BAB V RENCANA ANGGARAN BIAYA DAN
TIME SCHEDULE
5.1 Typical Potongan Melintang
Gambar 5.1 Potongan Melintang Jalan
5.2 Analisa Perhitungan Volume Pekerjaan
5.2.1. Penghitungan Volume Pekerjaan Tanah
1. Pembersihan Semak dan Pengupasan Tanah.
Luas =10 m xPanjang jalan – Bentang Jembatan – Lebar persimpangan
= 10 m x 3000 – 600 – 12 =
23.880 m²
2. Persiapan Badan Jalan m² .
Luas = Lebar lapis pondasi bawah x Panjang jalan – Bentang Jembatan
– Lebar persimpangan = 7,77 m x 3000 – 600 – 12
= 18.554,47 m²
commit to user
3. Galian Tanah Biasa m³
Contoh penghitungan : STA 0+100
2 : 1
- 2 - 4
2 :
1 - 2
- 4
STA 0+ 100
745,90 750
750,18 751,50
Lebar Perkerasan Jalan Bahu Jalan
Bahu Jalan Drainase
Drainase
2 x 3,5m 3 x 0.5m
3 x 0.5m 2 m
3 x 0.5m 0.5m
0.5m 0.5m
0.5m
745,83 745,75
745,75 750,128
750,102 750,06
750,525 750,9
751,125
745,83 745,75
745,75 1
2 3
4 5
6 7
8
Gambar 5.2 Tipical Cross Section STA 0+100 H1 = 750,12 - 745,75
= 4,37
H2 = 750,10 - 745,75 =
4,35 H3 = 750,06 - 745,83
= 4,23
H4 = 750 – 745,90 = 4,1
H5 = 750,52 – 745,83 = 4,69
H6 = 750,9 – 745,75 = 5,15
H7 = 751,12 – 745,75 = 5,37
commit to user
¤ Perhitungan Luas
2
77 ,
4 1
2 1
2 1
1 m
H H
Luas =
⎟ ⎠
⎞ ⎜
⎝ ⎛
× ×
=
2
9 ,
10 5
, 2
2 2
1 2
m H
H Luas
= ×
⎟ ⎠
⎞ ⎜
⎝ ⎛
+ =
2
58 ,
8 2
2 3
2 3
m H
H Luas
= ×
⎟ ⎠
⎞ ⎜
⎝ ⎛
+ =
2
57 ,
14 5
, 3
2 4
3 4
m H
H Luas
= ×
⎟ ⎠
⎞ ⎜
⎝ ⎛
+ =
2
38 ,
15 5
, 3
2 5
4 5
m H
H Luas
= ×
⎟ ⎠
⎞ ⎜
⎝ ⎛
+ =
2
84 ,
9 2
2 6
5 6
m H
H Luas
= ×
⎟ ⎠
⎞ ⎜
⎝ ⎛
+ =
2
15 ,
13 5
, 2
2 7
6 7
m H
H Luas
= ×
⎟ ⎠
⎞ ⎜
⎝ ⎛
+ =
2
21 ,
7 7
2 7
2 1
8 m
H H
Luas =
⎟ ⎠
⎞ ⎜
⎝ ⎛
Χ Χ
=
∑
=
2
m 84,4
Galian
Total
L
commit to user
4. Timbunan Tanah Biasa m³
Contoh penghitungan : STA 0 + 600
723,47 727
- 4 - 2
- 4 - 2
STA 0+ 600
724,87 722,07
Lebar Perkerasan Jalan Bahu Jalan
Bahu Jalan Drainase
2 x 3,5m 3 x 0.5m
2 m 2 m
0.5m 0.5m
Bahu Jalan Drainase
2 m 3 x 0.5m
0.5m 0.5m
2 :
1 726,93
726,85 726,93
726,85
724,24 723,96
722,993 722,721
2 3
4 5
6 1
Gambar 5.3 Tipical Cross Section STA 0 + 600 H1 = 726,85 – 722,72
= 4,13
H2 = 726,93 – 722,99 =
3,94 H3 = 727 – 723,47
= 3,53
H4 = 726,93 – 723,96 =
2,97 H5 = 726,85 – 724,24
= 2,61
commit to user
