BAB V RENCANA ANGGARAN BIAYA DAN
TIME SCHEDULE
5.1 Typical Potongan Melintang
Gambar 5.1 Potongan Melintang Jalan
5.2 Analisa Perhitungan Volume Pekerjaan
5.2.1. Penghitungan Volume Pekerjaan Tanah
1. Pembersihan Semak dan Pengupasan Tanah. Luas
= p. Damija x p. Jalan – p. Jembatan Total = 11 m x 3400,00 m – 60 m
= 36.740,00 m² 2. Persiapan Badan Jalan m² .
Luas = Lebar lapis pondasi bawah x Panjang jalan – p. Jembatan
total = 8,15 m x 3400,00 m – 60 m
= 27.650,00 m²
commit to user 146
3. Galian Tanah Biasa m³ Contoh penghitungan : STA 0+350
STA 0+350
Bahu Jalan Bahu Jalan
Lebar Perkerasan Jalan 1.5m
1.5m 2 x 3,5m
Drainase
0.5m
3 x 0.5m
0.5m
Drainase
0.5m
3 x 0.5m
0.5m
471.87
470.07 471.80
471.74 471.94
472.00
469.91 469.85
470.23 470.29
472.50 468.20
- 4 - 2
- 2 - 4
1 2
3 4
5 6
7 8
470.09 474.21
Gambar 5.2 Tipical Cross Section STA 0+350
H1 = 470,09 – 468,20 = 1, 89
H2 = 471,74 – 469, 89 = 1, 85
H3 = 471, 80 – 469, 91 = 1, 89
H4 = 471, 87 – 470,07 = 1, 80
H5 = 471,94 – 470,23 = 1,71
H6 = 472,00 – 470,29 = 1,71
H7 = 474,21 – 472,50 = 1,71
¤ Perhitungan Luas
2
782 ,
1 2
1 1
m H
a Luas
2
675 ,
4 5
, 2
2 2
1 2
m H
H Luas
2
74 ,
3 2
2 3
2 3
m H
H Luas
commit to user 147
2
457 ,
6 5
, 3
2 4
3 4
m H
H Luas
2
143 ,
6 5
, 3
2 5
4 5
m H
H Luas
2
42 ,
3 2
2 6
5 6
m H
H Luas
2
275 ,
4 5
, 2
2 7
6 7
m H
H Luas
2
946 ,
7 2
1 8
m H
a Luas
2
m 32,438
Galian
Total
L
4. Timbunan Tanah Biasa m³ Contoh penghitungan : STA 0 + 250
STA 0+250
Bahu Jalan Drainase
0.5m
3 x 0.5m
0.5m
1.5m Lebar Perkerasan Jalan
2 x 3,5m Bahu Jalan
1.5m Drainase
0.5m
3 x 0.5m
0.5m
468.29
465.95 468.22
468.16 468.36
468.42
466.11 468.25
465.79 463.39
- 4 - 4
- 2 - 2
1 2
3 4
5 6
Talud Talud
Gambar 5.3 Tipical Cross Section STA 0 + 250
commit to user 148
H1 = 468,42 – 468,25 = 0,17
H2 = 468,36 – 466,11 = 2,25
H3 = 468,29 –465,95 = 2,34
H4 = 468,22 – 465,79 = 2,43
H5 = 468,16 – 463,39 = 4,77
¤ Perhitungan Luas
2
0072 ,
1 2
1 2
1 1
m H
H Luas
2
42 ,
2 2
2 2
1 2
m H
H Luas
2
033 ,
8 5
, 3
2 3
2 3
m H
H Luas
2
8 34
, 8
5 ,
3 2
4 3
4 m
H H
Luas
2
20 ,
7 2
2 5
4 5
m H
H Luas
2
88 6
, 5
5 2
5 2
1 6
m H
H Luas
2
m 21,526
Timbunan Ltotal
Untuk hasil penghitungan selanjutnya disajikan dalam Tabel 5.1
commit to user 149
Tabel. 5.1 Hasil perhitungan volume galian dan timbunan
NO STA
JARAK LUAS m
²
VOLUME m
³
m GALIAN TIMBUNAN
GALIAN TIMBUNAN
1 0+000
1,127 50
66,220 6,533
2 0+050
1,522 0,261
50 38,050
33,733 3
0+100 1,088
50 31,720
27,200 4
0+150 1,269
50 31,720
189,815 5
0+200 7,593
50 727,975
6 0+250
21,526 50
6437,423 7
0+300 235,971
50 800,075
5899,263 8
0+350 32,003
50 1678,288
9 0+400
35,129 50
1113,760 10
0+450 9,422
50 239,635
90,533 11
0+500 0,164
3,621 50
4,088 501,248
12 0+550
16,429 50
1119,898 13
0+600 28,367
50 1676,223
14 0+650
38,682 50
815,130 967,040
15 0+700
32,605 50
1351,108 16
0+750 21,439
50 701,993
17 0+800
6,641 19,86
106,734 18
0+819,86 4,108
29,2 59,977
16,914
commit to user 150
19 0+849,06
1,159 0,94
1,582 20
0+850 2,208
28,26 188,486
31,202 21
0+878,26 13,339
21,74 144,999
103,010 22
0+900 9,477
50 502,913
23 0+919,86
10,640 50
785,873 24
0+950 20,795
50 1402,383
25 1+000
35,300 50
2088,683 26
1+050 48,247
1,24 57,497
27 1+051,24
44,491 41,59
1756,980 28
1+092,83 40,000
7,17 135,367
143,400 29
1+100 37,759
22,03 874,351
30 1+122,03
41,619 27,97
1118,565 31
1+150 38,364
1,24 56,980
32 1+151,24
53,539 48,76
1359,707 6,997
33 1+200
2,232 0,287
50 81,285
20,163 34
1+250 1,019
0,520 50
31,090 28,025
35 1+300
0,225 0,602
50 49,713
25,613 36
1+350 1,764
0,423 50
47,045 95,375
37 1+400
0,118 3,392
50 2,948
361,700 38
1+450 11,076
commit to user 151
50 479,910
276,900 39
1+500 19,196
