Typical Potongan Melintang Analisa Perhitungan Harga Satuan Pekerjaan

commit to user 145

BAB V RENCANA ANGGARAN BIAYA DAN

TIME SCHEDULE

5.1 Typical Potongan Melintang

Gambar 5.1 Potongan Melintang Jalan

5.2 Analisa Perhitungan Volume Pekerjaan

5.2.1. Penghitungan Volume Pekerjaan Tanah

1. Pembersihan Semak dan Pengupasan Tanah. Luas = p. Damija x p. Jalan – p. Jembatan Total = 11 m x 3400,00 m – 60 m = 36.740,00 m² 2. Persiapan Badan Jalan m² . Luas = Lebar lapis pondasi bawah x Panjang jalan – p. Jembatan total = 8,15 m x 3400,00 m – 60 m = 27.650,00 m² commit to user 146 3. Galian Tanah Biasa m³ Contoh penghitungan : STA 0+350 STA 0+350 Bahu Jalan Bahu Jalan Lebar Perkerasan Jalan 1.5m 1.5m 2 x 3,5m Drainase 0.5m 3 x 0.5m 0.5m Drainase 0.5m 3 x 0.5m 0.5m 471.87 470.07 471.80 471.74 471.94 472.00 469.91 469.85 470.23 470.29 472.50 468.20 - 4 - 2 - 2 - 4 1 2 3 4 5 6 7 8 470.09 474.21 Gambar 5.2 Tipical Cross Section STA 0+350 H1 = 470,09 – 468,20 = 1, 89 H2 = 471,74 – 469, 89 = 1, 85 H3 = 471, 80 – 469, 91 = 1, 89 H4 = 471, 87 – 470,07 = 1, 80 H5 = 471,94 – 470,23 = 1,71 H6 = 472,00 – 470,29 = 1,71 H7 = 474,21 – 472,50 = 1,71 ¤ Perhitungan Luas 2 782 , 1 2 1 1 m H a Luas     2 675 , 4 5 , 2 2 2 1 2 m H H Luas           2 74 , 3 2 2 3 2 3 m H H Luas           commit to user 147 2 457 , 6 5 , 3 2 4 3 4 m H H Luas           2 143 , 6 5 , 3 2 5 4 5 m H H Luas           2 42 , 3 2 2 6 5 6 m H H Luas           2 275 , 4 5 , 2 2 7 6 7 m H H Luas           2 946 , 7 2 1 8 m H a Luas       2 m 32,438 Galian Total L 4. Timbunan Tanah Biasa m³ Contoh penghitungan : STA 0 + 250 STA 0+250 Bahu Jalan Drainase 0.5m 3 x 0.5m 0.5m 1.5m Lebar Perkerasan Jalan 2 x 3,5m Bahu Jalan 1.5m Drainase 0.5m 3 x 0.5m 0.5m 468.29 465.95 468.22 468.16 468.36 468.42 466.11 468.25 465.79 463.39 - 4 - 4 - 2 - 2 1 2 3 4 5 6 Talud Talud Gambar 5.3 Tipical Cross Section STA 0 + 250 commit to user 148 H1 = 468,42 – 468,25 = 0,17 H2 = 468,36 – 466,11 = 2,25 H3 = 468,29 –465,95 = 2,34 H4 = 468,22 – 465,79 = 2,43 H5 = 468,16 – 463,39 = 4,77 ¤ Perhitungan Luas 2 0072 , 1 2 1 2 1 1 m H H Luas           2 42 , 2 2 2 2 1 2 m H H Luas           2 033 , 8 5 , 3 2 3 2 3 m H H Luas           2 8 34 , 8 5 , 3 2 4 3 4 m H H Luas           2 20 , 7 2 2 5 4 5 m H H Luas           2 88 6 , 5 5 2 5 2 1 6 m H H Luas             2 m 21,526 Timbunan Ltotal Untuk hasil penghitungan selanjutnya disajikan dalam Tabel 5.1 commit to user 149 Tabel. 5.1 Hasil perhitungan volume galian dan timbunan NO STA JARAK LUAS m ² VOLUME m ³ m GALIAN TIMBUNAN GALIAN TIMBUNAN 1 0+000 1,127 50 66,220 6,533 2 0+050 1,522 0,261 50 38,050 33,733 3 0+100 1,088 50 31,720 27,200 4 0+150 1,269 50 31,720 189,815 5 0+200 7,593 50 727,975 6 0+250 21,526 50 6437,423 7 0+300 235,971 50 800,075 5899,263 8 0+350 32,003 50 1678,288 9 0+400 35,129 50 1113,760 10 0+450 9,422 50 239,635 90,533 11 0+500 0,164 3,621 50 4,088 501,248 12 0+550 16,429 50 1119,898 13 0+600 28,367 50 1676,223 14 0+650 38,682 50 815,130 967,040 15 0+700 32,605 50 1351,108 16 0+750 21,439 50 701,993 17 0+800 6,641 19,86 106,734 18 0+819,86 4,108 29,2 59,977 16,914 commit to user 150 19 0+849,06 1,159 0,94 1,582 20 0+850 2,208 28,26 188,486 31,202 21 0+878,26 13,339 21,74 144,999 103,010 22 0+900 9,477 50 502,913 23 0+919,86 10,640 50 785,873 24 0+950 20,795 50 1402,383 25 1+000 35,300 50 2088,683 26 1+050 48,247 1,24 57,497 27 1+051,24 44,491 41,59 1756,980 28 1+092,83 40,000 7,17 135,367 143,400 29 1+100 37,759 22,03 874,351 30 1+122,03 41,619 27,97 1118,565 31 1+150 38,364 1,24 56,980 32 1+151,24 53,539 48,76 1359,707 6,997 33 1+200 2,232 0,287 50 81,285 20,163 34 1+250 1,019 0,520 50 31,090 28,025 35 1+300 0,225 0,602 50 49,713 25,613 36 1+350 1,764 0,423 50 47,045 95,375 37 1+400 0,118 3,392 50 2,948 361,700 38 1+450 11,076 commit to user 151 50 479,910 276,900 39 1+500 19,196 