¤ Perhitungan Luas
2
26 ,
4 1
2 1
2 1
1 m
H H
Luas =
⎟ ⎠
⎞ ⎜
⎝ ⎛
× ×
=
2
07 ,
8 2
2 2
1 2
m H
H Luas
= ×
⎟ ⎠
⎞ ⎜
⎝ ⎛
+ =
2
07 ,
13 5
, 3
2 3
2 3
m H
H Luas
= ×
⎟ ⎠
⎞ ⎜
⎝ ⎛
+ =
2
37 ,
11 5
, 3
2 4
3 4
m H
H Luas
= ×
⎟ ⎠
⎞ ⎜
⎝ ⎛
+ =
2
58 ,
5 2
2 5
4 5
m H
H Luas
= ×
⎟ ⎠
⎞ ⎜
⎝ ⎛
+ =
2
7 ,
1 5
2 5
2 1
6 m
H H
Luas =
⎟ ⎠
⎞ ⎜
⎝ ⎛
× ×
=
∑
=
2
44,05m timbunan
L
commit to user
NO STA
JARAK M
LUAS M2 VOLUME M3
GALIAN TIMBUNAN
GALIAN TIMBUNAN
1 0+000
14,448 100
4985,25 2
0+100 85,257
100 5832,8
3 0+200
31,399 100
4630,1 4
0+300 61,203
100 8587,95
5 0+400
110,556 100
6 0+500
Sungai 100
7 0+600
41,329 100
268,05 2114,45
8 0+700
5,361 0,96
100 268,05
792,95 9
0+800 14,899
64,49 893,67018
10 0+864,49
12,816 13,33
172,98341 11
0+877,82 13,138
13,33 177,11571
12 0+891,15
13,436 53,34
4570,5713 13
0+944,49 157,939
64,51 8734,654
14 1+009
112,861 53,34
3135,0585 15
1+062,34 4,689
13,33 38,103805
16 1+075,67
4,408 1,028
13,33 128,41456
17 1+089
14,859 11
431,7555 18
1+100 63,642
100 7901,1
19 1+200
94,38 100
10399,15 20
1+300 113,603
100 10100,05
21 1+400
88,398 100
5010,85
commit to user
NO STA JARAK
M LUAS M2
VOLUME M3 GALIAN
TIMBUNAN GALIAN TIMBUNAN
22 1+500
11,819 100
23 1+600
Sungai 100
24 1+700
167,622 100
18889,85 25
1+800 210,175
100 10508,75
26 1+900
4,54 29,08
254,31914 27
1+929,08 12,951
14,17 331,68428
28 1+943,25
33,864 14,17
667,46368 29
1+957,42 60,344
53,34 5427,8517
30 2+010,76
143,175 40,43
5522,5965 31
2+051,19 130,018
53,34 4753,5808
32 2+104,53
48,219 14,17
621,1207 33
2+118,70 39,448
14,17 500,55525
34 2+132,87
31,202 67,13
1047,2951 35
2+200 9,93
100 1502,3
36 2+300
20,116 100
3329,4 37
2+400 46,472
100 6885,25
38 2+500
91,233 100
39 2+600
Sungai 100
40 2+700
12,979 100
6227,2 41
2+800 111,565
100 5578,25
42 2+900
47,975 100
4874,25 43
3+000 49,51
JUMLAH
82.544,237 73.550,557
commit to user
Total Volume Galian = 82.544,237 m
3
Total Volume Timbunan = 73.550,557 m
3
Contoh perhitungan Volume Galian STA 0+100 s.d 0+200 Jarak : 0+100-0+200 = 100 m
3
8 ,
5832 100
2 399
, 31
257 ,
85 2
200 100
. m
Jarak LuasSTA
LuasSTA V
= ×
+ =
= ×
+ +
+ =
5.2.2. Penghitungan Volume Pekerjaan Drainase