BAB V RENCANA ANGGARAN BIAYA DAN
TIME SCHEDULE
5.1 Typical Potongan Melintang
Gambar 5.1 Potongan Melintang Jalan
5.2 Analisa Perhitungan Volume Pekerjaan
5.2.1. Penghitungan Volume Pekerjaan Tanah
1. Pembersihan Semak dan Pengupasan Tanah. Luas
= Lebar Badan Jalan x p. Jalan – p. Jembatan Total
= 11 m x 3087 m – 50 m
= 33.407 m² 2. Persiapan Badan Jalan m² .
Luas = Lebar lapis pondasi bawah x Panjang jalan
– p. Jembatan total
= 8,15 m x 3087 m – 50 m
= 25.109,05 m²
commit to user 3. Galian Tanah Biasa m³
Contoh penghitungan : STA 2+000
Bahu Jalan Drainase
Bahu Jalan Lebar Perkerasan Jalan
2m
0.5m
3 x 0.5m 2m
2 x 3,5m
0.5m
Drainase
0.5m
3 x 0.5m
0.5m
STA 2+000
-4 -2
-2 -4
2 :
1
155.01 154.88
154.79 155.14
155.23
153.28 154.72
155.30
153.21 153.13
153.13 153.13
153.13 153.21
1 2
3 4
5 6
7 8
Gambar 5.2
Tipical Cross Section
STA 2+000
H1 = 154.72 – 153.13
= 1.59 H2 = 154.79
– 153.13 = 1.66
H3 = 154.88 – 153.21
= 1.67 H4 = 155.01
– 153.28 = 1.73
H5 = 155.14 – 153.21
= 1.93 H6 = 155.23
– 153.13 = 2.1
H7 = 155.30 – 153.13
= 2.17
¤ Perhitungan Luas
2
62 .
1 2
1 1
m H
a Luas
2
063 .
4 5
, 2
2 2
1 2
m H
H Luas
2
33 .
3 2
2 3
2 3
m H
H Luas
2
95 .
5 5
, 3
2 4
3 4
m H
H Lua s
commit to user
2
405 .
6 5
, 3
2 5
4 5
m H
H Luas
2
03 .
4 2
2 6
5 6
m H
H Lua s
2
338 .
5 5
, 2
2 7
6 7
m H
H Luas
2
199 .
1 7
2 1
8
m H
a Luas
2
m 30.935
Galian
Total
L
4. Timbunan Tanah Biasa m³ Contoh penghitungan : STA 1 + 300
-4 -2
-2 -4
2 : 1
153.28 153.21
153.13
151.42 151.40
151.38 151.44
151.45 153.21
153.13
STA 1+300
Bahu Jalan Bahu Jalan
Lebar Perkerasan Jalan 2m
2m 2 x 3,5m
Drainase
0.5m
3 x 0.5m
0.5m
Drainase
0.5m
3 x 0.5m
0.5m
Talud Talud
2 1
3 4
5 6
Gambar 5.3
Tipical Cross Section
STA 1 + 300
H1 = 153.13 – 151.38
= 1.75 H2 = 153.21
– 151.40 = 1.81
H3 = 153.28 – 151.42
= 1.86 H4 = 153.21
– 151.44 = 1.77
H5 = 153.13 – 151.45
= 1.68
commit to user
¤ Perhitungan Luas
2
766 .
1 2
1 2
1 1
m H
H Luas
2
56 .
3 2
2 2
1 2
m H
H Lua s
2
423 .
6 5
, 3
2 3
2 3
m H
H Luas
2
353 .
6 5
, 3
2 4
3 4
m H
H Luas
2
45 .
3 2
2 5
4 5
m H
H Luas
2
706 .