50 593,328
40 1+550
4,537 50
178,120 10,133
41 1+600
2,588 0,405
50 363,728
10,133 42
1+650 11,961
7,85 86,810
43 1+657,85
10,156 42,15
214,042 228,622
44 1+700
10,848 3,35
37,100 45
1+703,35 11,301
43,3 338,931
46 1+746,65
4,354 3,35
12,623 47
1+750 3,182
39,96 36,136
82,737 48
1+789,96 1,809
0,959 10,04
282,735 4,814
49 1+800
54,513 50
1367,778 17,965
50 1+850
0,198 0,719
50 22,690
29,290 51
1+900 0,710
0,453 20,1
9,803 8,639
52 1+920,10
0,266 0,407
29,9 28,360
13,068 53
1+950 1,631
0,468 13,96
27,140 21,111
54 1+963,96
2,257 2,557
36,04 94,956
47,933 55
2+000 3,013
0,103 6,71
14,532 2,600
56 2+006,71
1,319 0,672
43,29 118,238
14,545 57
2+050 4,144
2,2 8,965
commit to user 152
58 2+052,20
4,006 47,8
98,697 153,080
59 2+100
0,124 6,405
50 7,895
730,475 60
2+150 0,192
22,814 50
11,030 946,750
61 2+200
0,249 15,056
50 10,300
924,775 62
2+250 0,163
21,935 50
11,425 572,313
63 2+300
0,294 0,958
50 107,675
23,938 64
2+350 4,013
50 104,993
641,675 65
2+400 0,187
25,667 50
11,268 1059,475
66 2+450
0,264 16,712
50 12,183
939,723 67
2+500 0,223
20,877 50
10,408 891,523
68 2+550
0,193 14,784
50 4,825
923,725 69
2+600 22,165
17,26 1,143
372,013 70
2+617,26 0,132
20,942 32,74
5,988 392,242
71 2+650
0,233 3,019
1,97 0,360
5,040 72
2+651,97 0,132
2,098 34,72
617,370 36,413
73 2+686,69
35,431 13,31
524,885 74
2+700 43,440
21,41 467,278
93,273 75
2+721,41 0,210
8,713 28,59
6,234 369,060
76 2+750
0,226 17,104
50 11,913
918,663 77
2+800 0,251
19,642
commit to user 153
50 9,440
985,978 78
2+850 0,127
19,797 50
6,480 1002,650
79 2+900
0,132 20,309
13,51 1,787
258,669 80
2+913,51 0,132
17,984 34,71
6,359 469,036
81 2+948,22
0,234 9,042
1,78 0,379
16,095 82
2+950 0,192
9,042 32,95
5,519 334,197
83 2+982,95
0,143 11,243
17,05 2,302
197,513 84
3+000 0,127
11,926 17,67
3,649 186,308
85 3+017,67
0,286 9,162
32,33 62,656
155,958 86
3+050 3,590
0,486 50
95,503 309,993
87 3+100
0,230 11,914
50 5,753
1348,393 88
3+150 42,022
50 503,550
1050,550 89
3+200 20,142
50 503,550
150,548 90
3+250 6,022
50 5,775
394,748 91
3+300 0,231
9,768 50
11,530 630,875
92 3+350
0,230 15,467
50 63,173
394,385 93
3+400 2,297
0,308 TOTAL
18369,571 40172,878
commit to user 154
NO STA
JARAK LUAS m
²
VOLUME m
³
m GALIAN TIMBUNAN GALIAN
TIMBUNAN
1 0+110
0,882 10
5,968 2
0+130 0,311
10 2,218
3 0+150
0,132 10
0,678 5,333
4 0+170
0,136 0,934
10 1,829
28,654 5
0+190 0,230
4,797 10
161,786 23,983
6 1+160
32,127 10
236,019 7
1+180 15,077
10 93,259
8 1+200
3,575 10
48,620 9
1+220 6,149
10 36,154
2,484 10
1+240 1,082
0,497 10
21,037 4,039
11 1+560
3,126 0,311
10 27,434
3,926 12
1+580 2,361
0,474 10
27,631 3,596
13 1+600
3,165 0,245
10 74,113
1,225 14
1+620 11,658
10 112,376
15 1+640
10,818 10
72,170 16
2+010 3,616
10 38,872
17 2+030
4,158 10
38,564 18
2+050 3,555
10 23,813
1,817 19
2+070 1,208
0,363
commit to user 155
10 6,039
12,102 20
2+090 2,057
10 7,038
14,035 21
2+310 1,408
0,750 10
28,305 3,750
22 2+330
4,253 10
39,217 23
2+350 3,590
10 18,313
6,876 24
2+370 0,073
1,375 10
1,308 124,011
25 2+390
0,189 23,427
10 1,924
194,555 26
2+560 0,196
15,484 10
1,657 171,265
27 2+580
0,136 18,769
10 1,357
203,443 28
2+600 0,136
21,920 10
1,860 212,806
29 2+620
0,236 20,642
10 2,363
157,736 30
2+640 0,236
10,906 10
2,346 109,610
31 3+010
0,233 11,016
10 1,165
75,111 32
3+030 4,006
10 19,227
22,113 33
3+050 3,845
0,417 10
29,712 4,638
34 3+070
2,097 0,511
10 11,701
30,116 35
3+090 0,243
5,513
TOTAL 1187,879
1425,401
commit to user 156
Total Volume Galian = 19.557,45 m
3
Total Volume Timbunan = 41.598,28 m
3
Contoh perhitungan Volume Galian STA 0+400 s.d 0+450 Jarak : 0+400 – 0+450 = 50 m
Jarak LuasSTA
LuasSTA V
2
450 ..