50 593,328 40 1+550 4,537 50 178,120 10,133 41 1+600 2,588 0,405 50 363,728 10,133 42 1+650 11,961 7,85 86,810 43 1+657,85 10,156 42,15 214,042 228,622 44 1+700 10,848 3,35 37,100 45 1+703,35 11,301 43,3 338,931 46 1+746,65 4,354 3,35 12,623 47 1+750 3,182 39,96 36,136 82,737 48 1+789,96 1,809 0,959 10,04 282,735 4,814 49 1+800 54,513 50 1367,778 17,965 50 1+850 0,198 0,719 50 22,690 29,290 51 1+900 0,710 0,453 20,1 9,803 8,639 52 1+920,10 0,266 0,407 29,9 28,360 13,068 53 1+950 1,631 0,468 13,96 27,140 21,111 54 1+963,96 2,257 2,557 36,04 94,956 47,933 55 2+000 3,013 0,103 6,71 14,532 2,600 56 2+006,71 1,319 0,672 43,29 118,238 14,545 57 2+050 4,144 2,2 8,965 commit to user 152 58 2+052,20 4,006 47,8 98,697 153,080 59 2+100 0,124 6,405 50 7,895 730,475 60 2+150 0,192 22,814 50 11,030 946,750 61 2+200 0,249 15,056 50 10,300 924,775 62 2+250 0,163 21,935 50 11,425 572,313 63 2+300 0,294 0,958 50 107,675 23,938 64 2+350 4,013 50 104,993 641,675 65 2+400 0,187 25,667 50 11,268 1059,475 66 2+450 0,264 16,712 50 12,183 939,723 67 2+500 0,223 20,877 50 10,408 891,523 68 2+550 0,193 14,784 50 4,825 923,725 69 2+600 22,165 17,26 1,143 372,013 70 2+617,26 0,132 20,942 32,74 5,988 392,242 71 2+650 0,233 3,019 1,97 0,360 5,040 72 2+651,97 0,132 2,098 34,72 617,370 36,413 73 2+686,69 35,431 13,31 524,885 74 2+700 43,440 21,41 467,278 93,273 75 2+721,41 0,210 8,713 28,59 6,234 369,060 76 2+750 0,226 17,104 50 11,913 918,663 77 2+800 0,251 19,642 commit to user 153 50 9,440 985,978 78 2+850 0,127 19,797 50 6,480 1002,650 79 2+900 0,132 20,309 13,51 1,787 258,669 80 2+913,51 0,132 17,984 34,71 6,359 469,036 81 2+948,22 0,234 9,042 1,78 0,379 16,095 82 2+950 0,192 9,042 32,95 5,519 334,197 83 2+982,95 0,143 11,243 17,05 2,302 197,513 84 3+000 0,127 11,926 17,67 3,649 186,308 85 3+017,67 0,286 9,162 32,33 62,656 155,958 86 3+050 3,590 0,486 50 95,503 309,993 87 3+100 0,230 11,914 50 5,753 1348,393 88 3+150 42,022 50 503,550 1050,550 89 3+200 20,142 50 503,550 150,548 90 3+250 6,022 50 5,775 394,748 91 3+300 0,231 9,768 50 11,530 630,875 92 3+350 0,230 15,467 50 63,173 394,385 93 3+400 2,297 0,308 TOTAL 18369,571 40172,878 commit to user 154 NO STA JARAK LUAS m ² VOLUME m ³ m GALIAN TIMBUNAN GALIAN TIMBUNAN 1 0+110 0,882 10 5,968 2 0+130 0,311 10 2,218 3 0+150 0,132 10 0,678 5,333 4 0+170 0,136 0,934 10 1,829 28,654 5 0+190 0,230 4,797 10 161,786 23,983 6 1+160 32,127 10 236,019 7 1+180 15,077 10 93,259 8 1+200 3,575 10 48,620 9 1+220 6,149 10 36,154 2,484 10 1+240 1,082 0,497 10 21,037 4,039 11 1+560 3,126 0,311 10 27,434 3,926 12 1+580 2,361 0,474 10 27,631 3,596 13 1+600 3,165 0,245 10 74,113 1,225 14 1+620 11,658 10 112,376 15 1+640 10,818 10 72,170 16 2+010 3,616 10 38,872 17 2+030 4,158 10 38,564 18 2+050 3,555 10 23,813 1,817 19 2+070 1,208 0,363 commit to user 155 10 6,039 12,102 20 2+090 2,057 10 7,038 14,035 21 2+310 1,408 0,750 10 28,305 3,750 22 2+330 4,253 10 39,217 23 2+350 3,590 10 18,313 6,876 24 2+370 0,073 1,375 10 1,308 124,011 25 2+390 0,189 23,427 10 1,924 194,555 26 2+560 0,196 15,484 10 1,657 171,265 27 2+580 0,136 18,769 10 1,357 203,443 28 2+600 0,136 21,920 10 1,860 212,806 29 2+620 0,236 20,642 10 2,363 157,736 30 2+640 0,236 10,906 10 2,346 109,610 31 3+010 0,233 11,016 10 1,165 75,111 32 3+030 4,006 10 19,227 22,113 33 3+050 3,845 0,417 10 29,712 4,638 34 3+070 2,097 0,511 10 11,701 30,116 35 3+090 0,243 5,513 TOTAL 1187,879 1425,401 commit to user 156 Total Volume Galian = 19.557,45 m 3 Total Volume Timbunan = 41.598,28 m 3 Contoh perhitungan Volume Galian STA 0+400 s.d 0+450 Jarak : 0+400 – 0+450 = 50 m Jarak LuasSTA LuasSTA V      2 450 .. 400 .. = 50 2 9,422 5,129 3   = 1113,775 m 3 Contoh perhitungan Volume Timbunan STA 0+250 s.d 0+300 Jarak : 0+250 – 0+300 = 50 m Jarak LuasSTA LuasSTA V      2 300 .. 250 .. = 50 2 971 , 235 526 , 21   = 6437,425 m 3

