BAB V RENCANA ANGGARAN BIAYA DAN
TIME SCHEDULE
5.1. Perhitungan Pekerjaan Tanah
5.1.1. Pekerjaan Galian Tanah Contoh penghitungan galian STA 2+300
Gambar 5.1 Tipical Cross Section STA 2+300 Elevasi Tanah Asli
= 550,068 m Elevasi Tanah Rencana
= 548,722 m
H
1
= 550,543 – 548,572
= 1,971 m H
2
= 550,368 – 548,572
= 1,796 m H
3
= 550,253 – 548,572
= 1,681 m H
4
= 550,143 – 548,652
= 1,491 m H
5
= 549,923 – 548,652
= 1,271 m H
6
= 549,813 – 548,572
= 1,241 m H
7
= 549,703 – 548,572
= 1,131 m H
8
= 549,593 – 548,572
= 1,021 m
-2 -2
-4 -4
550,068
548,722 548,652
548,572 550,543
549,593
Drainase 3x0,5 m
0,5 m
Bahu Jalan Lebar Perkerasan Jalan
2x3,5 m 2 m
Bahu Jalan 2 m
Drainase
0,5 m
3x0,5 m
1 2
3 4
5 6
7 8
550,143 550,253
550,368 549,923
549,813 549,703
,
548,652 548,572
STA 2+300
commit to user 112
Perhitungan Luas
2
563 ,
1,971 0,572
2 1
1 2
1 1
Luas
m H
a las
2
708 ,
4 5
, 2
2 796
, 1
1,971 5
, 2
2 2
1 2
Luas
m H
H
2
477 ,
3 2
2 681
, 1
796 ,
1 2
2 3
2 3
Luas
m H
H
2
551 ,
5 5
, 3
2 491
, 1
681 ,
1 5
, 3
2 4
3 4
Luas
m H
H
2
833 ,
4 5
, 3
2 271
, 1
491 ,
1 5
, 3
2 5
4 5
Luas
m H
H
2
512 ,
2 2
2 241
, 1
271 ,
1 2
2 6
5 6
Luas
m H
H
2
372 ,
2 5
, 2
2 131
, 1
241 ,
1 5
, 2
2 7
6 7
Luas
m H
H
2
324 ,
1,021 0,573
2 1
H8 alas
2 1
8 Luas
m
Luas Total Galian STA 2+300 = 24,34 m
2
commit to user 113
5.1.2. Pekerjaan Timbunan Tanah
Contoh penghitungan timbunan STA 0+000
Gambar 5.2 Tipical Cross Section STA 0+250
Elevasi Tanah Asli = 550,851 m
Elevasi Tanah Rencana = 552,937 m
H
1
= 552,787 – 551,455 m
= 1,332 m
2
H
2
= 552,867 – 551,156 m
= 1,711 m
2
H
3
= 552,937 – 550,851 m
= 2,086 m
2
H
4
= 552,867 – 550,552 m
= 2,315 m
2
H
5
= 552,787 – 550,253 m
= 2,534 m
2
-2 -2
-4 -4
STA 0+250
552,937 552,867
552,787
550,851 551,449
550,253
Drainase 3x0,5 m
0,5 m
Bahu Jalan Lebar Perkerasan Jalan
2x3,5 m 2 m
Bahu Jalan 2 m
Drainase
0,5 m
3x0,5 m
0,5 m Talud
0,5 m Talud
550,552 550,253
551,156 551,455
1 2
3 4
5 6
552,867 552,787
commit to user 114
Perhitungan Luas
2
m 0,734
1,327 1,107
2 1
1 2
1 1
H alas
Luas
2
m 3,038
2 2
1,711 1,327
2 2
2 1
2
H H
Luas
2
m 6,6447
5 ,
3 2
2,086 1,711
5 ,
3 2
3 2
3
H H
Luas
2
m 7,701
5 ,
3 2
2,315 2,086
5 ,
3 2
4 3
4
H H
Luas
2
m 4,849
2 2
2,534 2,315
2 2
5 4
5
H H
Luas
2 5
m 0,937
2,534 740
, 2
1 H
alas 2
1 6
Luas
Luas Total Timbunan STA 0+250 = 23,903 m
2
Untuk hasil penghitungan selanjutnya disajikan dalam tabel.
commit to user 115
Tabel. 5.1 Hasil perhitungan volume galian dan timbunan
STA
Luas m2 Volume m3
GALIAN TIMBUNAN GALIAN
TIMBUNAN 0+000
6.954 1.345
- 35.888
0+050 10.796
0.091 326.593
41.713 0+100
2.268 1.578
167.225 60.425
0+150 4.421
0.839 148.950
61.250 0+200
1.537 1.611
38.425 637.850
0+250 -
23.903 -
1210.800 0+300
- 24.529
- 726.075
0+350 -
4.514 -
350.625 0+400
- 9.511
2716.200 237.775
0+450 108.648
- 5868.625
- 0+500
126.097 -
6634.400 -
0+550 139.279
- 6002.925
- 0+600
100.838 -
4937.950 -
0+620,327 96.680
- 4904.500
- 0+634,327
99.500 -
4998.500 -
0+648,327 100.440
- 5137.250
- 0+704,327
105.050 -
5653.000 -
0+743,355 121.070
- 3026.750
821.000 Bersambung kehalaman selanjutnya
commit to user 116
Sambungan Tabel 5.1 Hasil perhitungan volume galian dan timbunan
STA
Luas m2 Volume m3
GALIAN TIMBUNAN
GALIAN TIMBUNAN
0+799,355 -
32.840 -
1766.250 0+813,355
- 37.810
- 2075.250
0+827,355 -
45.200 -
2086.200 0+850
- 38.248
- 1286.350
0+900 -
13.206 -
798.950 0+950
- 18.752
- 944.200
1+000 -
19.016 -
503.525 1+050
- 1.125
199.525 28.125
1+100 7.981
- 199.525
178.175 1+150
- 7.127
- 648.900
1+300 -
18.829 -
664.525 1+350
- 7.752
- 404.875
1+400 -
8.443 -
264.825 1+450
- 2.150
- 254.375
1+500 -
8.025 -
440.625 1+550
- 9.600
- 460.250
1+573,973 -
8.81 -
416.750 1+590,973
- 7.86
- 196.500
Bersambung kehalaman selanjutnya
commit to user 117
Sambungan Tabel 5.1 Hasil perhitungan volume galian dan timbunan
STA
Luas m2 Volume m3
GALIAN TIMBUNAN
GALIAN TIMBUNAN
1+607,973 -
11.23 -
964.000 1+647,973
- 27.33
- 1370.750
1+697,243 -
27.5 2.525
1551.500 1+737,243
0.101 34.56
8.525 1021.250
1+754,243 0.24
6.29 6.000
322.750 1+771,243
- 6.62
276.000 165.500
1+800 11.040
- 556.250
- 1+850
11.210 -
388.300 7.875
1+900 4.322
0.315 333.575
7.875 1+950
9.021 -
449.925 -
2+000 8.976
- 297.725
14.450 2+050
2.933 0.578
73.325 295.650
2+100 11.248
- 1289.475
2+150 40.331
- 1029.800
2+200 0.861
69.225 21.525
2+250 2.769
- 677.850
- 2+300
24.345 -
1212.175 -
2+350 24.142
- 681.175
13.950 2+370
3.105 0.558
77.625 13.950
Total Volume Galian = 56.070,543 m
3
Total Volume Timbunan = 25.973,100 m
3
commit to user 118
5.2. Pekerjaan Persiapan Badan Jalan Baru