Penghitungan Volume Pekerjaan Drainase Penghitungan Volume Pekerjaan Dinding Penahan

commit to user Total Volume Galian = 82.544,237 m 3 Total Volume Timbunan = 73.550,557 m 3 Contoh perhitungan Volume Galian STA 0+100 s.d 0+200 Jarak : 0+100-0+200 = 100 m 3 8 , 5832 100 2 399 , 31 257 , 85 2 200 100 . m Jarak LuasSTA LuasSTA V = × + = = × + + + =

5.2.2. Penghitungan Volume Pekerjaan Drainase

1. Galian Saluran Gambar 5.4 Sket volume galian saluran 1 1 2 5 , 5 , 1 x Luas ⎥⎦ ⎤ ⎢⎣ ⎡ × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = 2 1 m = 1,5 m 0,5 m 1 m commit to user Volume galian saluran kanan dan kiri V = Luas xPanjang saluran drainase – panjang jembatan [ ] 3 4800 600 3000 2 m x = − = 2. Pasangan Batu Dengan Mortar I II I 0.2 m 0.2 m 1.5 m 0.3 m 1.5 m 0.2 m 0.8 m Gambar 5. 5 Sket volume pasangan batu ⎟⎟⎠ ⎞ ⎜⎜⎝ ⎛ ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + × × = 2 2 , 2 , 1 2 I uas L = 0,4 m 2 2 , 2 3 , 1 , × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = II uas L = 0,04 m 2 40 , 04 , + = total uas L = 0,44 m 2 Volume = 2 x luas x panjang drainase – panjang jembatan = 2 x 0,44 x 3000 – 600 = 2.112 m 3 0,5 m commit to user A A H H5+0,3 25 cm H6+0,3 3. Plesteran Gambar 5.6 Detail Pot A – A pada drainase Luas = 0,25 + 0,1 + 0,05 x 2400 x 2 = 1.920 m 2 4. Siaran Luas = 1,1 x 2400x2 = 5.280 m 2