400 ..
=
50 2
9,422 5,129
3
= 1113,775 m
3
Contoh perhitungan Volume Timbunan STA 0+250 s.d 0+300 Jarak : 0+250 – 0+300 = 50 m
Jarak LuasSTA
LuasSTA V
2
300 ..
250 ..
=
50 2
971 ,
235 526
, 21
= 6437,425 m
3
5.2.2. Penghitungan Volume Pekerjaan Drainase
1. Galian Saluran
Gambar 5.4 Sket Volume galian saluran
1,5 m
0,5 m 1 m
commit to user 157
1
2 5
, 5
, 1
Luas
2
1 m
2 2
tan 1
tan .
jemba
jemba p
jalan Panjang
Luas V
3
00 ,
6680 2
60 00
, 3400
1 m
x
2. Pasangan Batu Dengan Mortar
I II
I
0.2 m 0.2 m
1.5 m
0.3 m
1.5 m 0.2 m
0.8 m
Gambar 5. 5 Sket volume pasangan batu
2 2
, 2
, 1
2 I
uas L
= 0,4 m
2
2 ,
2 3
, 1
,
II uas
L =
0,04 m
2
40 ,
04 ,
total uas
L =
0,44 m
2
Volume = 2 x luas x panjang Jalan – p. Jemb. total
= 2 x 0,44 x 3400,00 -60
= 2939,2 m
3 0,5 m
commit to user 158
A A
H
H5+0,3 25 cm
H6+0,3
3. Plesteran
Gambar 5.6 Detail Plesteran pada Potongan A-A
Luas = 0,25 + 0,1 + 0,05 x 3400,00 – 60 x 2
= 2672 m
2
4. Siaran Luas
= Lebar saluran drainase x p.jalan – p.jembatanx 2 = 2 x 3400,00 - 60 x 2
= 13360 m
2
5.2.3. Penghitungan Volume Pekerjaan Dinding Penahan
5.7 Sket volume pasangan batu pada dinding penahan
10 cm 5 cm
Pasangan batu 25 cm
Plesteran
commit to user 159
1. Galian Pondasi a. Ruas Kiri
Sta 0+200 sd 0+250 Sta 0+200
H Sta 0+200 = 0,9458 m
H5+0,3 = 0,489 m
H6+0,3 = 0,457 m
Luas galian pondasi = 0,489 x 0,457 = 0,223 m
2
Sta 0+250 H Sta 0+200
= 2,0822 m H5+0,3
= 0,716 m H6+0,3
= 0,647 m Luas galian pondasi = 0,716 x = 0,647 = 0,463 m
2
Volume 0+200 sd 0+250 = 50
2 0,463
0,223
= 17,15 m a. Ruas Kanan
Sta 0+200 sd 0+250 Sta 0+200
H Sta 0+200 = 1,0763 m H5+0,3
= 0,515 m H6+0,3
= 0,479 m Luas galian pondasi = 0,515 x 0,479 = 0,247 m
2
Sta 0+250 H Sta 0+250
= 2,3402 m H5+0,3
= 0,768 m H6+0,3
= 0,690 m Luas galian pondasi = 0,768 x 0,690 = 0,529 m
2
Volume Sta 0+200 sd 0+250 =
50 2
0,529 0,247
= 19,40 m
3
commit to user 160
Perhitungan selanjutnya dapat dilihat pada tabel 5.2 Tabel 5.2 Perhitungan Volume Galian Pondasi pada Dinding Penahan
commit to user 161
Volume galian dinding penahan Kiri = 813,703 m³
Volume galian dinding penahan Kanan = 531,934 m³
Volume Total galian dinding penahan = 813,703 + 531,934
= 1.345,637 m³
2. Pasangan Batu untuk Dinding Penahan a. Ruas Kiri
Sta Sta 0+200 sd 0+250 Sta 0+200
Lebar atas = 0,25 m
H Sta 0+200 = 0,946 m
H5+0,3 = 0,489 m
H6+0,3 = 0,456 m
Luas pasangan batu =
0,456 0,489
946 ,
2 0,456
25 ,
= 0,557 m
2
Sta 0+250 Lebar atas
= 0,25 m H Sta 0+250
= 2,082 m H5+0,3
= 0,716 m H6+0,3
= 0,647 m Luas pasangan batu =
0,647 x
0,716 82
, 2
2 0,647
25 ,
= 1,397 m
2
Volume =
50 2
397 ,
1 557
,
= 48, 85 m³
commit to user 162
a. Ruas Kanan Sta Sta 0+200 sd 0+250
Sta 0+200 Lebar atas
= 0,25 m H Sta 0+200
= 1,076 m H5+0,3
= 0,515 m H6+0,3
= 0,479 m Luas pasangan batu =
0,479 515
, 076
, 1
2 0,479
25 ,
= 0,639 m
2
Sta 0+250 Lebar atas
= 0,25 m H Sta 0+250
= 2,340 m H5+0,3
= 0,768 m H6+0,3
= 0,690 m Luas pasangan batu =
690 ,
768 ,
340 ,
2 2
690 ,
25 ,
= 1,597 m
2
Volume = 50
2 597
, 1
0,639
= 55,90 m
3
commit to user 163