5.2.2. Penghitungan Volume Pekerjaan Drainase

1. Galian Saluran Gambar 5.4 Sket Volume galian saluran 1,5 m 0,5 m 1 m commit to user 157                1 2 5 , 5 , 1 Luas 2 1 m      2 2 tan 1 tan .      jemba jemba p jalan Panjang Luas V   3 00 , 6680 2 60 00 , 3400 1 m x     2. Pasangan Batu Dengan Mortar I II I 0.2 m 0.2 m 1.5 m 0.3 m 1.5 m 0.2 m 0.8 m Gambar 5. 5 Sket volume pasangan batu                 2 2 , 2 , 1 2 I uas L = 0,4 m 2 2 , 2 3 , 1 ,          II uas L = 0,04 m 2 40 , 04 ,   total uas L = 0,44 m 2 Volume = 2 x luas x panjang Jalan – p. Jemb. total = 2 x 0,44 x 3400,00 -60 = 2939,2 m 3 0,5 m commit to user 158 A A H H5+0,3 25 cm H6+0,3 3. Plesteran Gambar 5.6 Detail Plesteran pada Potongan A-A Luas = 0,25 + 0,1 + 0,05 x 3400,00 – 60 x 2 = 2672 m 2 4. Siaran Luas = Lebar saluran drainase x p.jalan – p.jembatanx 2 = 2 x 3400,00 - 60 x 2 = 13360 m 2

