Hitungan Tulangan Lentur Sloof

commit to user 293 Penulangan Kolom 8 D16 Ø 10- 200

7.10. Penulangan Sloof

7.10.1. Hitungan Tulangan Lentur Sloof

Data perencanaan : h = 400 mm b = 250 mm p = 40 mm fy = 390 MPa = 25 MPa Ø t = 19 mm Ø s = 8 mm d = h - p - Ø s - ½.Ø t = 400 40 8 - ½.19 = 342,5 mm b = fy 600 600 fy c. 0,85.f = 390 600 600 85 , 390 25 . 85 , = 0,0281 commit to user 294 max = 0,75 . b = 0,75 . 0,0281 = 0,021 min = 0036 , 390 4 , 1 4 , 1 fy Daerah Tumpuan Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 131. Mu = 11265,31 kgm = 11,26531 × 10 7 Nmm Mn = Mu = 8 , 10 11,26531 7 = 14,08 × 10 7 Nmm Rn = 80 , 4 342,5 250 10 14,08 d . b Mn 2 7 2 m = 35 , 18 20 0,85 360 c 0,85.f fy = fy 2.m.Rn 1 1 m 1 = 390 80 , 4 35 , 18 2 1 1 35 , 18 1 = 0,0141 min max dipakai tulangan tunggal Digunakan = 0,0141 As perlu = . b . d = 0,0141 × 250 × 342,5 = 1207, 31 mm 2 Digunakan tulangan D 16 n = 39 , 283 1207,31 19 . 4 1 perlu As 2 = 4,26 5 tulangan commit to user 295 = 2 16 . 4 1 = 2 19 . 14 , 3 . 4 1 = 283,39 mm As ada = 5 × 283,39 = 1416,95 mm 2 Aman Ok Jadi dipakai tulangan 5 D 16 Cek jarak = 1 - n t - s 2 - p 2 - b 1 - 5 19 5. - 2.8 - 2.40 - 250 = 14,75 mm 25 mm dipakai tulangan 2 lapis d1 = 344 mm d2 = 342,5 30 9,5 = 303 mm d = 5 303 x 2 342,5 x 3 = 326,7 mm a = 250 25 85 , 390 1416,95 b c f 0,85 fy ada As = 104,02 Mn ada = As ada × fy d - 2 a = 1416,95 × 390 342,5 - 2 104,02 = 16,05 . 10 7 Nmm Mn ada Mn ......... Aman Daerah Lapangan Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 131. Mu = 6307,85 kgm = 6,30785 × 10 7 Nmm commit to user 296 Mn = Mu = 8 , 10 6,30785 7 = 7,88 × 10 7 Nmm Rn = 69 , 2 342,5 250 10 7,88 d . b Mn 2 7 2 m = 35 , 18 25 0,85 390 c 0,85.f fy = fy 2.m.Rn 1 1 m 1 = 390 69 , 2 35 , 18 2 1 1 35 , 18 1 = 0,0074 min max dipakai tulangan tunggal Digunakan = 0,0072 As perlu = . b . d = 0,0074 × 250 × 342,5 = 633,63 mm 2 Digunakan tulangan D 16 n = 39 , 283 633,63 19 . 4 1 perlu As 2 = 2,24 3 tulangan = 2 19 . 4 1 = 2 19 . 14 , 3 . 4 1 = 283,39 As ada = 3 × 283,39= 850,17 mm 2 Jadi dipakai tulangan 3 D 16 7.10.2 Perhitungan Tulangan Geser Sloof Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 131: Vu = 7719,58 kg =77195,8 N commit to user 297 Vc = 1 6 . c f .b .d = 1 6 . 25 .250.344 = 71666,67 N Vc = 0,75 . 71666,67 = 53750 N 3 Vc = 3 . 53750 = 80625 N Syarat tulangan geser : Ø Vc Vu 3 Ø Vc : 53750 N 77195,8 N 80625 N Jadi diperlukan tulangan geser Ø Vs = Vu Ø Vc = 77195,8 53750 = 23445,8 N Vs perlu = 75 , 23445,8 75 , Vs = 31261,07 N Av = 2 . ¼ 8 2 = 2 . ¼ . 3,14 . 64 = 100,48 mm 2 S = 37 , 265 31261,07 344 . 240 . 