.926 1453.942 79 4+050 1450.446 1455.480 80 4+100 1453.819 1456.991 a 4+136,5 1457.391 1457.090 b 4+143,25 1458.253 1457.290 81 c 4+150 1458.681 1457.800 d 4+156,75 1459.395 1458.310 e 4+163,5 1459.673 1458.920 82 4+200 1463.333 1467.167 83 4+250 1467.083 1472.241 84 4+300 1471.875 1472.250 85 4+350 1475.000 1477.333 86 4+400 1482.639 1482.417 87 4+450 1487.500 1487.500 commit to user 133

BAB IV PERENCANAAN TEBAL PERKERASAN

4.1 Data Perencanaan Tebal Perkerasan

• Tebal perkerasan untuk 2 lajur dan 2 arah • Pelaksanaan konstruksi jalan dimulai pada tahun 2011 • Jalan dibuka pada tahun 2012 • Masa konstruksi n 1 = 1 tahun, angka pertumbuhan lalu lintas i 1 = 2 • Umur rencana n 2 = 10 tahun, angka pertumbuhan lalu lintas i 2 = 6 • Jalan yang direncanakan adakah jalan kelas II jalan Arteri • Curah hujan diperkirakan 2500 – 3000 mm tahun Tabel 4.1 Nilai LHR S No Jenis kendaraan LHR S Kendaraan hari 2arah 1 Mobil 1420 2 Mikro Bus 587 3 Pick-UP 520 4 Truk 2 As 293 Sumber : Survey lalu lintas daerah Kalisoro Tawangmangu 24 Juni 2010