5.2.3. Penghitungan Volume Pekerjaan Dinding Penahan

5.7 Sket volume pasangan batu pada dinding penahan 10 cm 5 cm Pasangan batu 25 cm Plesteran commit to user 159 1. Galian Pondasi a. Ruas Kiri Sta 0+200 sd 0+250  Sta 0+200 H Sta 0+200 = 0,9458 m H5+0,3 = 0,489 m H6+0,3 = 0,457 m Luas galian pondasi = 0,489 x 0,457 = 0,223 m 2  Sta 0+250 H Sta 0+200 = 2,0822 m H5+0,3 = 0,716 m H6+0,3 = 0,647 m Luas galian pondasi = 0,716 x = 0,647 = 0,463 m 2  Volume 0+200 sd 0+250 = 50 2 0,463 0,223         = 17,15 m a. Ruas Kanan Sta 0+200 sd 0+250  Sta 0+200 H Sta 0+200 = 1,0763 m H5+0,3 = 0,515 m H6+0,3 = 0,479 m Luas galian pondasi = 0,515 x 0,479 = 0,247 m 2  Sta 0+250 H Sta 0+250 = 2,3402 m H5+0,3 = 0,768 m H6+0,3 = 0,690 m Luas galian pondasi = 0,768 x 0,690 = 0,529 m 2  Volume Sta 0+200 sd 0+250 = 50 2 0,529 0,247         = 19,40 m 3 commit to user 160 Perhitungan selanjutnya dapat dilihat pada tabel 5.2 Tabel 5.2 Perhitungan Volume Galian Pondasi pada Dinding Penahan commit to user 161 Volume galian dinding penahan Kiri = 813,703 m³ Volume galian dinding penahan Kanan = 531,934 m³ Volume Total galian dinding penahan = 813,703 + 531,934 = 1.345,637 m³ 2. Pasangan Batu untuk Dinding Penahan a. Ruas Kiri Sta Sta 0+200 sd 0+250  Sta 0+200 Lebar atas = 0,25 m H Sta 0+200 = 0,946 m H5+0,3 = 0,489 m H6+0,3 = 0,456 m Luas pasangan batu =   0,456 0,489 946 , 2 0,456 25 ,                 = 0,557 m 2  Sta 0+250 Lebar atas = 0,25 m H Sta 0+250 = 2,082 m H5+0,3 = 0,716 m H6+0,3 = 0,647 m Luas pasangan batu =   0,647 x 0,716 82 , 2 2 0,647 25 ,                = 1,397 m 2 Volume = 50 2 397 , 1 557 ,         = 48, 85 m³ commit to user 162 a. Ruas Kanan Sta Sta 0+200 sd 0+250  Sta 0+200 Lebar atas = 0,25 m H Sta 0+200 = 1,076 m H5+0,3 = 0,515 m H6+0,3 = 0,479 m Luas pasangan batu =   0,479 515 , 076 , 1 2 0,479 25 ,                 = 0,639 m 2  Sta 0+250 Lebar atas = 0,25 m H Sta 0+250 = 2,340 m H5+0,3 = 0,768 m H6+0,3 = 0,690 m Luas pasangan batu =   690 , 768 , 340 , 2 2 690 , 25 ,                 = 1,597 m 2 Volume = 50 2 597 , 1 0,639         = 55,90 m 3 commit to user 163 Perhitungan selanjutnya dapat dilihat pada tabel 5.3 Tabel 5.3 Perhitungan Volume Pasangan Batu pada Dinding Penahan commit to user 164 25 c m 3 0 c m 1 0 c m H - 0 ,3 Volume pasangan batu pada dinding penahan kiri = 1.786,323 m 3 Volume pasangan batu pada dinding penahan kanan = 883,673 m 3 Volume Total pasangan batu pada dinding penahan = 1.786,323 + 883,673 = 2.669,996 m 3 3. Plesteran Gambar 5.8 Detail plesteran pada Dinding Penahan  Ruas kiri Luas = 0,1+0,3+0,25x p.dinding penahan kiri = 0,1+0,3+0,25 x 50+50+50+50+12,457+12,243+35,757+6,727+26,7+16,573+7,427+ 50+50+50+50+50+50+50+14,5+17,905+50+50+50+50+50+50+50+ 14+5,63+8,77+41,23+10,37+39,63+50+50+50+50+50 = 0,65 x 1419,919 = 922,947 m 2  Ruas kanan Luas = 0,1+0,3+0,25x p.dinding penahan kanan = 0,1+0,3+0,25x 50+50+50+50+6,727+26,7+50+50+50+50+50+50+ 14,5+17,905+50+50+50+50+50+50+50+50+8,77+14+5,63+41,23+10,37+ 39,63+50+33,178+16,822+50+50+50 = 0,65 x 1285,462 = 835,550 m 2 Luas total = 922,947 + 835,550 = 1.758,497 m 2 commit to user 165 3. Siaran  Ruas kiri Sta 0+200 sd 0+250 H Sta 0+200 = 0,946 m H Sta 0+200 – 0.3 = 0,646 m H Sta 0+250 = 2,082 m H Sta 0+250 – 0,3 = 1,782 m Luas = 50 2 82 , 2 946 ,         = 75,70 m 2  Ruas kanan