Prarancangan Pabrik Biodiesel dari Crude Palm Oil CPO dan Metanol Kapasitas 700.000 TonTahun
Hendri Susanto D 500 080 005
Universitas Muhammadiyah Surakarta
2.3.3. Neraca Panas
1. Neraca Panas Mixer
Tabel 12 Neraca Panas Mixer
Komponen Q Masuk
Q Keluar Arus
Arus Metanol
139.612,1809 139.612,1809
Air 13.328,8602
13.328,8602 Natrium hidroksida
6.293,7591 6.293,7591
TOTAL 159.234,8002
159.234,8002
2. Neraca Panas Heat Exchanger 1
Tabel 13 Neraca Panas Heat Exchanger 1
Komponen Masuk
Keluar METANOL
139.612,1809 832.418,5969
AIR 13.328,8602
79.488,1433 NATRIUM HIDROKSIDA
6.293,7591 64.547,4670
Panas Yang Dibutuhkan 770.521,1600
- TOTAL
929.755,9602 976.454,2073
3. Neraca Panas Heat Exchanger 2
Tabel 14 Neraca Panas Heat Exchanger 2
Komponen Masuk
Keluar TRIGISERIDA
165.164,6288 1.096.022,8455
AIR 1.088,0700
6.488,5718 Panas Yang Dibutuhkan
882.758,2200 -
TOTAL 1.049.010,9188
1.102.511,4173
Prarancangan Pabrik Biodiesel dari Crude Palm Oil CPO dan Metanol Kapasitas 700.000 TonTahun
Hendri Susanto D 500 080 005
Universitas Muhammadiyah Surakarta
4. Neraca Panas Reaktor 1
Tabel 15 Neraca Panas di Reaktor 1
Komponen Reaktor I
Q Masuk Q Keluar
METANOL 832.418,5969
528.585,8090 TRIGISERIDA
1.096.138,4159 295.957,3723
NATRIUM HIDROKSIDA 64.547,4670
64.547,4670 AIR
85.976,9714 85.976,9714
METIL ESTER -
1.715.244,9324 GLISEROL
- 368.054,8530
SUB TOTAL 2.079.081,4512
3.058.367,4052 PANAS REAKSI
97.248.686,6672 -
BEBAN PENDINGIN -
96.269.400,4569 TOTAL
99.327.768,1183 99.327.767,8621
5. Neraca Panas Reaktor 2
Tabel 16 Neraca Panas di Reaktor 2
Komponen Reaktor II
Q Masuk Q Keluar
METANOL 528.585,8090
424.075,6542 TRIGISERIDA
295.957,3723 20.717,0161
NATRIUM HIDROKSIDA 64.547,4670
64.547,4670 AIR
85.976,9714 85.976,9714
METIL ESTER 1.715.244,9324
2.305.242,1962 GLISEROL
368.054,8530 494.655,6388
SUB TOTAL 3.058.367,4052
3.395.214,9436 PANAS REAKSI
34.502.878,4624 -
BEBAN PENDINGIN -
34.166.030,9240 TOTAL
37.561.245,8676 37.561.245,8676
Prarancangan Pabrik Biodiesel dari Crude Palm Oil CPO dan Metanol Kapasitas 700.000 TonTahun
Hendri Susanto D 500 080 005
Universitas Muhammadiyah Surakarta
6. Neraca Panas Reaktor 3
Tabel 17 Neraca Panas di Reaktor 3
Komponen Reaktor II
Q Masuk Q Keluar
METANOL 424.075,6542
416.366,6256 TRIGISERIDA
20.717,0161 414,3403
NATRIUM HIDROKSIDA 64.547,4670
64.547,4670 AIR
85.976,9714 85.976,9714
METIL ESTER 2.305.242,1962
2.348.762,4245 GLISEROL
494.655,6388 503.994,1483
SUB TOTAL 3.395.214,9436
3.420.061,9771 PANAS REAKSI
2.544.458,6120 -
BEBAN PENDINGIN -
2.519.611,5785 TOTAL
5.939.673,5556 5.939.673,5556
7. Neraca Panas Dekanter 1
Tabel 18 Neraca Panas di Dekanter 1
Komponen Q Masuk
Q Keluar Arus 10
Arus 12 Arus 13
METANOL 416.366,6256
- 416.366,6256
TRIGISERIDA 414,3403
207,1702 207,1702
NATRIUM HIDROKSIDA 64.547,4670
- 64.547,4670
AIR 85.976,9714
- 85.976,9714
METIL ESTER 2.348.762,4245
1.174.381,2122 1.174.381,2122
GLISEROL 503.994,1483
- 503.994,1483
Sub total 3.420.061,9771
1.174.588,3824 2.245.473,5947
Total 3.420.061,9771
3.420.061,9771
Prarancangan Pabrik Biodiesel dari Crude Palm Oil CPO dan Metanol Kapasitas 700.000 TonTahun
Hendri Susanto D 500 080 005
Universitas Muhammadiyah Surakarta
8. Neraca Panas Dekanter 2
Tabel 19 Neraca Panas di Dekanter 2
Komponen Q Masuk
Q Keluar Arus 14
Arus 16 Arus 18
METANOL 416.366,6256
- 416.366,6256
TRIGISERIDA 207,1702
207,1702 -
NATRIUM HIDROKSIDA 64.547,4670
- 64.547,4670
AIR 2.544.935,0976
- 2.544.935,0976
METIL ESTER 1.174.381,2122
1.174.381,2122 -
GLISEROL 503.994,1483
- 503.994,1483
SUB TOTAL 4.704.431,7209
1.174.588,3824 3.529.843,3385
TOTAL 4.704.431,7209
4.704.431,7209
9. Neraca Panas Netralizer
Tabel 20 Neraca Panas Netralizer
Komponen Q Masuk
Q Keluar Arus 18
Arus 19 Arus 21
METANOL 416.366,6256
- 416.366,6256
TRIGISERIDA -
- -
NATRIUM HIDROKSIDA 64.547,4670
- -
AIR 2.544.935,0976
3.544,9350 2.548.480,0326
METIL ESTER -
- -
GLISEROL 503.994,1483
- 1.366.704,6401
HIDROGEN KLORIDA -
103.450,4389 -
NATRIUM HIDROKSIDA -
- 106.804,4199
SUB TOTAL 3.529.843,3385
106.995,3739 4.438.355,7182
PANAS REAKSI -
801.517,0058 -
TOTAL 4.438.355,7182
4.438.355,7182
Prarancangan Pabrik Biodiesel dari Crude Palm Oil CPO dan Metanol Kapasitas 700.000 TonTahun
Hendri Susanto D 500 080 005
Universitas Muhammadiyah Surakarta
10. Neraca Panas Flash Drum
Tabel 21 Neraca Panas Flash Drum
Komponen Q Masuk
Q Keluar Arus 23
Arus 24 Arus 25
METANOL 416.366,6256
198.109,7460 69.199,3377
AIR 156.875,6720
27.843,4016 332.995,3393
GLISEROL 1.366.704,6401
- 5.540.685,1759
SUB TOTAL 1.939.946,9377
225.953,1476 5.942.879,8529
BEBAN PANAS 4.228.886,0628
6.168.833,0006 TOTAL
6.168.833,0006 6.168.833,0006
Prarancangan Pabrik Biodiesel dari Crude Palm Oil CPO dan Metanol Kapasitas 700.000 TonTahun
Hendri Susanto D 500 080 005
Universitas Muhammadiyah Surakarta
2.4. Tata Letak Pabrik dan Peralatan