Perhitungan selanjutnya dapat dilihat pada tabel 5.3 Tabel 5.3 Perhitungan Volume Pasangan Batu pada Dinding Penahan
commit to user 164
25 c m 3 0 c m
1 0 c m H - 0 ,3
Volume pasangan batu pada dinding penahan kiri = 1.786,323 m
3
Volume pasangan batu pada dinding penahan kanan = 883,673 m
3
Volume Total pasangan batu pada dinding penahan = 1.786,323 + 883,673
= 2.669,996 m
3
3. Plesteran
Gambar 5.8 Detail plesteran pada Dinding Penahan Ruas kiri
Luas = 0,1+0,3+0,25x p.dinding penahan kiri = 0,1+0,3+0,25 x
50+50+50+50+12,457+12,243+35,757+6,727+26,7+16,573+7,427+ 50+50+50+50+50+50+50+14,5+17,905+50+50+50+50+50+50+50+
14+5,63+8,77+41,23+10,37+39,63+50+50+50+50+50 = 0,65 x 1419,919
= 922,947 m
2
Ruas kanan Luas = 0,1+0,3+0,25x p.dinding penahan kanan
= 0,1+0,3+0,25x 50+50+50+50+6,727+26,7+50+50+50+50+50+50+ 14,5+17,905+50+50+50+50+50+50+50+50+8,77+14+5,63+41,23+10,37+
39,63+50+33,178+16,822+50+50+50 = 0,65 x 1285,462
= 835,550 m
2
Luas total = 922,947 + 835,550 = 1.758,497 m
2
commit to user 165
3. Siaran Ruas kiri
Sta 0+200 sd 0+250 H Sta 0+200
= 0,946 m H Sta 0+200 – 0.3 = 0,646 m
H Sta 0+250 = 2,082 m H Sta 0+250 – 0,3
= 1,782 m Luas
= 50
2 82
, 2
946 ,
= 75,70 m
2
Ruas kanan Sta 0+200 sd 0+250
H Sta 0+200 = 1,076 m H Sta 0+200 – 0.3
= 0,776 m H Sta 0+250
= 2,340 m H Sta 0+250 – 0,3 = 2,040 m
Luas =
50 2
340 ,
2 076
, 1
= 85,4 m
2
Perhitungan selanjutnya dapat dilihat pada tabel 5.4
commit to user 166
Tabel 5.4 Perhitungan Luas Siaran pada dinding Penahan
STA Jarak
KIRI KANAN
H H - 0,3
Luas H
H - 0,3 Luas
0+050 0,160
-0,140 50
-1,675 -7,333
0+100 0,373
0,073 0,307
0,007 50
17,975 19,575
0+200 0,946
0,646 1,076
0,776 50
60,695 70,413
0+250 2,082
1,782 2,340
2,040 50
115,700 131,983
0+300 3,146
2,846 3,539
3,239 0+500
0,940 0,640
0,355 0,055
0+550 2,195
1,895 50
0+600 3,289
50 0+650
4,225 0+850
0,476 0,176
0,544 0,244
50 24,430
30,100 0+900
1,101 0,801
1,260 0,960
19,86 15,889
21,656 0+919,86
1,099 0,799
1,521 1,221
19,86 25,108
9,146 0+950
2,030 1,730
7,427 46,414
-2,228 1+051,24
11,069 10,769
1+092,83 4,449
4,149 1+300
0,386 0,086
50 15,545
1+400 0,836
0,536 0,412
50 45,375
1+450 1,579
1,279 1,071
commit to user 167
1+700 1,552
1,252 1,057
3,305 4,194
1+703,305 1,586
1,286 1,103
0,803 50
48,383 24,590
1+746,65 0,949
0,649 0,480
0,180 3,35
1,981 0,428
1+750 0,833
0,533 0,375
0,075 1+789,96
0,246 -0,054
0,164 -0,136
14,5 0,734
-0,986 1+850
0,455 0,155
50 4,560
1+900 0,327
0,027 2+100
1,135 0,674
0,374 50
49,615 2+150
2,733 1,911
1,611 50
62,380 2+200
2,173 1,184
0,884 2+250
2,596 2,296
1,908 1,608
50 65,393
32,688 2+300
0,620 0,320
0,000 -0,300
0,000 0,000
2+400 2,958
2,658 2,145
1,845 8,77
20,639 12,446
2+450 2,349
2,049 1,293
0,993 50
109,503 59,838
2+500 2,631
2,331 1,700
1,400 50
101,658 59,180
2+550 2,035
1,735 1,267
0,967 0,000
0,000 2+617,26
2,430 2,130
1,901 1,601
32,74 46,579
24,478 2+650
1,016 0,716
0,194 -0,106
1,97 0,409
-0,400 2+651,97
-0,300 0,000
-0,300 0,000
2+721,41 -0,300
1,084 2+750
2,134 1,834
1,557 1,257
commit to user 168