Sta 0+200 sd 0+250 H Sta 0+200 = 1,076 m H Sta 0+200 – 0.3 = 0,776 m H Sta 0+250 = 2,340 m H Sta 0+250 – 0,3 = 2,040 m Luas = 50 2 340 , 2 076 , 1         = 85,4 m 2 Perhitungan selanjutnya dapat dilihat pada tabel 5.4 commit to user 166 Tabel 5.4 Perhitungan Luas Siaran pada dinding Penahan STA Jarak KIRI KANAN H H - 0,3 Luas H H - 0,3 Luas 0+050 0,160 -0,140 50 -1,675 -7,333 0+100 0,373 0,073 0,307 0,007 50 17,975 19,575 0+200 0,946 0,646 1,076 0,776 50 60,695 70,413 0+250 2,082 1,782 2,340 2,040 50 115,700 131,983 0+300 3,146 2,846 3,539 3,239 0+500 0,940 0,640 0,355 0,055 0+550 2,195 1,895 50 0+600 3,289 50 0+650 4,225 0+850 0,476 0,176 0,544 0,244 50 24,430 30,100 0+900 1,101 0,801 1,260 0,960 19,86 15,889 21,656 0+919,86 1,099 0,799 1,521 1,221 19,86 25,108 9,146 0+950 2,030 1,730 7,427 46,414 -2,228 1+051,24 11,069 10,769 1+092,83 4,449 4,149 1+300 0,386 0,086 50 15,545 1+400 0,836 0,536 0,412 50 45,375 1+450 1,579 1,279 1,071 commit to user 167 1+700 1,552 1,252 1,057 3,305 4,194 1+703,305 1,586 1,286 1,103 0,803 50 48,383 24,590 1+746,65 0,949 0,649 0,480 0,180 3,35 1,981 0,428 1+750 0,833 0,533 0,375 0,075 1+789,96 0,246 -0,054 0,164 -0,136 14,5 0,734 -0,986 1+850 0,455 0,155 50 4,560 1+900 0,327 0,027 2+100 1,135 0,674 0,374 50 49,615 2+150 2,733 1,911 1,611 50 62,380 2+200 2,173 1,184 0,884 2+250 2,596 2,296 1,908 1,608 50 65,393 32,688 2+300 0,620 0,320 0,000 -0,300 0,000 0,000 2+400 2,958 2,658 2,145 1,845 8,77 20,639 12,446 2+450 2,349 2,049 1,293 0,993 50 109,503 59,838 2+500 2,631 2,331 1,700 1,400 50 101,658 59,180 2+550 2,035 1,735 1,267 0,967 0,000 0,000 2+617,26 2,430 2,130 1,901 1,601 32,74 46,579 24,478 2+650 1,016 0,716 0,194 -0,106 1,97 0,409 -0,400 2+651,97 -0,300 0,000 -0,300 0,000 2+721,41 -0,300 1,084 2+750 2,134 1,834 1,557 1,257 commit to user 168 50 99,735 65,605 2+600 2,455 2,155 1,667 1,367 50 110,520 66,413 2+850 2,565 2,265 1,589 1,289 50 116,128 63,868 2+900 2,680 2,380 1,565 1,265 13,51 29,586 17,277 2+913,51 2,300 2,000 1,592 1,292 34,71 58,922 28,815 2+948,22 1,695 1,395 0,668 0,368 1,780 2,488 0,602 2+950 1,700 1,400 0,608 0,308 32,950 47,405 15,183 2+982,95 1,777 1,477 0,913 0,613 17,050 25,792 10,705 3+000 1,849 1,549 0,942 0,642 17,67 26,241 8,376 3+017,67 1,722 1,422 0,606 0,306 82,330 120,062 36,390 3+100 1,795 1,495 0,878 0,578 50 137,500 89,133 3+150 4,305 4,005 3,287 2,987 100 249,885 157,185 3+250 1,293 0,993 0,457 0,157 50 57,898 16,513 3+300 1,623 1,323 0,804 0,504 50 76,505 39,580 3+350 2,037 1,737 1,379 1,079 TOTAL 1125,456 TOTAL 810,729 commit to user 169 STA Jarak KIRI KANAN H H - 0,3 Luas H H - 0,3 Luas 0+110 0,003 0,237 -0,063 50 0+170 0,569 0,269 10,195 1,638 20 0+190 1,051 0,751 0,464 0,164 2+090 0,713 0,413 0,276 -0,024 2+370 0,692 0,392 28,445 16,894 20 2+390 2,752 2,452 1,989 1,689 2+560 0,086 -0,214 17,384 1,336 1,036 24,544 20 2+580 2,253 1,953 41,706 1,718 1,418 30,915 20 2+600 2,518 2,218 45,313 1,973 1,673 30,526 20 2+620 2,613 2,313 37,654 1,680 1,380 19,58 20 2+640 1,752 1,452 0,879 0,579 3+010 1,756 1,456 16,56045 0,894 0,594 4,3065 14,5 3+030 1,128 0,828 18,666 40 3+070 0,405 0,105 10,41 0,757 20 3+090 1,236 0,936 0,376 0,076 TOTAL 226,333 TOTAL 129,161 Luas Kiri = 1351,789 m 2 Luas Kanan = 939, 89 m 2 Luas Total = 1351,789 + 939, 89 = 2.291,679 m 2 commit to user 170

