Double-click the Type lookup field.

Developing Resource Objects 11-63

3. Click OK.

The role is selected. Removing a Role from a Resource Object To remove a role from a resource object: 1. Select the desired role.

2. Click Delete.

The role is removed from the Object Authorizers tab. 11.9.4.2.3 Process Determination Rules Tab A resource object is a template for the resource that is provisioned to users or organizations. This template can be linked to multiple provisioning processes. Oracle Identity Manager uses process determination rules to select a provisioning process when a resource is requested or directly provisioned. Process determination rules provide the following criteria: ■ Which provisioning process to select when a resource is requested ■ Which provisioning process to select when a resource is provisioned directly Each provisioning process has a process determination rule. Each rule and process combination has a priority number that indicates the order in which Oracle Identity Manager will evaluate it. If the condition of a rule is false, Oracle Identity Manager evaluates the rule with the next highest priority. If a rule is true, Oracle Identity Manager executes the process associated with it. Adding a Process Determination Rule to a Resource Object To add a process determination rule to a resource object:

1. Click Add in the Provisioning Processes region, depending on the rule or process

combination you intend to create.

2. From the row that is displayed, double-click the Rules lookup field.

3. From the Lookup dialog box, select a rule, and assign it to the resource object only rules of Process Determination type are available for selection.

4. Click OK.

5. In the adjacent column, double-click the Processes lookup field.

6. From the Lookup dialog box, select a process, and assign it to the rule.

7. Click OK.

8. Enter a numeric value in the Priority field.

This determines the order in which Oracle Identity Manager evaluates the rule and process combination.

9. Click Save.

The rule and process combination is added to the resource object. Remove a Process Determination Rule From a Resource Object To remove a process determination rule from a resource object: 1. Select a rule and process combination.