5.2.3. Penghitungan Volume Pekerjaan Dinding Penahan

5.7 Sket volume pasangan batu pada dinding penahan 10 cm 5 cm Pasangan batu 25 cm commit to user 1. Galian Pondasi a. Ruas Kiri Sta 0+600 sd 0+700 • Sta 0+0600 H Sta 0+600 = 4,12m H5+0,3 = 1,12 m H6+0,3 = 0,98 m Luas galian pondasi = 1,12 x 0,98 = 10,97 m 2 • Sta 0+700 H Sta 0+700 = 0,57 m H5+0,3 = 0,41 m H6+0,3 = 0,39 m Luas galian pondasi = 0,41 x 0,39 = 0,159 m 2 • Volume Sta 0+600 sd 0+700 = 100 2 159 , 97 , 10 × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = 556,45 m³ a. Ruas Kanan Sta 0+600 sd 0+700 • Sta 0+600 H Sta 0+600 = 2,61 m H5+0,3 = 0,82 m H6+0,3 = 0,73 m Luas galian pondasi = 0,82 x 0,73 = 0,598 m 2 commit to user • Sta 0+700 H Sta 0+700 = 0 m H5+0,3 = 0,3 m H6+0,3 = 0,3 m Luas galian pondasi = 0,3 x 0,3 = 0,09 m 2 • Volume Sta 0+600 sd 0+700 = 100 2 09 , 598 , × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = 34,4 m³ Tabel 5.2 Perhitungan Volume Galian Pondasi pada Dinding Penahan Sta Jarak KIRI KANAN H H5+0,3 H6+0,3 Luas Volume H H5+0,3 H+0,3 Luas Volume 0+000 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 0+100 ‐ ‐ 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 0+200 ‐ ‐ 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 0+300 ‐ ‐ 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 0+400 ‐ ‐ 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 0+500 Sungai ‐ ‐ 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 0+600 4,124 1,125 0,987 1,111 2,61 0,822 0,735 0,604 100 63,704 30,209 0+700 0,57 0,414 0,395 0,164 100 28,754 11,535 0+800 1,867 0,673 0,611 0,412 0,985 0,497 0,464 0,231 64,49 39,989 21,017 0+864,49 1,766 0,653 0,594 0,388 0,74 0,448 0,423 0,190 13,33 40,544 18,989 0+877,82 1,914 0,683 0,619 0,423 0,743 0,449 0,424 0,190 13,33 43,592 19,013 0+891,15 2,024 0,705 0,637 0,449 0,743 0,449 0,424 0,190 53,34 294,168 205,782 0+944,49 11,119 2,524 2,153 5,434 9,203 2,141 1,834 3,926 64,51 461,561 318,532 1+009 9,024 2,105 1,804 3,797 6,916 1,683 1,453 2,445 53,34 204,537 122,256 STA JARAK KIRI KANAN H H5+0,3 H6+0,3 Luas Volume H H5+0,3 H+0,3 Luas Volume 1+062,34 1,322 0,564 0,520 0,294 13,33 23,265 1+075,67 0,624 0,425 0,404 0,172 13,33 8,581 1+089 11 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+100 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+200 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+300 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+400 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+500 ‐ ‐ 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+600 Sungai 100 258,217 227,022 1+700 10,798 2,460 2,100 5,164 10,022 2,304 1,970 4,540 100 598,853 533,938 1+800 12,647 2,829 2,408 6,813 11,921 2,684 2,287 6,138 100 340,636 306,916 1+900 29,08 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+929,08 ‐ ‐ 14,17 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+943,25 ‐ ‐ 14,17 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+957,42 ‐ ‐ STA JARAK KIRI KANAN H H5+0,3 H6+0,3 Luas Volume H H5+0,3 H+0,3 Luas Volume 53,34 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 2+010,76 ‐ ‐ 40,43 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 2+051,19 ‐ ‐ 53,34 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 2+104,53 ‐ ‐ 14,17 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 2+118,70 ‐ ‐ 14,17 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 2+132,87 ‐ ‐ 67,13 13,979 10,049 2+200 1,25 0,550 0,508 0,280 0,81 0,462 0,435 0,201 100 35,566 28,917 2+300 1,952 0,690 0,625 0,432 1,718 0,644 0,586 0,377 100 70,329 67,611 2+400 3,76 1,052 0,927 0,975 3,76 1,052 0,927 0,975 100 164,993 155,079 2+500 6,703 1,641 1,417 2,325 6,339 1,568 1,357 2,127 100 116,250 106,336 2+600 Sungai 100 12,005 16,732 2+700 1,038 0,508 0,473 0,240 1,522 0,604 0,554 0,335 100 173,671 160,534 2+800 8,2 1,940 1,667 3,233 7,64 1,828 1,573 2,876053 100 161,667 143,803 2+900 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 2+982 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ JUMLAH 3.154,861 JUMLAH 2.504,268 commit to user Volume total = 3.154,861 + 2.504,268 = 5.659,129 m³ 2. pasangan Batu untuk Dinding Penahan a. Ruas Kiri Sta 0+600 sd 0+700 • Sta 0+600 Lebar atas = 0,25 m H Sta 0+600 = 4,12 m H5+0,3 =1,12 m H6+0,3 = 0,98 m Luas pasangan batu = 98 , 12 , 1 12 , 4 2 98 , 25 , × + ⎭ ⎬ ⎫ ⎩ ⎨ ⎧ × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = 3,63 m 2 • Sta 0+ 700 Lebar atas = 0,25 m H Sta 0+700 = 0,57 m H5+0,3 = 0,41 m H6+0,3 = 0,39 m Luas pasangan batu = 39 , 41 , 57 , 2 39 , 25 , × + ⎭ ⎬ ⎫ ⎩ ⎨ ⎧ × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = 0,34 m 2 Volume = 100 2 34 , 63 , 3 × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = 198,61 m³ a. Ruas Kanan commit to user Sta 0+600 sd 0+700 • Sta 0+600 Lebar atas = 0,25 m H Sta 0+600 = 2,61 m H5+0,3 = 0,82 m H6+0,3 = 0,73 m Luas pasangan batu = 73 , 82 , 61 , 2 2 73 , 25 , × + ⎭ ⎬ ⎫ ⎩ ⎨ ⎧ × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = 1,87 m 2 • Sta 0+700 Lebar atas = 0,25 m H Sta 0+700 = 0 m H5+0,3 = 0,3m H6+0,3 = 0,3 m Luas pasangan batu = 3 , 3 , 2 3 , 25 , × + ⎭ ⎬ ⎫ ⎩ ⎨ ⎧ × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = 0,09 m 2 Volume = 100 2 09 , 87 , 1 × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = 98 m³ Tabel 5.3 Perhitungan Volume Pasangan Batu pada Dinding Penahan Sta Jarak KIRI KANAN H H5+0,3 H6+0,3 Luas Volume H H5+0,3 H+0,3 Luas Volume 0+000 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 0+100 ‐ ‐ 