50 99,735
65,605 2+600
2,455 2,155
1,667 1,367
50 110,520
66,413 2+850
2,565 2,265
1,589 1,289
50 116,128
63,868 2+900
2,680 2,380
1,565 1,265
13,51 29,586
17,277 2+913,51
2,300 2,000
1,592 1,292
34,71
58,922 28,815
2+948,22 1,695
1,395 0,668
0,368 1,780
2,488 0,602
2+950 1,700
1,400 0,608
0,308 32,950
47,405 15,183
2+982,95 1,777
1,477 0,913
0,613 17,050
25,792 10,705
3+000 1,849
1,549 0,942
0,642 17,67
26,241 8,376
3+017,67 1,722
1,422 0,606
0,306 82,330
120,062 36,390
3+100 1,795
1,495 0,878
0,578 50
137,500 89,133
3+150 4,305
4,005 3,287
2,987 100
249,885 157,185
3+250 1,293
0,993 0,457
0,157 50
57,898 16,513
3+300 1,623
1,323 0,804
0,504 50
76,505 39,580
3+350 2,037
1,737 1,379
1,079 TOTAL
1125,456 TOTAL
810,729
commit to user 169
STA Jarak
KIRI KANAN
H H - 0,3
Luas H
H - 0,3 Luas
0+110 0,003
0,237 -0,063
50 0+170
0,569 0,269
10,195 1,638
20 0+190
1,051 0,751
0,464 0,164
2+090 0,713
0,413 0,276
-0,024 2+370
0,692 0,392
28,445 16,894
20 2+390
2,752 2,452
1,989 1,689
2+560 0,086
-0,214 17,384
1,336 1,036
24,544 20
2+580 2,253
1,953 41,706
1,718 1,418
30,915 20
2+600 2,518
2,218 45,313
1,973 1,673
30,526 20
2+620 2,613
2,313 37,654
1,680 1,380
19,58 20
2+640 1,752
1,452 0,879
0,579 3+010
1,756 1,456
16,56045 0,894
0,594 4,3065
14,5 3+030
1,128 0,828
18,666 40
3+070 0,405
0,105 10,41
0,757 20
3+090 1,236
0,936 0,376
0,076 TOTAL
226,333 TOTAL
129,161
Luas Kiri = 1351,789 m
2
Luas Kanan = 939, 89 m
2
Luas Total = 1351,789 + 939, 89
= 2.291,679 m
2
commit to user 170
5.2.4. Penghitungan Volume Pekerjaan Perkerasan
1. Lapis Permukaan
Gambar 5.9. Sket lapis pondasi bawah L =
075 ,
2 15
, 7
00 ,
7
= 0,531 m² V = 0,531 x Panjang jalan
= 0,531 x 3400,00 m = 1.805,40 m³
2. Lapis Resap Pengikat prime Coat Luas = Lebar pondasi atas x Panjang jalan
= 7,15 x 3400,00 = 24.310,00 m²
3. Lapis Pondasi Atas
5.10. Sket lapis pondasi atas L =
20 ,
2 55
, 7
15 ,
7
= 1,47 m² V = 1,47 x Panjang jalan
= 1,47 x 3400,00 = 4.998,00 m³
7,00 m 0,075 m
0,075 m 0,075 m
7,15 m 0,20 m
0,20 m 0,20 m
commit to user 171
4. Lapis Pondasi Bawah
Gambar 5.11. Sket lapis permukaan L =
3 ,
2 15
, 8
55 ,
7
= 2,355 m²
V = 2,355 x Panjang jalan = 2,355 x 3400,00
= 8.007,00 m³
5.2.5. Penghitungan Volume Pekerjaan Pelengkap
1. Pekerjaan Pengecatan Marka Jalan Ukuran marka
Gambar 5.12 Sket marka jalan
a. Marka ditengah putus-putus Jumlah = Panjang Jalan – Panjang Tikungan PI1+PI2+PI3
5 = 3400,00 – 231,48 + 264,09 + 264,09
5 = 528,068 buah
Luas = 528,068 x 0,1x 2 = 105,614 m²
0,10m 0,10m
2 m 3 m
2 m
7,55 m 0,3 m
0,3 m 0,3 m
commit to user 172
b. Marka Tikungan menerus Luas = Panjang tikungan PI1+PI2+PI3 x lebar marka
= 231,48 + 264,09 + 264,09 x 0,1
= 75,97 m² c. Marka Tepi dan Tengah menerus
Luas = Panjang jalan x Lebar marka x 4 = 3400,00 x 0,1 x 4
= 1360 m d. Luas total marka jalan
Luas = 105,614 + 75,97 + 1360 = 1541,58 m²
2. Rambu Jalan Rambu kelas Jalan 2 buah , rambu batas kecepatan 2 buah , rambu melewati
Jembatan 8 buah, rambu memasuki tikungan 6 buah , rambu dilarang menyiap 4 buah.
