Develop Project Develop Project Management Plan
4.5.1 Monitor and Control Project Work: Inputs
.1 Project Management Plan Described in the introduction to Section 4.3. .2 Work Performance Information Described in Section 4.4.3.7. .3 Rejected Change Requests Rejected change requests include the change requests, their supporting documentation, and their change review status showing a disposition of rejected change requests.4.5.2 Monitor and Control Project Work: Tools and Techniques
.1 Project Management Methodology The project management methodology defines a process that aids a project management team in monitoring and controlling the project work being performed in accordance with the project management plan. .2 Project Management Information System The project management information system PMIS, an automated system, is used by the project management team to monitor and control the execution of activities that are planned and scheduled in the project management plan. The PMIS is also used to create new forecasts as needed. .3 Earned Value Technique The earned value technique measures performance of the project as it moves from project initiation through project closure. The earned value management methodology also provides a means to forecast future performance based upon past performance. .4 Expert Judgment Expert judgment is used by the project management team to monitor and control project work.4.5.3 Monitor and Control Project Work: Outputs
.1 Recommended Corrective Actions Corrective actions are documented recommendations required to bring expected future project performance into conformance with the project management plan. .2 Recommended Preventive Actions Preventive actions are documented recommendations that reduce the probability of negative consequences associated with project risks. .3 Forecasts Forecasts include estimates or predictions of conditions and events in the project’s future, based on information and knowledge available at the time of the forecast. Forecasts are updated and reissued based on work performance information provided as the project is executed. This information is about the project’s past performance that could impact the project in the future; for example, estimate at completion and estimate to complete. .4 Recommended Defect Repair Some defects, which are found during the quality inspection and audit process, are recommended for correction. .5 Requested Changes Described in Section 4.4.3.2.4.6 Integrated Change Control
The Integrated Change Control process is performed from project inception through completion. Change control is necessary because projects seldom run exactly according to the project management plan. The project management plan, the project scope statement, and other deliverables must be maintained by carefully and continuously managing changes, either by rejecting changes or by approving changes so those approved changes are incorporated into a revised baseline. The Integrated Change Control process includes the following change management activities in differing levels of detail, based upon the completion of project execution: • Identifying that a change needs to occur or has occurred. • Influencing the factors that circumvent integrated change control so that only approved changes are implemented. • Reviewing and approving requested changes. • Managing the approved changes when and as they occur, by regulating the flow of requested changes. • Maintaining the integrity of baselines by releasing only approved changes for incorporation into project products or services, and maintaining their related configuration and planning documentation. • Reviewing and approving all recommended corrective and preventive actions. A Guide to the Project Management Body of Knowledge PMBOK ® Guide Third Edition 96 2004 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USAParts
» Project Characteristics What is a Project?