5.2.4. Penghitungan Volume Pekerjaan Perkerasan

1. Lapis Permukaan Gambar 5.9. Sket lapis pondasi bawah L = 075 , 2 15 , 7 00 , 7         = 0,531 m² V = 0,531 x Panjang jalan = 0,531 x 3400,00 m = 1.805,40 m³ 2. Lapis Resap Pengikat prime Coat Luas = Lebar pondasi atas x Panjang jalan = 7,15 x 3400,00 = 24.310,00 m² 3. Lapis Pondasi Atas 5.10. Sket lapis pondasi atas L = 20 , 2 55 , 7 15 , 7         = 1,47 m² V = 1,47 x Panjang jalan = 1,47 x 3400,00 = 4.998,00 m³ 7,00 m 0,075 m 0,075 m 0,075 m 7,15 m 0,20 m 0,20 m 0,20 m commit to user 171 4. Lapis Pondasi Bawah Gambar 5.11. Sket lapis permukaan L = 3 , 2 15 , 8 55 , 7         = 2,355 m² V = 2,355 x Panjang jalan = 2,355 x 3400,00 = 8.007,00 m³

5.2.5. Penghitungan Volume Pekerjaan Pelengkap

1. Pekerjaan Pengecatan Marka Jalan Ukuran marka Gambar 5.12 Sket marka jalan a. Marka ditengah putus-putus Jumlah = Panjang Jalan – Panjang Tikungan PI1+PI2+PI3 5 = 3400,00 – 231,48 + 264,09 + 264,09 5 = 528,068 buah Luas = 528,068 x 0,1x 2 = 105,614 m² 0,10m 0,10m 2 m 3 m 2 m 7,55 m 0,3 m 0,3 m 0,3 m commit to user 172 b. Marka Tikungan menerus Luas = Panjang tikungan PI1+PI2+PI3 x lebar marka = 231,48 + 264,09 + 264,09 x 0,1 = 75,97 m² c. Marka Tepi dan Tengah menerus Luas = Panjang jalan x Lebar marka x 4 = 3400,00 x 0,1 x 4 = 1360 m d. Luas total marka jalan Luas = 105,614 + 75,97 + 1360 = 1541,58 m² 2. Rambu Jalan Rambu kelas Jalan 2 buah , rambu batas kecepatan 2 buah , rambu melewati Jembatan 8 buah, rambu memasuki tikungan 6 buah , rambu dilarang menyiap 4 buah. Jadi total rambu yang digunakan adalah = 22 rambu jalan 3. Patok Jalan Digunakan 31 buah patok setiap 100 m. Digunakan 4 buah patok kilometer. Digunakan 50 patok pengaman di kiri dan kanan daerah bahu jalan curam dan di daerah tikungan. commit to user 173

5.3 Analisa Perhitungan Waktu Pelaksanaan Proyek

5.3.1. Pekerjaan Umum

1. Pekerjaan pengukuran diperkirakan dikerjakan selama 3 minggu. 2. Pekerjaan mobilisasi dan demobilisasi diperkirakan dikerjakan selama 2 minggu. 3. Pembuatan papan nama proyek diperkirakan selama 1 minggu. 4. Pembuatan Direksi Keet diperkirakan selama 1 minggu. 5. Pekerjaan administrasi dan dokumentasi dilakukan selama proyek berjalan.

5.3.2. Pekerjaan Tanah

1. Pekerjaan pembersihan semak dan pengupasan tanah : Luas Lahan = 33.149,49 m² Kemampuan pekerjaan per hari berdasar kuantitas kerja tenaga kerja diperkirakan 900 m² Kemampuan pekerjaan per minggu = 900 m² x 6 hari = 5.400 m² Waktu yang dibutuhkan untuk pekerjaan pembersihan semak dan pengupasan tanah =   minggu 139 , 6 400 . 5 33.149,49 7 minggu

2. Pekerjaan persiapan badan jalan :

Luas Lahan = 25.275,76 m 2 Kemampuan pekerjaan per hari berdasar kuantitas kerja Vibratory Roller adalah 249 m²jam x 7 jam =1.743 m 2 Kemampuan pekerjaan per minggu = 1.743 m 2 x 6 hari = 10.458 m 2 Misal digunakan 2 Vibratory Roller maka waktu yang dibutuhkan untuk pekerjaan pembersihan :     minggu 208 , 1 458 . 10 2 25.275,76 2 minggu 3. Pekerjaan galian tanah : Volume galian = 19.557,45 m 3 commit to user 174 Kemampuan pekerjaan per hari berdasar kuantitas kerja Excavator adalah 18,68 m³jam x 7 jam = 130,76 m 3 Kemampuan pekerjaan per minggu = 130,76 m 3 x 6 hari = 784,56 m 3 Misal digunakan 10 buah Excavator maka waktu yang dibutuhkan untuk pekerjaan galian :     minggu 493 , 2 56 , 784 10 19.557,45 3 minggu 4. Pekerjaan timbunan tanah setempat : Volume timbunan = 41.598,28 m 3 Kemampuan pekerjaan per hari berdasar kuantitas kerja Whell Loader diperkirakan = 56,03 m³jam x 7 jam = 392,21 m 3 Kemampuan pekerjaan per minggu = 392,21 m 3 x 6 hari = 2.353,26 m 3 Misal digunakan 2 buah Whell Loader maka waktu yang dibutuhkan untuk pekerjaan timbunan :     minggu 838 , 8 26 , 353 . 2 2 41.598,28 9 minggu

5.3.3. Pekerjaan Drainase

1. Pekerjaan galian saluran drainase : Volume galian saluran = 6.680 m 3 Kemampuan pekerjaan per hari berdasar kuantitas kerja Excavator adalah 18,68 m³jam x 7 jam = 130,76 m 3 Kemampuan pekerjaan per minggu = 130,76 m 3 x 6 hari = 784,56 m 3 Misal digunakan 2 buah Excavator maka waktu yang dibutuhkan untuk pekerjaan galian :     minggu 257 , 4 56 , 784 2 6.680 5 minggu 2. Pekerjaan pasangan batu dengan mortar : Volume pasangan batu = 2.939,2 m 3 Kemampuan pekerjaan per hari diperkirakan 150 m 3 Kemampuan pekerjaan per minggu = 150 x 6 = 900 m 3 commit to user 175 Waktu yang dibutuhkan untuk pekerjaan pasangan batu :    minggu 266 , 3 900 2.939,2 4 minggu 3. Pekerjaan plesteran : Volume plesteren = 2672,00 m 2 Kemampuan pekerjaan per hari diperkirakan 150 m 2 Kemampuan pekerjaan per minggu = 150 x 6 = 900 m 2 Waktu yang dibutuhkan untuk pekerjaan plesteran : = 900 2.672,00  2,969 minggu ≈ 3 minggu 4. Pekerjaan siaran : Volume siaran = 12.360,00 m 2 Kemampuan pekerjaan per hari diperkirakan 150 m 2 Kemampuan pekerjaan per minggu = 150 x 6 = 900 m 2 Waktu yang dibutuhkan untuk pekerjaan siaran : =  900 13.360,00 14, 844 minggu ≈ 15 minggu

