Penulangan lapangan arah x Rekapitulasi Tulangan

commit to user T ugas Ak hir Perencanaan Struktur Gedung Sekolah 2 Lantai 66 BAB 5 Plat Lantai ATAP

5.7. Penulangan lapangan arah x

Mu = 435,99 kgm = 4,35599.10 6 Nmm Mn = φ Mu = 6 6 10 . 44 , 5 8 , 10 . 4,35599 = Nmm Rn = = 2 .dx b Mn = 2 6 95 . 1000 10 . 44 , 5 0,602 Nmm 2 m = 294 , 11 25 . 85 , 240 . 85 , = = c f fy ρ perlu = ⎟⎟⎠ ⎞ ⎜⎜⎝ ⎛ − − fy Rn . m 2 1 1 . m 1 = ⎟⎟⎠ ⎞ ⎜⎜⎝ ⎛ − − 240 602 , . 294 , 11 . 2 1 1 . 294 , 11 1 = 0,00255 ρ ρ max ρ ρ min , di pakai ρ perlu = 0,00255 As = ρ min . b . dx = 0,00255. 1000 . 95 = 242,25 mm 2 Digunakan tulangan ∅ 10 As = ¼ . π . 10 2 = 78,5 mm 2 S = perlu As b As. = 25 , 242 1000 . 5 , 78 = 324,045 ~ 330 mm Jarak maksimum = 2 x h = 2 x 120 = 240 mm n = s b = 240 1000 = 4,2 ∼ 5 commit to user As ada = 5. ¼ . π . 10 2 = 392,5 mm 2 As…...............OK ☺ Dipakai tulangan ∅ 10 – 240 mm Cek kapasitas lentur : a = b c f fy As ada . . 85 , . = 1000 . 25 . 85 , 240 . 5 , 392 = 4,433 mm M n = As ada .fy.d-a2 = 8,740.10 6 Nmm Mn ada Mn = 8,740.10 6 6 10 . 44 , 5 → OK ☺ 5.8. Penulangan lapangan arah y Mu = 435,99 kgm = 4,35599.10 6 Nmm Mn = φ Mu = 6 6 10 . 44 , 5 8 , 10 . 4,35599 = Nmm Rn = = 2 .dx b Mn = 2 6 95 . 1000 10 . 44 , 5 0,602 Nmm 2 m = 294 , 11 25 . 85 , 240 . 85 , = = c f fy ρ perlu = ⎟⎟⎠ ⎞ ⎜⎜⎝ ⎛ − − fy Rn . m 2 1 1 . m 1 = ⎟⎟⎠ ⎞ ⎜⎜⎝ ⎛ − − 240 602 , . 294 , 11 . 2 1 1 . 294 , 11 1 = 0,00255 ρ ρ max ρ ρ min , di pakai ρ perlu = 0,00255 As = ρ min . b . dx = 0,00255. 1000 . 95 = 242,25 mm 2 Digunakan tulangan ∅ 10 As = ¼ . π . 10 2 commit to user T ugas Ak hir Perencanaan Struktur Gedung Sekolah 2 Lantai 66 BAB 5 Plat Lantai ATAP = 78,5 mm 2 S = perlu As b As . = 25 , 242 1000 . 5 , 78 = 324,045 ~ 330 mm Jarak maksimum = 2 x h = 2 x 120 = 240 mm n = s b = 240 1000 = 4,2 ∼ 5 As ada = 5. ¼ . π . 10 2 = 392,5 mm 2 As…................... OK ☺ Dipakai tulangan ∅ 10 – 240 mm Cek kapasitas lentur : a = b c f fy As ada . . 85 , . = 1000 . 25 . 85 , 240 . 5 , 392 = 4,433 mm M n = As ada .fy.d-a2 = 8,740.10 6 Nmm Mn ada Mn = 8,740.10 6 6 10 . 44 , 5 → OK ☺

5.9. Rekapitulasi Tulangan

Dari perhitungan diatas diperoleh : Tulangan lapangan arah x ∅ 10 – 240 mm Tulangan lapangan arah y ∅ 10 – 240 mm Tulangan tumpuan arah x ∅ 10 – 120 mm Tulangan tumpuan arah y ∅ 10 – 120 mm commit to user Tabel 5.2. Penulangan Plat Lantai Tipe Plat Momen Tulangan Lapangan Tulangan Tumpuan Mlx kgm Mly kgm Mtx kgm Mty kgm Arah x mm Arah y mm Arah x mm Arah y mm A 323,98 386,69 - -877,9 ∅10–200 ∅10–240 ∅10–125 ∅10–125 B1 435,99 435,99 - 1058,84 - 1058,84 ∅10–200 ∅10–200 ∅10–125 ∅10–125 B2 404,85 327 - 937,28 - 856,42 ∅10–200 ∅10–200 ∅10–125 ∅10–125 B3 327 327 - 809,71 - 809,71 ∅10–200 ∅10–200 ∅10–125 ∅10–125 C1 205,78 73,96 - 459,75 - 307,53 ∅10–200 ∅10–200 ∅10–125 ∅10–125 C2 214,104 81,75 - 443,78 - 303,64 ∅10–200 ∅10–200 ∅10–125 ∅10–125 C3 330,88 151,82 - - 463,24 ∅10–200 ∅10–200 ∅10–125 ∅10–125

5.10. Perencanaan Plat Atap