» Projects vs. Operational Work
» Projects and Strategic Planning
» Introduction, defines key terms and provides an overview for the
» Project Life Cycle and Organization, describes the environment in
» Project Management Processes for a Project, describes the five
» Project Integration Management, describes the processes and
» Project Scope Management, describes the processes involved in
» Project Procurement Management, describes the processes that
» Project Management Body of Knowledge
» Application Area Knowledge, Standards and Regulations
» Understanding the Project Environment
» General Management Knowledge and Skills
» Interpersonal Skills Areas of Expertise
» Project Management Office Project Management
» What is Project Management? The Project Life Cycle 2.2 Project Stakeholders
» Organizational Influences Index of /misc
» Characteristics of the Project Life Cycle
» Characteristics of Project Phases
» Project Life Cycle and Product Life Cycle Relationships
» Project Stakeholders Index of /misc
» Organizational Structure Organizational Influences
» The Role of the PMO in Organizational Structures
» Project Management System Organizational Influences
» Project Management Processes Index of /misc
» Initiating Process Group Project management Process Groups
» Planning Process Group Project management Process Groups
» Executing Process Project management Process Groups
» Monitoring and Controlling Process Group
» Process Interactions Index of /misc
» Project Management Process Mapping
» Develop Project Charter – developing the project charter that formally
» Develop Preliminary Project Scope Statement – developing the preliminary
» Develop Project Management Plan – documenting the actions necessary to
» Direct and Manage Project Execution – executing the work defined in the
» Monitor and Control Project Work – monitoring and controlling the
» Integrated Change Control – reviewing all change requests, approving
» Close Project – finalizing all activities across all of the Project Management
» Develop Project Charter: Inputs
» Develop Project Develop Project
» Develop Preliminary Project Scope Statement: Inputs
» Develop Preliminary Project Scope Statement: Tools and Techniques
» Develop Preliminary Project Scope Statement: Outputs
» Develop Project Develop Project Management Plan
» Develop Project Management Plan: Outputs
» Direct and Manage Project Execution: Inputs
» Monitor and Control Project Work: Inputs Monitor and Control Project Work: Tools and Techniques
» Monitor and Control Project Work: Outputs
» Close Project: Inputs Close Project
» Close Project: Close Project
» Close Project: Outputs Close Project
» Scope Control – controlling changes to the project scope.
» Scope Planning: Scope Planning
» Scope Planning: Tools and Techniques Scope Planning:
» Scope Definition: Inputs Scope Definition
» Scope Definition: Tools and Techniques Scope Definition: Outputs
» Create WBS: Tools and Techniques
» Create WBS: Outputs Create WBS
» Scope Control: Inputs Scope Control
» Scope Control: Tools and Techniques
» Scope Control: Outputs Scope Control
» Activity Definition – identifying the specific schedule activities that need to
» Activity Sequencing – identifying and documenting dependencies among schedule activities.
» Activity Duration Estimating – estimating the number of work periods that
» Schedule Development – analyzing activity sequences, durations, resource
» Schedule Control Index of /misc
» Activity Definition: Inputs Activity Definition
» Activity Definition: Tools and Techniques
» Activity Definition: Outputs Activity Definition
» Activity Sequencing: Inputs Activity Sequencing
» Activity Sequencing: Tools and Techniques
» Activity Resource Estimating: Inputs
» Activity Resource Estimating: Tools and Techniques
» Activity Resource Estimating: Outputs
» Activity Duration Estimating: Inputs
» Activity Duration Activity Duration
» Activity Duration Estimating: Outputs
» Schedule Development: Inputs Schedule Development
» Schedule Development: Tools and Techniques
» Schedule Development: Outputs Schedule Development
» Schedule Control: Outputs Schedule Control
» Cost Estimating – developing an approximation of the costs of the resources
» Cost Budgeting – aggregating the estimated costs of individual activities or
» Cost Control – influencing the factors that create cost variances and
» Cost Estimating: Cost Estimating
» Cost Estimating: Tools and Techniques
» Cost Estimating: Outputs Cost Estimating
» Cost Budgeting: Inputs Cost Budgeting
» Cost Budgeting: Cost Budgeting
» Cost Budgeting: Outputs Cost Budgeting
» Cost Control: Inputs Cost Control: Tools and Techniques
» Cost Control: Outputs Cost Control