Jadi total rambu yang digunakan adalah = 22 rambu jalan 3. Patok Jalan
Digunakan 31 buah patok setiap 100 m. Digunakan 4 buah patok kilometer.
Digunakan 50 patok pengaman di kiri dan kanan daerah bahu jalan curam dan di daerah tikungan.
commit to user 173
5.3 Analisa Perhitungan Waktu Pelaksanaan Proyek
5.3.1. Pekerjaan Umum
1. Pekerjaan pengukuran diperkirakan dikerjakan selama 3 minggu. 2. Pekerjaan mobilisasi dan demobilisasi diperkirakan dikerjakan selama
2 minggu. 3. Pembuatan papan nama proyek diperkirakan selama 1 minggu.
4. Pembuatan Direksi Keet diperkirakan selama 1 minggu. 5. Pekerjaan administrasi dan dokumentasi dilakukan selama proyek berjalan.
5.3.2. Pekerjaan Tanah
1. Pekerjaan pembersihan semak dan pengupasan tanah : Luas Lahan = 33.149,49 m²
Kemampuan pekerjaan per hari berdasar kuantitas kerja tenaga kerja diperkirakan 900 m²
Kemampuan pekerjaan per minggu = 900 m² x 6 hari = 5.400 m² Waktu yang dibutuhkan untuk pekerjaan pembersihan semak dan pengupasan
tanah =
minggu 139
, 6
400 .
5 33.149,49
7 minggu
2. Pekerjaan persiapan badan jalan :
Luas Lahan = 25.275,76 m
2
Kemampuan pekerjaan per hari berdasar kuantitas kerja Vibratory Roller adalah 249 m²jam x 7 jam =1.743 m
2
Kemampuan pekerjaan per minggu = 1.743 m
2
x 6 hari = 10.458 m
2
Misal digunakan 2 Vibratory Roller maka waktu yang dibutuhkan untuk pekerjaan pembersihan :
minggu 208
, 1
458 .
10 2
25.275,76
2 minggu 3. Pekerjaan galian tanah :
Volume galian = 19.557,45 m
3
commit to user 174
Kemampuan pekerjaan per hari berdasar kuantitas kerja Excavator adalah 18,68 m³jam x 7 jam = 130,76 m
3
Kemampuan pekerjaan per minggu = 130,76 m
3
x 6 hari = 784,56 m
3
Misal digunakan 10 buah Excavator maka waktu yang dibutuhkan untuk pekerjaan galian :
minggu 493
, 2
56 ,
784 10
19.557,45 3 minggu
4. Pekerjaan timbunan tanah setempat : Volume timbunan = 41.598,28 m
3
Kemampuan pekerjaan per hari berdasar kuantitas kerja Whell Loader diperkirakan = 56,03 m³jam x 7 jam = 392,21 m
3
Kemampuan pekerjaan per minggu = 392,21 m
3
x 6 hari = 2.353,26 m
3
Misal digunakan 2 buah Whell Loader maka waktu yang dibutuhkan untuk pekerjaan timbunan :
minggu 838
, 8
26 ,
353 .
2 2
41.598,28 9 minggu
5.3.3. Pekerjaan Drainase
1. Pekerjaan galian saluran drainase : Volume galian saluran = 6.680 m
3
Kemampuan pekerjaan per hari berdasar kuantitas kerja Excavator adalah 18,68 m³jam x 7 jam = 130,76 m
3
Kemampuan pekerjaan per minggu = 130,76 m
3
x 6 hari = 784,56 m
3
Misal digunakan 2 buah Excavator maka waktu yang dibutuhkan untuk pekerjaan galian :
minggu 257
, 4
56 ,
784 2
6.680 5 minggu
2. Pekerjaan pasangan batu dengan mortar : Volume pasangan batu = 2.939,2 m
3
Kemampuan pekerjaan per hari diperkirakan 150 m
3
Kemampuan pekerjaan per minggu = 150 x 6 = 900 m
3
commit to user 175
Waktu yang dibutuhkan untuk pekerjaan pasangan batu :
minggu
266 ,
3 900
2.939,2
4 minggu 3. Pekerjaan plesteran :
Volume plesteren = 2672,00 m
2
Kemampuan pekerjaan per hari diperkirakan 150 m
2
Kemampuan pekerjaan per minggu = 150 x 6 = 900 m
2
Waktu yang dibutuhkan untuk pekerjaan plesteran : =
900 2.672,00
2,969 minggu ≈ 3 minggu
4. Pekerjaan siaran : Volume siaran = 12.360,00 m
2
Kemampuan pekerjaan per hari diperkirakan 150 m
2
Kemampuan pekerjaan per minggu = 150 x 6 = 900 m
2
Waktu yang dibutuhkan untuk pekerjaan siaran : =
900
13.360,00