5.3.4. Pekerjaan Dinding Penahan

1. Pekerjaan Galian Pondasi Volume galian pondasi = 1.345,637 m³ Kemampuan pekerjaan per hari berdasar kualitas kerja Excavator adalah 18,68m³jam x 7 jam = 130,76 m 3 Kemampuan pekerjaan per minggu = 130,76 m 3 x 6 hari = 784,56 m 3 Misal digunakan 2 buah Excavator maka waktu yang dibutuhkan untuk pekerjaan galian :     minggu 858 , 56 , 784 2 1.345,637 1 minggu 2. Pekerjaan Pasangan Batu pada Dinding Penahan Volume pasangan batu = 2.669,966 m³ Kemampuan pekerjaan per hari diperkirakan 150 m 2 commit to user 176 Kemampuan pekerjaan per minggu = 150 x 6 = 900 m 2 Waktu yang dibutuhkan untuk pekerjaan pasangan batu: = 900 2.669,966  2,967 minggu ≈ 3 minggu 3. Pekerjaan Plesteran Luas plesteran= 1.758,497 m 2 Kemampuan pekerjaan per hari diperkirakan 150 m 2 Kemampuan pekerjaan per minggu = 150 x 6 = 900 m 2 Waktu yang dibutuhkan untuk pekerjaan pasangan batu: = 900 1.758,497  1,954 minggu ≈ 2 minggu 4. Pekerjaan Siaran Luas siaran= 2.291,679 m 2 Kemampuan pekerjaan per hari diperkirakan 150 m 2 Kemampuan pekerjaan per minggu = 150 x 6 = 900 m 2 Waktu yang dibutuhkan untuk pekerjaan pasangan batu: = 900 2.291,679  2,546 minggu ≈ 3 minggu

5.3.5. Pekerjaan Perkerasan

1. Pekerjaan LASTON : Volume = 1. 805,40 m 3 Kemampuan pekerjaan per hari berdasar kuantitas kerja Asphalt Finisher diperkirakan 14,43 x 7 jam = 101,01 m 3 Kemampuan pekerjaan per minggu = 101,01 x 6 = 606,06 m 3 Maka waktu yang dibutuhkan untuk pekerjaan LASTON =    minggu 979 , 2 06 , 606 1.805,40 3 minggu commit to user 177 2. Pekerjaan Prime Coat : Luas volume perkerjaan untuk Prime Coat adalah 24.310,00 m 2 Kemampuan pekerjaan per hari berdasar kuantitas kerja Asphalt Sprayer diperkirakan 2.324 m 2 Kemampuan pekerjaan per minggu = 2.324 x 6 = 13.944 m 2 Waktu yang dibutuhkan untuk pekerjaan prime coat :    minggu 743 , 1 944 . 13 24.310,00 2 minggu 3. Pekerjaan LPA Lapis Pondasi Atas : Volume = 4.998,00 m 3 Kemampuan pekerjaan per hari berdasar kuantitas kerja Whell Loader diperkirakan = 16,01 m³ x 7 jam = 112,07 m 3 Kemampuan pekerjaan per minggu = 112,07 m 3 x 6 hari = 672,42 m 3 Waktu yang dibutuhkan untuk pekerjaan LPA :    minggu 433 , 7 42 , 672 4.998,00 8 minggu 4. Pekerjaan LPB Lapis Pondasi Bawah : Volume = 8.007,00 m³ Kemampuan pekerjaan per hari berdasar kuantitas kerja Vibro roller diperkirakan = 21 m³ x 7 jam = 147 m 3 Kemampuan pekerjaan per minggu = 147 m 3 x 6 hari = 882 m 3 Waktu yang dibutuhkan untuk pekerjaan LPB :    minggu 8 07 , 9 882 8.007,00 10 minggu commit to user 178

5.3.6. Pekerjaan Pelengkap

1. Pekerjaan marka jalan : Luas = 181,584 m 2 Kemampuan pekerjaan per hari berdasar kuantitas tenaga kerja diperkirakan 93,33 m 2 Kemampuan pekerjaan per minggu = 93,33 x 6 = 559,98 m 2 Waktu yang dibutuhkan untuk pekerjaan marka : =   324 , 98 , 559 181,584 1 minggu 2. Pekerjaan rambu jalan diperkirakan selama 1 minggu. 3. Pembuatan patok kilometer diperkirakan selama 1 minggu. 4. Pembuatan patok pengaman diperkirakan selama 1 minggu. commit to user 179