5 2
5 2
1 6
m H
H Luas
2
21.258m Timbunan
Ltota l
Untuk hasil penghitungan selanjutnya disajikan dalam Tabel 5.1
commit to user Tabel. 5.1 Hasil perhitungan volume galian dan timbunan
NO STA
JARAK LUAS m²
VOLUME m³ m
GALIAN TIMBUNAN GALIAN
TIMBUNAN
1 0+000
1,515 50
208,100 2
0+050 6,809
50 475,125
3 0+100
12,196 50
584,225 4
0+150 11,173
50 521,350
5 0+200
9,681 50
459,875 6
0+250 8,714
50 430,850
7 0+300
8,520 50
401,900 8
0+350 7,556
50 356,750
9 0+400
6,714 50
311,025 10
0+450 5,727
50 253,575
11 0+500
4,416 50
200,925 12
0+550 3,621
50 160,950
13 0+600
2,817 32,02
77,216 14
0+632,02 2,006
17,98 30,395
1,420 15
0+650 1,375
0,158 5,71
8,882 1,476
16 0+655,71
1,736 0,359
23,19 30,309
13,891 17
0+678,90 0,878
0,839 21,1
16,954 22,018
18 0+700
0,729 1,248
3,12 2,187
4,026 Bersambung ke halaman berikutnya
commit to user 19
0+703,12 0,673
1,333 46,88
23,088 93,549
20 0+750
0,312 2,658
50 7,800
127,350 21
0+800 2,436
50 172,500
22 0+850
4,464 6,07
27,339 23
0+856,07 4,544
23,53 105,332
24 0+879,60
4,409 20,4
76,367 25
0+900 3,078
3,47 10,741
26 0+903,47
3,113 23,7
75,449 27
0+927,17 3,254
22,83 71,526
28 0+950
3,012 50
116,675 29
1+000 1,655
50 244,825
30 1+050
8,138 50
446,050 31
1+100 9,704
50 575,075
32 1+150
13,299 50
708,675 33
1+200 15,048
50 884,225
34 1+250
20,321 50
1039,475 35
1+300 21,258
33 582,021
36 1+333
14,016 17
228,948 37
1+350 12,919
16,83 216,467
38 1+366,83
12,805 Sambungan Tabel 5.1 Hasil perhitungan volume galian dan timbunan
Bersambung ke halaman berikutnya
commit to user 33,17
442,106 39
1+400 13,852
0,7 9,722
40 1+400,70
13,925 49,3
748,423 41
1+450 16,437
13,6 227,134
42 1+463,60
16,965 36,4
623,113 43
1+500 17,272
26,49 449,615
44 1+526,49
16,674 23,51
369,178 45
1+550 14,732
10,36 145,423
46 1+560,36
13,342 33,94
382,690 47
1+594,30 9,209
5,7 52,494
48 1+600
9,210 50
359,450 49
1+650 5,168
50 129,200
50 1+700
50 265,125
51 1+750
10,605 50
310,800 52
1+800 1,827
50 22,175
45,675 53
1+850 0,887
50 275,375
54 1+900
10,128 50
723,175 55
1+950 18,799
50 1243,350
56 2+000
30,935 50
1436,350 57
2+050 26,519
50 1265,925
Sambungan Tabel 5.1 Hasil perhitungan volume galian dan timbunan
Bersambung ke halaman berikutnya
commit to user 58
2+100 24,118
50 933,725
59 2+150
13,231 50
931,475 60
2+200 24,028
3,5 84,404
61 2+203,50
24,203 15,46
369,772 62
2+218,96 23,633
21,85 513,213
63 2+240,81
23,343 9,19
217,256 64
2+250 23,938
24,6 559,133
65 2+274,60
21,520 25,4
548,919 66
2+300 21,702
10,1 216,297
67 2+310,10
21,129 39,9
832,793 68
2+350 20,615
11,19 219,128
69 2+361,19
18,550 11,85
212,873 70
2+373,04 17,378
8,16 139,822
71 2+381,20
16,892 18,8
294,963 72
2+400 14,487
50 590,900
73 2+450
9,149 50
341,700 74
2+500 4,519
50 213,900
75 2+550
4,037 50
288,200 76
2+600 7,491
50 520,725
77 2+650
13,338 Sambungan Tabel 5.1 Hasil perhitungan volume galian dan timbunan
Bersambung ke halaman berikutnya
commit to user 50
726,250 78
2+700 15,712
50 892,375
79 2+750
19,983 50
1038,700 80
2+800 21,565
50 1125,875
81 2+850
23,470 50
896,475 82
2+900 12,389
50 716,700
83 2+950
16,279 50
747,850 84
3+000 13,635
50 646,275
85 3+050
12,216 37
316,369 15,910
86 3+087
4,885 0,860
TOTAL 24663,899
10421,481
Total Volume Galian = 24.663,899 m
3
Total Volume Timbunan = 10,421,481 m
3
Contoh perhitungan Volume Galian STA 0+450 s.d 0+500 Jarak : 0+450
– 0+500 = 50 m
Jarak LuasSTA
LuasSTA V
2
500 ..
450 ..
=
50 2
4,416 5,727
= 253,575 m
3
Sambungan Tabel 5.1 Hasil perhitungan volume galian dan timbunan
commit to user Contoh perhitungan Volume Timbunan STA 1+050 s.d 1+100
Jarak : 1+050 – 1+100 = 50 m
Jarak LuasSTA
LuasSTA V
2
100 1
.. 050
1 ..
=
50 2
704 ,
9 138
, 8
= 446,050 m
3
5.2.2. Penghitungan Volume Pekerjaan Drainase