14, 844 minggu ≈ 15 minggu
5.3.4. Pekerjaan Dinding Penahan
1. Pekerjaan Galian Pondasi Volume galian pondasi = 1.345,637 m³
Kemampuan pekerjaan per hari berdasar kualitas kerja Excavator adalah 18,68m³jam x 7 jam = 130,76 m
3
Kemampuan pekerjaan per minggu = 130,76 m
3
x 6 hari = 784,56 m
3
Misal digunakan 2 buah Excavator maka waktu yang dibutuhkan untuk pekerjaan galian :
minggu 858
, 56
, 784
2 1.345,637
1 minggu 2. Pekerjaan Pasangan Batu pada Dinding Penahan
Volume pasangan batu = 2.669,966 m³ Kemampuan pekerjaan per hari diperkirakan 150 m
2
commit to user 176
Kemampuan pekerjaan per minggu = 150 x 6 = 900 m
2
Waktu yang dibutuhkan untuk pekerjaan pasangan batu: =
900 2.669,966
2,967 minggu ≈ 3 minggu
3. Pekerjaan Plesteran Luas plesteran= 1.758,497 m
2
Kemampuan pekerjaan per hari diperkirakan 150 m
2
Kemampuan pekerjaan per minggu = 150 x 6 = 900 m
2
Waktu yang dibutuhkan untuk pekerjaan pasangan batu: =
900 1.758,497
1,954 minggu ≈ 2 minggu
4. Pekerjaan Siaran Luas siaran= 2.291,679 m
2
Kemampuan pekerjaan per hari diperkirakan 150 m
2
Kemampuan pekerjaan per minggu = 150 x 6 = 900 m
2
Waktu yang dibutuhkan untuk pekerjaan pasangan batu: =
900 2.291,679
2,546 minggu ≈ 3 minggu
5.3.5. Pekerjaan Perkerasan
1. Pekerjaan LASTON : Volume = 1. 805,40 m
3
Kemampuan pekerjaan per hari berdasar kuantitas kerja Asphalt Finisher diperkirakan 14,43 x 7 jam = 101,01 m
3
Kemampuan pekerjaan per minggu = 101,01 x 6 = 606,06 m
3
Maka waktu yang dibutuhkan untuk pekerjaan LASTON =
minggu 979
, 2
06 ,
606 1.805,40
3 minggu
commit to user 177
2. Pekerjaan Prime Coat : Luas volume perkerjaan untuk Prime Coat adalah 24.310,00 m
2
Kemampuan pekerjaan per hari berdasar kuantitas kerja Asphalt Sprayer diperkirakan 2.324 m
2
Kemampuan pekerjaan per minggu = 2.324 x 6 = 13.944 m
2
Waktu yang dibutuhkan untuk pekerjaan prime coat :
minggu
743 ,
1 944
. 13
24.310,00
2 minggu
3. Pekerjaan LPA Lapis Pondasi Atas : Volume = 4.998,00 m
3
Kemampuan pekerjaan per hari berdasar kuantitas kerja Whell Loader diperkirakan = 16,01 m³ x 7 jam = 112,07 m
3
Kemampuan pekerjaan per minggu = 112,07 m
3
x 6 hari = 672,42 m
3
Waktu yang dibutuhkan untuk pekerjaan LPA :
minggu 433
, 7
42 ,
672 4.998,00
8 minggu
4. Pekerjaan LPB Lapis Pondasi Bawah : Volume = 8.007,00 m³
Kemampuan pekerjaan per hari berdasar kuantitas kerja Vibro roller diperkirakan = 21 m³ x 7 jam = 147 m
3
Kemampuan pekerjaan per minggu = 147 m
3
x 6 hari = 882 m
3
Waktu yang dibutuhkan untuk pekerjaan LPB :
minggu
8 07
, 9
882 8.007,00
10 minggu
commit to user 178
5.3.6. Pekerjaan Pelengkap
1. Pekerjaan marka jalan : Luas = 181,584 m
2
Kemampuan pekerjaan per hari berdasar kuantitas tenaga kerja diperkirakan 93,33 m
2
Kemampuan pekerjaan per minggu = 93,33 x 6 = 559,98 m
2
Waktu yang dibutuhkan untuk pekerjaan marka : =
324
, 98
, 559
181,584 1 minggu
2. Pekerjaan rambu jalan diperkirakan selama 1 minggu. 3. Pembuatan patok kilometer diperkirakan selama 1 minggu.
4. Pembuatan patok pengaman diperkirakan selama 1 minggu.
commit to user 179
5.4. Analisa Perhitungan Harga Satuan Pekerjaan
Perhitungan harga satuan pekerjaan dihitung dengan cara mengalikan volume dengan upah atau harga tenaga material dan peralatan,kemudian dijumlah
dikalikan 10 Overhead dan Profit.Hasil dari jumlah biaya ditambah dengan hasil Overhead dan Profit dinamakan Harga Satuan Pekerjaan.
