commit to user 151
Tugas Akhir
Perencanaan Struktur Gedung Lembaga Pendidikan dan Keterampilan 2 lantai
Bab 6 Perencanaan Balok Anak
Yosep Denica K I8508078
Ø
Beban Mati qd Elemen As 3’ = As 8’ = G-H Beban plat
= 2 × 0,84 × 408 = 685,44 kgm’
Beban sendiri balok = 0,25 × 0,35 – 0,12 × 2400 = 138 kgm’
Beban dinding = 0,15 × 3 – 0,35 × 1700
= 675,75 kgm’ qD = 1499,19 kgm’
Ø Beban Hidup ql qL
= 2 × 0,84 × 250 = 420 kgm
2
6.5.2. Perhitungan Tulangan Balok Anak As 3’= As 8’= G-H
a. Tulangan lentur balok anak Data Perencanaan :
h = 350 mm
b = 250 mm
fy = 390 MPa Ulir
fy
s
= 240 MPa Polos f’c
= 20 MPa Ø
tulangan
= 16 mm Ø
sengkang
= 8 mm Tebal selimut p = 40 mm
d = h - p - 12 Ø
t
- Ø
s
= 350 – 40 – ½ . 16 – 8 = 294 mm
rb = 0,0226
r
max
= 0,75 . rb = 0,75 . 0,0226 = 0,0169
r
min
= 0,0035
1. Penulangan Daerah Lapangan
Dari Perhitungan SAP 2000 diperoleh momen terbesar : Mu = 4942,06 kgm= 4,942.10
7
Nmm Mn = 6,117.10
7
Nmm Rn = 2,83
m = 22,94
r =
÷ ÷
ø ö
ç ç
è æ
- -
fy 2.m.Rn
1 1
m 1
commit to user 152
Tugas Akhir
Perencanaan Struktur Gedung Lembaga Pendidikan dan Keterampilan 2 lantai
Bab 6 Perencanaan Balok Anak
Yosep Denica K I8508078
=
0079 ,
390 83
, 2
. 94
, 22
. 2
1 1
94 ,
22 1
= ÷
÷ ø
ö ç
ç è
æ -
-
r r
min
r r
max
®
dipakai tulangan tunggal Digunakan r
perlu
= 0,0079 As perlu = r . b . d
= 0,0079. 250 . 294 = 580,65 mm
2
n =
2
16 .
π .
4 1
perlu As
= tulangan
3 88
, 2
96 ,
200 580,65
» =
Kontrol Spasi : S
=
1 -
n sengkang
2 -
tulangan n
- 2p
- b
f f
=
1 3
8 .
2 -
16 3.
- 40
. 2
- 50
2 -
= 53 25 mm ..... OK
Jadi dipakai tulangan 3 D16 mm 2. Penulangan Daerah Tumpuan
Mu = 4942,06 kgm= 4,942.10
7
Nmm sama dengan penulangan daerah lapangan
Jadi dipakai tulangan 3 D16 mm
c Tulangan Geser Balok anak
Dari Perhitungan SAP 2000 diperoleh gaya geser : Vu
= 4942,06 kg = 49420,6 N f’c
= 20 MPa fy
= 240 MPa d
= 294 mm Vc
= 1 6 . c
f .b .d = 1 6 . 20 . 250 . 294 = 54782 N
Ø Vc = 0,75 . 54782 N = 41086,5 N
commit to user 153
Tugas Akhir
Perencanaan Struktur Gedung Lembaga Pendidikan dan Keterampilan 2 lantai
Bab 6 Perencanaan Balok Anak
Yosep Denica K I8508078
3 Ø Vc = 3 . 41086,5 = 123259,5 N
Syarat Tulangan Geser : Ø Vc Vu 3 Ø Vc Jadi diperlukan tulangan geser minimum:
S
max
≤ d2 ≤ 600 mm ØVs perlu = Vu – Ø Vc
= 49420,6 N – 41086,5 N = 8334,1 N Vs perlu
=
75 ,
perlu
Vs
f =
75 ,
8334,1 = 11112,14 N
Av = 2 . ¼ p 8
2
= 2 . ¼ . 3,14 . 64 = 100,48 mm
2
S =
02 ,
638 11112,14
294 .
240 .
48 ,
100 .
. =
=
perlu
Vs d
fy Av
mm S max
= d2 = 2942 = 147 mm
≈ 140 mm Di pakai S = 140 mm
Jadi dipakai sengkang dengan tulangan Ø8 – 140 mm 6.6.
Perencanaan Balok Anak As H’ = 5-7 6.6.1.
Pembebanan
Gambar 6.8. Lebar Equivalen Balok Anak As H’= 5-7
c. Dimensi Balok h = 112 . L
y
b = 23 . h = 112 × 3000
= 23 × 300 = 250 mm = 300 mm
= 200 mm d. Pembebanan Setiap Elemen
5 5
6
H 6
7
commit to user 154
Tugas Akhir
Perencanaan Struktur Gedung Lembaga Pendidikan dan Keterampilan 2 lantai
Bab 6 Perencanaan Balok Anak
Yosep Denica K I8508078
Ø Beban Mati Elemen As H’= 5-7 qd Berat sendiri balok = 0,175 × 0,25 – 0,12 × 2400
= 54,6 kgm’ Berat plat
= 2 × 0,5 + 0,68 × 408 = 685,44 kgm’
Berat dinding = 0,15× 4 – 0,25 × 1700
= 956,25 kgm’ qD = 1696,29 kgm’
Ø Beban Hidup ql qL = 2 × 0,5 + 0,68 × 250 = 420 kgm’
6.6.2.
Perhitungan Tulangan Balok Anak As H’= 5-7
a. Tulangan lentur balok anak Data Perencanaan :
h = 300 mm
b = 200 mm
fy = 390 MPa Ulir
fy
s
= 240 MPa Polos f’c
= 20 MPa Ø
tulangan
= 16 mm Ø
sengkang
= 8 mm Tebal selimut p = 40 mm
d = h – p – 12 Ø
t
– Ø
s
= 300 – 40 – ½ . 16 – 8 = 244 mm
rb = 0,0226 r
max
= 0,016 r
min
= 0,0035
1. Penulangan Daerah Lapangan Dari Perhitungan SAP 2000 diperoleh momen terbesar :