48 , 100 perlu Vs d . fy . Av mm S max = d2 = 2 344 = 172 mm Jadi dipakai sengkang dengan tulangan Ø 8 150 mm Tul. Tumpuan Tul. Lapangan 25 5 D 16 2 Ø 10 Ø 8 - 150 2 D 16 25 2 D 16 3 D 16 commit to user 298 Potongan tulangan Sloof 7.10.3. Hitungan Tulangan Lentur Sloof tanpa dinding Data perencanaan : h = 400 mm b = 250 mm p = 40 mm fy = 390 Mpa = 25 MPa Ø t = 16 mm Ø s = 8 mm d = h - p - Ø s - ½.Ø t = 400 40 8 - ½.16 = 344 mm b = fy 600 600 fy c. 0,85.f = 390 600 600 85 , 390 25 . 85 , = 0,0281 max = 0,75 . b = 0,75 . 0,0281 = 0,021 min = 0036 , 390 4 , 1 4 , 1 fy Daerah Tumpuan Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 172. Mu = 3262,12 kgm = 32,6212 × 10 7 Nmm Mn = Mu = 8 , 10 26212 , 3 7 = 4,07765× 10 7 Nmm Rn = 378329 , 1 344 250 10 07765 4, d . b Mn 2 7 2 commit to user 299 m = 35 , 18 25 0,85 390 c 0,85.f fy = fy 2.m.Rn 1 1 m 1 = 390 378 , 1 35 , 18 2 1 1 35 , 18 1 = 0,0037 min max dipakai tulangan tunggal Digunakan = 0,0037 As perlu = . b . d = 0,0037 × 20 × 344 = 318,2 mm 2 Digunakan tulangan D 16 n = 96 , 200 2 , 318 16 . 4 1 perlu As 2 = 1,58 2 tulangan = 2 16 . 4 1 = 2 16 . 14 , 3 . 4 1 = 200,96 mm As ada = 2 × 200,96 = 401,92 mm 2 Aman Ok Jadi dipakai tulangan 2 D 16 Daerah Lapangan Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 172. Mu = 1645,07 kgm = 1,64507 × 10 7 Nmm Mn = Mu = 8 , 10 64507 , 1 7 = 2,06 × 10 7 Nmm Rn = 70 , 344 250 10 2,06 d . b Mn 2 7 2 commit to user 300 m = 35 , 18 25 0,85 390 c 0,85.f fy = fy 2.m.Rn 1 1 m 1 = 390 70 , 35 , 18 2 1 1 35 , 18 1 = 0,0018 min max dipakai tulangan tunggal Digunakan = 0,0018 As perlu = . b . d = 0,0018 × 250 × 344 = 154,8 mm 2 Digunakan tulangan D 16 n = 96 , 200 8 , 154 16 . 4 1 perlu As 2 = 0,77 2 tulangan = 2 16 . 4 1 = 2 16 . 14 , 3 . 4 1 = 200,96 As ada = 2× 200,96 = 401,92 mm 2 Aman Ok Jadi dipakai tulangan 2 D 16 7.10.4 Perhitungan Tulangan Geser Sloof Tanpa Dinding Dari Perhitungan SAP 2000 diperoleh momen terbesar pada batang nomor 172: Vu = 2372,40 kg = 23272,4 N Vc = 1 6 . c f .b .d = 1 6 . 25 .250.344 = 71666,67 N commit to user 301 Vc = 0,75 . 71666,67 = 53750 N ½ Ø Vc = 0.5 . 53750 = 26875 N 3 Vc = 3 . 53750 = 161250 N Syarat tulangan geser : Vu ½ Ø Vc : 23272,4 N 26875 N Jadi diperlukan tulangan geser praktis S max = d2 = 2 344 = 172 mm Jadi dipakai sengkang dengan tulangan Ø 8 150 mm Potongan tulangan Sloof memanjang Tul. Tumpuan Tul. Lapangan 25 2 D 16 2 Ø 10 Ø 8 - 150 2 D 16 25 2 D 16 2 D 16 commit to user 302

BAB 8 PONDASI

8.1. Data Perencanaan

Gambar 8.1. Perencanaan Pondasi Dari perhitungan SAP 2000 pada Frame 107-1 diperoleh : - Pu = 103528,13 kg - Mu = 1142,14 kgm Data tanah pada kedalaman 2 meter : qa tegangan geser ijin = 2,0 kgcm 2 = 20000 kgm 2 tanah = 1,7 tm 3 = 1700 kgm 3 45 Lantai Kerja t = 10 cm Tanah Urug Pasir t = 5 cm 260 45 260