5.4. Analisa Perhitungan Harga Satuan Pekerjaan

Perhitungan harga satuan pekerjaan dihitung dengan cara mengalikan volume dengan upah atau harga tenaga material dan peralatan,kemudian dijumlah dikalikan 10 Overhead dan Profit.Hasil dari jumlah biaya ditambah dengan hasil Overhead dan Profit dinamakan Harga Satuan Pekerjaan. Contoh perhitungan pekerjaan penyiapan badan jalan: Diketahui : a. Tenaga 1. Pekerja jam ; Volume 0,0161 ; Upah Rp 5.500,00 Biaya = Volume x Upah = 0,0161 x 5.500,00 = 88,55 2. Mandor jam ; Volume 0,004 ; Upah Rp 9.000,00 Biaya = Volume x Upah = 0,004 x 9.000,00 = 36,00 Total biaya tenaga = 124,55 b. Peralatan 1. Motor Grader jam ; Volume 0,0025 ; Harga Rp 220.000,00 Biaya = Volume x Upah = 0,0025 x 220.000,00 = 550,00 commit to user 180 2. Vibro Roller jam ; Volume 0,004 ; Harga Rp 170.000,00 Biaya = Volume x Upah = 0,004 x 170.000,00 = 680,00 3. Water Tanker jam ; Volume 0,0105 ; Harga Rp 108.000,00 Biaya = Volume x Upah = 0,0105 x 108.000,00 = 1.134,00 4. Alat Bantu Ls ; Volume 1 ; Harga Rp 150,00 Biaya = Volume x Upah = 1 x 150,00 = 150,00 Total biaya peralatan = 2514,00 Total biaya tenaga dan peralatan = 2638,55 A Overhead dan Profit 10 x A = 263,86 B Harga Satuan Pekerjaan A + B = 2902,41 Untuk hasil penghitungan selanjutnya dapat dilihat di Lampiran. commit to user 181 5.4.1 Bobot Pekerjaan Perhitungan bobot pekerjaan dihitung dengan mengalikan volume tiap pekerjaan dengan harga satuan tiap pekerjaan.  Bobot = Volume  Harga satuan Contoh perhitungan untuk pekerjaan persiapan badan jalan : Bobot pekerjaan persiapan badan jalan = Volume pekerjaan  Harga satuan = 35061  2902,41 = 101.761.397,010 5.4.2 Persen Bobot Pekerjaan Perhitungan persen bobot pekerjaan dihitung dengan membandingkan bobot tiap pekerjaan dengan bobot total pekerjaan dikalikan 100  Bobot pekerjaan = 100 total Bobot pekerjaan Bobot  Contoh perhitungan untuk pekerjaan persiapan badan jalan : Bobot pekerjaan persiapan badan jalan = 100 total Bobot pekerjaan Bobot  = 100 .386,21 17.379.529 7,01 101.761.39  = 0,586 Untuk hasil penghitungan selanjutnya dapat dilihat di Lampiran. commit to user 182 Tabel 5.5. Rekapitulasi Perkiraan Waktu Pekerjaan No Nama Pekerjaan Volume Pekerjaan Kemampuan Kerja per hari Kemampuan Kerja per minggu Waktu Pekerjaan minggu 1 Pengukuran Ls - - 3 2 Mobilisasi dan Demobilisasi Ls - - 3 3 Pembuatan papan nama proyek Ls - - 1 4 Pekerjaan Direksi Keet Ls - - 2 5 Administrasi dan Dokumentasi Ls - - Selama proyek 6 Pembersihan semak pengupasan tanah 33.149,49 m 2 900,00 m2 5.400,00 m 2 7 7 Persiapan badan jalan 25.275,76 m 2 1.743,00 m 2 10.458,00 m 2 2 8 Galian tanah 19.557,45 m 3 130,76 m 3 784,56 m 3 3 9 Timbunan tanah 41.598,28 m 3 392,21 m 3 2.353,26 m 3 9 10 Drainase : a. Galian saluran 6.680,00 m 3 130,76 m 3 784,56 m 3 5 b. Pasangan batu dengan mortar 2.939,20 m 3 150 m 3 900 m 3 4 c Plesteran 2.672,00 m 2 150 m 3 900 m 3 3 d. Siaran 12.360,00 m 2 150 m 3 900 m 3 15 11 Dinding penahan : a Galian Pondasi Pada Dinding Penahan 1.345,637 m 3 130,76 m 3 784,56 m 3 1 b. Pasangan batu dengan mortar 2.669,966 m 3 150 m 3 900 m 3 3 c. Plesteran 1.758,497 m 2 150 m 3 900 m 3 2 d. Siaran 2.291,679 m 2 150 m 3 900 m 3 3 12 Lapis Pondasi Bawah LPB 8.007,00 m 3 147 m 3 882 m 3 10 13 Lapis Pondasi Atas LPA 4.998,00 m 3 112,07 m 3 672,42 m 3 8 14 Lapis Permukaan LASTON 1. 805,40 m 3 101,01 m 3 606,06 m 3 3 15 Prime Coat 24.310,00 m 2 2324,00 m 2 13.944,00 m 2 2 16 Pelengkap a. Marka jalan 181,584 m 2 93,33 m 2 559,98 m 2 1 b. Rambu - - - 1 c. Patok - - - 1 commit to user 183 Dari hasil analisis perhitungan waktu pelaksanaan, analisis harga satuan pekerjaan dan perhitungan bobot pekerjaan, maka dapat dibuat Rencana Anggaran Biaya RAB dan Time Schedule pelaksanaan proyek dalam bentuk Bar Chard dan Kurva S. commit to user 184

5.6. REKAPITULASI RENCANA ANGGARAN BIAYA