3.7.3. Perhitungan Pembebanan Kuda-kuda Utama A

Data-data pembebanan : Berat gording = 11 kgm Jarak antar kuda-kuda utama = 3 m Berat penutup atap = 50 kgm 2 Berat profil = 14,76 kgm Gambar 3.20. Pembebanan Kuda- kuda Utama A akibat Beban Mati

1. Beban Mati

1 Beban P1 = P9 a Beban gording = 38,5 kg b Beban atap = 353,5 kg c Beban plafon = 47,25 kg d Beban kuda-kuda = 35,853 kg e Beban plat sambung = 10,7559 kg f Beban bracing = 3,5853 kg commit to user 81 Tugas akhir 81 Perencanaan Struktur Gedung Lembaga Pendidikan dan Keterampilan 2 lantai Bab 3 Perencanaan Atap Yosep Denica K I8508078 2 Beban P2 = P8 a Beban gording = 38,5 kg b Beban atap = 302,75 kg c Beban kuda-kuda = 67,266 kg d Beban plat sambung = 20,1798 kg e Beban bracing = 6,7266 kg 3 Beban P3 = P7 a Beban gording = 38,5 kg b Beban atap = 294,5 kg c Beban kuda-kuda = 83,028 kg d Beban plat sambung = 24,9084 kg e Beban bracing = 8,3028 kg 4 Beban P4 = P6 a Beban gording = 30,25 kg b Beban atap = 238,3 kg c Beban kuda-kuda = 100,566 kg d Beban plat sambung = 30,1698 kg e Beban bracing = 10,0566 kg 5 Beban P5 a Beban gording = 22 kg b Beban atap = 97,515kg c Beban kuda-kuda = 76,812 kg d Beban plat sambung = 23,0436 kg e Beban bracing = 7,6812 kg commit to user 82 Tugas akhir 82 Perencanaan Struktur Gedung Lembaga Pendidikan dan Keterampilan 2 lantai Bab 3 Perencanaan Atap Yosep Denica K I8508078 6 Beban P10 = P16 a Beban plafon = 94,5 kg b Beban kuda-kuda = 42,957 kg c Beban plat sambung = 12,8871 kg d Beban bracing = 4,2957 kg 7 Beban P11 = P15 a Beban plafon = 91,98 kg b Beban kuda-kuda = 71,706 kg c Beban plat sambung = 21,512 kg d Beban bracing = 7,1706 kg 8 Beban P12 = P14 a Beban plafon = 74,434 kg b Beban kuda-kuda = 94,35 kg c Beban plat sambung = 28,305 kg d Beban bracing = 9,435 kg 9 Beban P13 a Beban plafon = 59,13 kg b Beban kuda-kuda = 138,306 kg c Beban plat sambung = 41,4918 kg d Beban bracing = 13,8306 kg Tabel 3.18. Rekapitulasi Beban Mati Kuda-kuda Utama Beban Beban Atap kg Beban gording kg Beban Bracing kg Beban Plat Penyambung kg Beban Plafon kg Jumlah Beban kg Input SAP kg P1=P9 353,5 38,5 3,5853 10,7559 47,25 453,59 454 P2=P8 302,75 38,5 6,7266 20,1798 - 368,156 369 P3=P7 294,5 38,5 8,3028 24,9084 - 366,211 367 commit to user 83 Tugas akhir 83 Perencanaan Struktur Gedung Lembaga Pendidikan dan Keterampilan 2 lantai Bab 3 Perencanaan Atap Yosep Denica K I8508078 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 29 28 27 26 25 24 23 22 21 20 19 18 17 W 1 W 2 W 3 W 4 W 5 W 6 W 7 W 8 W 9 W 10 P4=P6 283,3 30,25 10,0567 30,1698 - 353,7765 354 P5 97,515 22 7,6812 23,0436 - 150,24 151 P10=P16 - - 4,2957 12,8871 94,5 111,68 112 P11=P15 - - 7,1706 21,512 91,98 120,663 121 P12=P14 - - 9,435 28,305 74,434 112,174 113 P13 - - 13,8306 41,4918 59,13 114,452 115

2. Beban Hidup