Contoh perhitungan pekerjaan penyiapan badan jalan:
Diketahui : a. Tenaga
1. Pekerja jam ; Volume 0,0161 ; Upah Rp 5.500,00 Biaya = Volume x Upah
= 0,0161 x 5.500,00 = 88,55
2. Mandor jam ; Volume 0,004 ; Upah Rp 9.000,00 Biaya = Volume x Upah
= 0,004 x 9.000,00 = 36,00
Total biaya tenaga = 124,55 b. Peralatan
1. Motor Grader jam ; Volume 0,0025 ; Harga Rp 220.000,00 Biaya = Volume x Upah
= 0,0025 x 220.000,00 = 550,00
commit to user 180
2. Vibro Roller jam ; Volume 0,004 ; Harga Rp 170.000,00 Biaya = Volume x Upah
= 0,004 x 170.000,00 = 680,00
3. Water Tanker jam ; Volume 0,0105 ; Harga Rp 108.000,00 Biaya = Volume x Upah
= 0,0105 x 108.000,00 = 1.134,00
4. Alat Bantu Ls ; Volume 1 ; Harga Rp 150,00 Biaya = Volume x Upah
= 1 x 150,00 = 150,00
Total biaya peralatan = 2514,00
Total biaya tenaga dan peralatan = 2638,55 A Overhead dan Profit 10 x A = 263,86 B
Harga Satuan Pekerjaan A + B = 2902,41 Untuk hasil penghitungan selanjutnya dapat dilihat di Lampiran.
commit to user 181
5.4.1 Bobot Pekerjaan Perhitungan bobot pekerjaan dihitung dengan mengalikan volume tiap pekerjaan
dengan harga satuan tiap pekerjaan. Bobot = Volume
Harga satuan Contoh perhitungan untuk pekerjaan persiapan badan jalan :
Bobot pekerjaan persiapan badan jalan = Volume pekerjaan
Harga satuan = 35061
2902,41 = 101.761.397,010
5.4.2 Persen Bobot Pekerjaan Perhitungan persen bobot pekerjaan dihitung dengan membandingkan bobot
tiap pekerjaan dengan bobot total pekerjaan dikalikan 100 Bobot pekerjaan =
100 total
Bobot pekerjaan
Bobot
Contoh perhitungan untuk pekerjaan persiapan badan jalan : Bobot pekerjaan persiapan badan jalan =
100 total
Bobot pekerjaan
Bobot
= 100
.386,21 17.379.529
7,01 101.761.39
= 0,586 Untuk hasil penghitungan selanjutnya dapat dilihat di Lampiran.
commit to user 182
Tabel 5.5. Rekapitulasi Perkiraan Waktu Pekerjaan
No Nama Pekerjaan
Volume Pekerjaan Kemampuan
Kerja per hari
Kemampuan Kerja
per minggu Waktu
Pekerjaan minggu
1 Pengukuran
Ls -
- 3
2 Mobilisasi dan Demobilisasi
Ls -
- 3
3 Pembuatan papan nama proyek
Ls -
- 1
4 Pekerjaan Direksi Keet
Ls -
- 2
5 Administrasi dan Dokumentasi
Ls -
- Selama
proyek 6
Pembersihan semak pengupasan tanah 33.149,49 m
2
900,00 m2 5.400,00 m
2
7 7
Persiapan badan jalan 25.275,76
m
2
1.743,00 m
2
10.458,00 m
2
2 8
Galian tanah 19.557,45
m
3
130,76 m
3
784,56 m
3
3 9
Timbunan tanah 41.598,28 m
3
392,21 m
3
2.353,26 m
3
9 10 Drainase :
a. Galian saluran 6.680,00
m
3
130,76 m
3
784,56 m
3
5 b. Pasangan batu dengan mortar
2.939,20 m
3
150 m
3
900 m
3
4 c Plesteran
2.672,00 m
2
150 m
3
900 m
3
3 d. Siaran
12.360,00 m
2
150 m
3
900 m
3
15 11 Dinding penahan :
a Galian Pondasi Pada Dinding Penahan 1.345,637 m
3
130,76 m
3
784,56 m
3
1 b. Pasangan batu dengan mortar
2.669,966 m
3
150 m
3
900 m
3
3 c. Plesteran
1.758,497 m
2
150 m
3
900 m
3
2 d. Siaran
2.291,679 m
2
150 m
3
900 m
3
3 12 Lapis Pondasi Bawah LPB
8.007,00 m
3
147 m
3
882 m
3
10 13 Lapis Pondasi Atas LPA
4.998,00 m
3
112,07 m
3
672,42 m
3
8 14 Lapis Permukaan LASTON
1. 805,40 m
3
101,01 m
3
606,06 m
3
3 15 Prime Coat
24.310,00 m
2
2324,00 m
2
13.944,00 m
2
2 16 Pelengkap
a. Marka jalan 181,584
m
2
93,33 m
2
559,98 m
2
1 b. Rambu
- -
- 1
c. Patok -
- -
1
commit to user 183
Dari hasil analisis perhitungan waktu pelaksanaan, analisis harga satuan pekerjaan dan perhitungan bobot pekerjaan, maka dapat dibuat Rencana Anggaran Biaya
RAB dan Time Schedule pelaksanaan proyek dalam bentuk Bar Chard dan Kurva S.
commit to user 184
5.6. REKAPITULASI RENCANA ANGGARAN BIAYA