» Quality Planning – identifying which quality standards are relevant to the
» Perform Quality Assurance – applying the planned, systematic quality
» Perform Quality Control – monitoring specific project results to determine
» Quality Planning: Inputs Quality Planning
» Quality Planning: Tools and Techniques
» Quality Planning: Quality Planning
» Perform Quality Assurance: Inputs Perform Quality
» Perform Quality Assurance: Outputs
» Perform Quality Control: Inputs
» Perform Quality Control: Tools and Techniques
» Perform Quality Control: Outputs
» Human Resource Planning – Identifying and documenting project roles,
» Acquire Project Team – Obtaining the human resources needed to complete
» Develop Project Team – Improving the competencies and interaction of team
» Manage Project Team – Tracking team member performance, providing
» Human Resource Planning: Inputs
» Human Resource Planning: Tools and Techniques
» Human Resource Planning: Outputs
» Acquire Project Team: Inputs
» Acquire Project Team: Tools and Techniques
» Acquire Project Team: Outputs
» Develop Project Team: Inputs Develop Project Team: Tools and Techniques
» Manage Project Team: Tools and Techniques
» Manage Project Team: Outputs
» Communications Planning: Inputs Communications Planning
» Communications Planning: Tools and Techniques
» Communications Planning: Outputs Communications Planning
» Information Distribution: Inputs Information Distribution
» Information Distribution: Tools and Techniques
» Information Distribution: Outputs Information Distribution
» Performance Reporting: Inputs Performance Reporting: Tools and Techniques
» Performance Reporting: Outputs Performance Reporting
» Manage Stakeholders: Inputs Manage Stakeholders: Tools and Techniques
» Manage Stakeholders: Outputs Manage Stakeholders
» Risk Management Planning: Inputs
» Risk Management Planning: Tools and Techniques
» Risk Management Planning: Outputs
» Risk Identification: Inputs Risk Identification: Tools and Techniques
» Qualitative Risk Analysis: Inputs
» Qualitative Risk Analysis: Tools and Techniques
» Qualitative Risk Analysis: Outputs
» Quantitative Risk Analysis: Inputs
» Quantitative Risk Analysis: Tools and Techniques
» Quantitative Risk Analysis: Outputs
» Risk Response Planning: Inputs
» Risk Response Planning: Tools and Techniques
» Risk Response Planning: Outputs
» Risk Monitoring and Control: Inputs Risk Monitoring and Control: Tools and Techniques
» Risk Monitoring and Control: Outputs
» Plan Purchases and Acquisitions – determining what to purchase or acquire
» Plan Contracting – documenting products, services, and results requirements
» Request Seller Responses – obtaining information, quotations, bids, offers,
» Select Sellers – reviewing offers, choosing among potential sellers, and
» Contract Administration – managing the contract and relationship between
» Contract Closure – completing and settling each contract, including the
» Plan Purchases and Acquisitions: Inputs
» Plan Purchases and Acquisitions: Tools and Techniques
» Cost-Plus-Fee CPF or Cost-Plus-Percentage of Cost CPPC. Seller
» Plan Purchases and Acquisitions: Outputs
» Plan Contracting: Inputs Plan Contracting
» Plan Contracting: Tools and Techniques
» Plan Contracting: Outputs Plan Contracting
» Request Seller Responses: Inputs
» Request Seller Responses: Tools and Techniques
» Request Seller Responses: Outputs
» Select Sellers: Inputs Select Sellers
» Select Sellers: Tools and Techniques
» Select Sellers: Outputs Select Sellers
» Contract Administration: Inputs Contract Administration: Tools and Techniques
» Contract Administration: Outputs Contract Administration
» Contract Closure: Inputs Contract Closure
» Contract Closure: Tools and Techniques
» - Introduction Changes Contract Closure: Outputs
» - Project Life Cycle and Organization Changes
» - Project Management Processes for a Project Changes
» - Project Integration Management Changes
» - Project Scope Management Changes
» - Project Time Management Changes - Project Cost Management Changes
» - Project Quality Management Changes
» - Project Human Resource Management Changes
» - Project Communications Management Changes
» - Project Risk Management Changes - Project Procurement Management Changes
» Introduction Contract Closure: Outputs
» Project Life Cycle and Organization
» Project Management Processes for a Project
» Project Integration Management Contract Closure: Outputs
» Project Scope Management Contract Closure: Outputs
» Project Time Management Contract Closure: Outputs
» Project Cost Management Contract Closure: Outputs
» Project Quality Management Contract Closure: Outputs
» Project Human Resource Management
» Project Communications Management Contract Closure: Outputs
Show more