Penghitungan Volume Pekerjaan Tanah

commit to user

BAB V RENCANA ANGGARAN BIAYA DAN

TIME SCHEDULE

5.1 Typical Potongan Melintang

Gambar 5.1 Potongan Melintang Jalan

5.2 Analisa Perhitungan Volume Pekerjaan

5.2.1. Penghitungan Volume Pekerjaan Tanah

1. Pembersihan Semak dan Pengupasan Tanah. Luas = Lebar Badan Jalan x p. Jalan – p. Jembatan Total = 11 m x 3087 m – 50 m = 33.407 m² 2. Persiapan Badan Jalan m² . Luas = Lebar lapis pondasi bawah x Panjang jalan – p. Jembatan total = 8,15 m x 3087 m – 50 m = 25.109,05 m² commit to user 3. Galian Tanah Biasa m³ Contoh penghitungan : STA 2+000 Bahu Jalan Drainase Bahu Jalan Lebar Perkerasan Jalan 2m 0.5m 3 x 0.5m 2m 2 x 3,5m 0.5m Drainase 0.5m 3 x 0.5m 0.5m STA 2+000 -4 -2 -2 -4 2 : 1 155.01 154.88 154.79 155.14 155.23 153.28 154.72 155.30 153.21 153.13 153.13 153.13 153.13 153.21 1 2 3 4 5 6 7 8 Gambar 5.2 Tipical Cross Section STA 2+000 H1 = 154.72 – 153.13 = 1.59 H2 = 154.79 – 153.13 = 1.66 H3 = 154.88 – 153.21 = 1.67 H4 = 155.01 – 153.28 = 1.73 H5 = 155.14 – 153.21 = 1.93 H6 = 155.23 – 153.13 = 2.1 H7 = 155.30 – 153.13 = 2.17 ¤ Perhitungan Luas 2 62 . 1 2 1 1 m H a Luas     2 063 . 4 5 , 2 2 2 1 2 m H H Luas           2 33 . 3 2 2 3 2 3 m H H Luas           2 95 . 5 5 , 3 2 4 3 4 m H H Lua s           commit to user 2 405 . 6 5 , 3 2 5 4 5 m H H Luas           2 03 . 4 2 2 6 5 6 m H H Lua s           2 338 . 5 5 , 2 2 7 6 7 m H H Luas           2 199 . 1 7 2 1 8 m H a Luas       2 m 30.935 Galian Total L 4. Timbunan Tanah Biasa m³ Contoh penghitungan : STA 1 + 300 -4 -2 -2 -4 2 : 1 153.28 153.21 153.13 151.42 151.40 151.38 151.44 151.45 153.21 153.13 STA 1+300 Bahu Jalan Bahu Jalan Lebar Perkerasan Jalan 2m 2m 2 x 3,5m Drainase 0.5m 3 x 0.5m 0.5m Drainase 0.5m 3 x 0.5m 0.5m Talud Talud 2 1 3 4 5 6 Gambar 5.3 Tipical Cross Section STA 1 + 300 H1 = 153.13 – 151.38 = 1.75 H2 = 153.21 – 151.40 = 1.81 H3 = 153.28 – 151.42 = 1.86 H4 = 153.21 – 151.44 = 1.77 H5 = 153.13 – 151.45 = 1.68 commit to user ¤ Perhitungan Luas 2 766 . 1 2 1 2 1 1 m H H Luas           2 56 . 3 2 2 2 1 2 m H H Lua s           2 423 . 6 5 , 3 2 3 2 3 m H H Luas           2 353 . 6 5 , 3 2 4 3 4 m H H Luas           2 45 . 3 2 2 5 4 5 m H H Luas           2 706 . 5 2 5 2 1 6 m H H Luas             2 21.258m Timbunan Ltota l Untuk hasil penghitungan selanjutnya disajikan dalam Tabel 5.1 commit to user Tabel. 5.1 Hasil perhitungan volume galian dan timbunan NO STA JARAK LUAS m² VOLUME m³ m GALIAN TIMBUNAN GALIAN TIMBUNAN 1 0+000 1,515 50 208,100 2 0+050 6,809 50 475,125 3 0+100 12,196 50 584,225 4 0+150 11,173 50 521,350 5 0+200 9,681 50 459,875 6 0+250 8,714 50 430,850 7 0+300 8,520 50 401,900 8 0+350 7,556 50 356,750 9 0+400 6,714 50 311,025 10 0+450 5,727 50 253,575 11 0+500 4,416 50 200,925 12 0+550 3,621 50 160,950 13 0+600 2,817 32,02 77,216 14 0+632,02 2,006 17,98 30,395 1,420 15 0+650 1,375 0,158 5,71 8,882 1,476 16 0+655,71 1,736 0,359 23,19 30,309 13,891 17 0+678,90 0,878 0,839 21,1 