Pembebanan Balok Bordes  Beban mati qD Perhitungan Tulangan Geser

commit to user Tugas Akhir 110 Perencanaan Struktur dan Rencana Anggaran Biaya Gedung Asrama 2 Lantai Bab 4 Perencanaan Tangga

4.5.1. Pembebanan Balok Bordes  Beban mati qD

Berat sendiri = 0,20 x 0,30 x 2400 = 144 kgm Berat dinding = 0,15 x 2 x 1700 = 510 kgm Berat plat bordes = 0,15 x 2400 x 1 = 360 kgm qD =1014 kgm  Akibat beban hidup qL qL = 300 kgm  Beban ultimate qU qU = 1,2 . qD + 1,6. qL = 1,2 . 1014 + 1,6.300 = 1696,8 kgm  Beban reaksi bordes qU = bordes lebar bordes aksi Re = 1 48 , 1491 = 1491,48 kgm  qU Total = 1696,48 + 1491,48 = 3187,96 kgm 4.5.2. Perhitungan tulangan lentur M u = . 11 1 qu.L 2 = 11 1 . 3187,96 .3 2 = 2608,331 kgm = 2,608.10 7 Nmm Mn = Mu = 8 , 10 . 608 , 2 7 3,26 . 10 7 Nmm m = 412 , 9 30 . 85 , 240 . 85 , fc fy commit to user Tugas Akhir 111 Perencanaan Struktur dan Rencana Anggaran Biaya Gedung Asrama 2 Lantai Bab 4 Perencanaan Tangga b = fy 600 600 . . fy fc . 85 , = 240 600 600 . 85 , . 240 30 . 85 , = 0,065 max = 0,75 . b = 0,0488 min = 0058 , 240 4 , 1 4 , 1 fy Rn = 2 .d b Mn 2 7 244 . 200 10 . 26 , 3 2,74 Nmm ada = fy 2.m.Rn 1 1 m 1 = . 412 , 9 1 240 74 , 2 . 412 , 9 . 2 1 1 = 0,012 ada min max di pakai ada = 0,012 As = ada . b . d = 0,012 x 200 x 244 = 585,6 mm 2 Dipakai tulangan 12 mm = ¼ . x 12 2 = 113,04 mm 2 Jumlah tulangan = 113,04 585,6 = 5,18 ≈ 6 buah As yang timbul = 6. ¼ .π. d 2 = 678,24 mm 2 As 585,6........ aman Dipakai tulangan 6 12 mm commit to user Tugas Akhir 112 Perencanaan Struktur dan Rencana Anggaran Biaya Gedung Asrama 2 Lantai Bab 4 Perencanaan Tangga

4.5.3. Perhitungan Tulangan Geser

Vu = ½ . qU . L = ½. 3187,96 .3 = 4781,94 kg = 47819,4 N Vc = . c f b.d. . 6 1 = 16 . 200 . 244. 30 = 44548,101 N Vc = 0,6 . Vc = 26728,861 N 3 Vc = 3 . Vc = 80186,583 N Syarat tulangan geser : Ø Vc Vu 3Ø Vc : 26728,861 N 47819,4 N 80186,583 N Jadi diperlukan tulangan geser Ø Vs = Vu – Ø Vc = 47819,4 – 26728,861 = 21090,539 N Vs perlu = 6 , Vs = 6 , 21090,539 = 35150,898 N Digunakan sengkang 10 Av = 2 . ¼ 10 2 = 2. ¼ . 3,14 . 100 = 157 mm 2 s = 35150,898 244 . 240 . 157 perlu Vs d . fy . Av 261,556 mm ~ 200 mm s max = d2 = 2 244 = 122 mm ~ 120 mm Vs ada = 76616 120 244 240 157 S d . fy . Av N Vs ada Vs perlu 76616 35150,898...... aman Jadi dipakai sengkang dengan tulangan Ø 10 – 120 mm commit to user Tugas Akhir 113 Perencanaan Struktur dan Rencana Anggaran Biaya Gedung Asrama 2 Lantai Bab 4 Perencanaan Tangga

4.6. Perhitungan Pondasi Tangga