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 0+200 ‐ ‐ 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 0+300 ‐ ‐ 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 0+400 ‐ ‐ 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 0+500 Sungai ‐ ‐ 100 0+600 4,124 1,125 0,987 3,662 2,61 0,822 0,735 1,890 100 200,464 94,480 0+700 0,57 0,414 0,395 0,347 100 78,141 29,121 0+800 1,867 0,673 0,611 1,215 0,985 0,497 0,464 0,582 64,49 117,461 51,060 0+864,49 1,766 0,653 0,594 1,134 0,74 0,448 0,423 0,439 13,33 119,403 43,962 0+877,82 1,914 0,683 0,619 1,254 0,743 0,449 0,424 0,440 13,33 130,073 44,046 0+891,15 2,024 0,705 0,637 1,347 0,743 0,449 0,424 0,440 53,34 1007,087 697,736 0+944,49 11,119 2,524 2,153 18,795 9,203 2,141 1,834 13,514 64,51 1592,964 1092,361 1+009 9,024 2,105 1,804 13,065 6,916 1,683 1,453 8,333 53,34 693,379 416,647 STA JARAK KIRI KANAN H H5+0,3 H6+0,3 Luas Volume H H5+0,3 H+0,3 Luas Volume 1+062,34 1,322 0,564 0,520 0,803 13,33 58,927 1+075,67 0,624 0,425 0,404 0,376 13,33 18,783 1+089 11 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+100 ‐ ‐ 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+200 ‐ ‐ 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+300 ‐ ‐ 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+400 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+500 ‐ ‐ 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+600 Sungai ‐ ‐ 100 892,510 783,326 1+700 10,798 2,460 2,100 17,850 10,022 2,304 1,970 15,667 100 2073,486 1846,282 1+800 12,647 2,829 2,408 23,620 11,921 2,684 2,287 21,259 100 1180,977 1062,956 1+900 29,08 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+929,08 ‐ ‐ 14,17 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+943,25 ‐ ‐ 14,17 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 1+957,42 ‐ ‐ 53,34 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 2+010,76 ‐ ‐ STA JARAK KIRI KANAN H H5+0,3 H6+0,3 Luas Volume H H5+0,3 H+0,3 Luas Volume 40,43 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 2+051,19 ‐ ‐ 53,34 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 2+104,53 ‐ ‐ 14,17 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 2+118,70 ‐ ‐ 14,17 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 2+132,87 ‐ ‐ 67,13 37,677 23,920 2+200 1,25 0,550 0,508 0,754 0,81 0,462 0,435 0,478 100 101,980 78,708 2+300 1,952 0,690 0,625 1,286 1,718 0,644 0,586 1,096 100 223,652 214,138 2+400 3,76 1,052 0,927 3,187 3,76 1,052 0,927 3,187 100 554,975 520,275 2+500 6,703 1,641 1,417 7,913 6,339 1,568 1,357 7,219 100 395,626 360,926 2+600 Sungai 100 30,767 47,311 2+700 1,038 0,508 0,473 0,615 1,522 0,604 0,554 0,946 100 585,350 539,371 2+800 8,2 1,940 1,667 11,092 7,64 1,828 1,573 9,841 100 554,583 492,059 2+900 100 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ 3+000 ‐ ‐ ‐ ‐ ‐ ‐ ‐ ‐ JUMLAH 10.648,263 JUMLAH 8.438,687 commit to user 2 5 cm 3 0 cm 1 0 cm H - 0 ,3 Volume total = 10.648,263 + 8.438,687 = 19.086,95 m³ 3. Plesteran Gambar 5.8 Detail potongan A-A pada Dinding Penahan • Ruas kiri Luas=0,1+0,3+0,25x100+100+64,49+13,33+13,33+53,34+64,51+53,34+13,33+13,3 3+100+100+100+100 = 0,65 x 889 = 577,785 m 2 • Ruas kanan Luas=0,1+0,3+0,25x100+64.49+13,33+13,33+53,34+64,51+53,34+100+ 100+100+100+100+100 = 0,65 x 962,34 = 625,52 m 2 Luas total = 577,785 + 625,52 = 1.203,305 m 2 commit to user 3. Siaran • Ruas kiri Sta 0+600 sd 0+700 H Sta 0+600 = 4,12 m H – 0.3 Sta 0+600 = 3,82 m H Sta 0+700 = 0,57 m H – 0,3 Sta 0+700 = 0,27 m Luas = 100 2 27 , 82 , 3 × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = 204,5 m 2 • Ruas kanan Sta 0+600 sd 0+700 H Sta 0+600 = 2,61 m H – 0.3 Sta 0+000 = 2,31 m H Sta 0+700 = 0 m H – 0,3 Sta 0+100 = 0 m Luas = 100 2 31 , 2 × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = 115,5 m 2 commit to user Perhitungan selanjutnya dapat dilihat pada tabel 5.4 Tabel 5.4 Perhitungan Luas Siaran pada dinding Penahan STA JARAK KIRI KANAN H H-0,3 LUAS M2 H H-0,3 LUAS M2 0+000 100 0+100 ‐ ‐ ‐ ‐ 100 ‐ ‐ 0+200 ‐ ‐ ‐ ‐ 100 ‐ ‐ 0+300 ‐ ‐ ‐ ‐ 100 ‐ ‐ 0+400 ‐ ‐ ‐ ‐ 100 ‐ ‐ 0+500 Sungai 100 0+600 4,124 3,824 2,61 2,31 100 204,7 115,5 0+700 0,57 0,27 100 91,85 34,25 0+800 1,867 1,567 0,985 0,685 64,49 151,65 56,25 0+864,49 1,766 1,466 0,74 0,44 13,33 154 44,15 0+877,82 1,914 1,614 0,743 0,443 13,33 166,9 44,3 0+891,15 2,024 1,724 0,743 0,443 53,34 627,15 467,3 0+944,49 11,119 10,819 9,203 8,903 64,51 977,15 775,95 1+009 9,024 8,724 6,916 6,616 53,34 487,3 330,8 1+062,34 1,322 1,022 13,33 67,3 1+075,67 0,624 0,324 13,33 1+089 ‐ ‐ ‐ ‐ 11 ‐ ‐ 1+100 ‐ ‐ ‐ ‐ 100 ‐ ‐ 1+200 ‐ ‐ ‐ ‐ 100 ‐ ‐ commit to user 1+300 ‐ ‐ ‐ ‐ 100 ‐ ‐ STA JARAK KIRI KANAN H H-0,3 LUAS M2 H H-0,3 LUAS M2 1+400 ‐ ‐ ‐ ‐ 100 ‐ ‐ 1+500 ‐ ‐ ‐ ‐ 100 1+600 Sungai 100 486,1 1+700 10,798 10,498 10,022 9,722 100 1142,25 1067,15 1+800 12,647 12,347 11,921 11,621 100 617,35 581,05 1+900 ‐ ‐ ‐ ‐ 29,08 ‐ ‐ 1+929,08 ‐ ‐ ‐ ‐ 14,17 ‐ ‐ 1+943,25 ‐ ‐ ‐ ‐ 14,17 ‐ ‐ 1+957,42 ‐ ‐ ‐ ‐ 53,34 ‐ ‐ 2+010,76 ‐ ‐ ‐ ‐ 40,43 ‐ ‐ 2+051,19 ‐ ‐ ‐ ‐ 53,34 ‐ ‐ 2+104,53 ‐ ‐ ‐ ‐ 14,17 ‐ ‐ 2+118,70 ‐ ‐ ‐ ‐ 14,17 ‐ ‐ 2+132,87 ‐ ‐ ‐ ‐ 67,13 ‐ ‐ 2+200 1,25 0,95 0,81 0,51 100 130,1 96,4 2+300 1,952 1,652 1,718 1,418 100 255,6 243,9 2+400 3,76 3,46 3,76 3,46 100 493,15 474,95 2+500 6,703 6,403 6,339 6,039 100 320,15 301,95 2+600 Sungai 100 2+700 1,038 0,738 1,522 1,222 100 431,9 428,1 2+800 8,2 7,9 7,64 7,34 100 395 367 2+900 ‐ ‐ ‐ ‐ commit to user 100 ‐ ‐ 3+000 ‐ ‐ ‐ ‐ JUMLAH 6.13,5 JUMLAH 5.915,1 Volume total = 6.713,5 + 5.915,1 = 12.628,86 m³