16,954 22,018 18 0+700 0,729 1,248 3,12 2,187 4,026 Bersambung ke halaman berikutnya commit to user 19 0+703,12 0,673 1,333 46,88 23,088 93,549 20 0+750 0,312 2,658 50 7,800 127,350 21 0+800 2,436 50 172,500 22 0+850 4,464 6,07 27,339 23 0+856,07 4,544 23,53 105,332 24 0+879,60 4,409 20,4 76,367 25 0+900 3,078 3,47 10,741 26 0+903,47 3,113 23,7 75,449 27 0+927,17 3,254 22,83 71,526 28 0+950 3,012 50 116,675 29 1+000 1,655 50 244,825 30 1+050 8,138 50 446,050 31 1+100 9,704 50 575,075 32 1+150 13,299 50 708,675 33 1+200 15,048 50 884,225 34 1+250 20,321 50 1039,475 35 1+300 21,258 33 582,021 36 1+333 14,016 17 228,948 37 1+350 12,919 16,83 216,467 38 1+366,83 12,805 Sambungan Tabel 5.1 Hasil perhitungan volume galian dan timbunan Bersambung ke halaman berikutnya commit to user 33,17 442,106 39 1+400 13,852 0,7 9,722 40 1+400,70 13,925 49,3 748,423 41 1+450 16,437 13,6 227,134 42 1+463,60 16,965 36,4 623,113 43 1+500 17,272 26,49 449,615 44 1+526,49 16,674 23,51 369,178 45 1+550 14,732 10,36 145,423 46 1+560,36 13,342 33,94 382,690 47 1+594,30 9,209 5,7 52,494 48 1+600 9,210 50 359,450 49 1+650 5,168 50 129,200 50 1+700 50 265,125 51 1+750 10,605 50 310,800 52 1+800 1,827 50 22,175 45,675 53 1+850 0,887 50 275,375 54 1+900 10,128 50 723,175 55 1+950 18,799 50 1243,350 56 2+000 30,935 50 1436,350 57 2+050 26,519 50 1265,925 Sambungan Tabel 5.1 Hasil perhitungan volume galian dan timbunan Bersambung ke halaman berikutnya commit to user 58 2+100 24,118 50 933,725 59 2+150 13,231 50 931,475 60 2+200 24,028 3,5 84,404 61 2+203,50 24,203 15,46 369,772 62 2+218,96 23,633 21,85 513,213 63 2+240,81 23,343 9,19 217,256 64 2+250 23,938 24,6 559,133 65 2+274,60 21,520 25,4 548,919 66 2+300 21,702 10,1 216,297 67 2+310,10 21,129 39,9 832,793 68 2+350 20,615 11,19 219,128 69 2+361,19 18,550 11,85 212,873 70 2+373,04 17,378 8,16 139,822 71 2+381,20 16,892 18,8 294,963 72 2+400 14,487 50 590,900 73 2+450 9,149 50 341,700 74 2+500 4,519 50 213,900 75 2+550 4,037 50 288,200 76 2+600 7,491 50 520,725 77 2+650 13,338 Sambungan Tabel 5.1 Hasil perhitungan volume galian dan timbunan Bersambung ke halaman berikutnya commit to user 50 726,250 78 2+700 15,712 50 892,375 79 2+750 19,983 50 1038,700 80 2+800 21,565 50 1125,875 81 2+850 23,470 50 896,475 82 2+900 12,389 50 716,700 83 2+950 16,279 50 747,850 84 3+000 13,635 50 646,275 85 3+050 12,216 37 316,369 15,910 86 3+087 4,885 0,860 TOTAL 24663,899 10421,481 Total Volume Galian = 24.663,899 m 3 Total Volume Timbunan = 10,421,481 m 3 Contoh perhitungan Volume Galian STA 0+450 s.d 0+500 Jarak : 0+450 – 0+500 = 50 m Jarak LuasSTA LuasSTA V      2 500 .. 450 .. = 50 2 4,416 5,727   = 253,575 m 3 Sambungan Tabel 5.1 Hasil perhitungan volume galian dan timbunan commit to user Contoh perhitungan Volume Timbunan STA 1+050 s.d 1+100 Jarak : 1+050 – 1+100 = 50 m Jarak LuasSTA LuasSTA V      2 100 1 .. 050 1 .. = 50 2 704 , 9 138 , 8   = 446,050 m 3

5.2.2. Penghitungan Volume Pekerjaan Drainase