5.2.4. Penghitungan Volume Pekerjaan Perkerasan

1. Lapis Pondasi Bawah Gambar 5.9. Sket lapis pondasi bawah L = 13 , 2 61 , 7 35 , 7 × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = 0,972 m² V = 0,972 x 2.400 = 2.333,76 m³ 2. Lapis Pondasi Atas 5.10. Sket lapis pondasi atas L = 20 , 2 45 , 7 15 , 7 × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = 1,46 m² V = 1,46 x 2.400 0,13m 0,13 m 7,35 m 0,13 m 0,20 m 0,20 m 7,15m 0,20 m commit to user = 3.504 m³ 3. Lapis Resap Pengikat prime Coat Luas = Lebar pondasi atas x Panjang jalan = 7,15 x 2.400 = 17.160 m² 4. Lapis Permukaan Gambar 5.11. Sket lapis permukaan L = 075 , 2 15 , 7 7 × ⎟ ⎠ ⎞ ⎜ ⎝ ⎛ + = 0,53 m² V = 0,53 x 3.000 = 1.590 m³

5.2.5. Penghitungan Volume Pekerjaan Pelengkap

1. Pekerjaan Pengecatan Marka Jalan Ukuran marka Gambar 5.12 Sket marka jalan a. Marka ditengah putus-putus Jumlah = Panjang jalan – Panjang Tikungan PI1+PI2 5 =3000 - 224,5+207,11 5 0,10m 0,10m 2 m 3 m 2 m 0,075m 7 m 0,075m 0,075m