Coordinating team is tasked with:

Guideline for Developing Local Action Plan for Green House Gas Emission Reduction RAD-GRK 23 b. Providing directions and inputs to Working Groups on policies, programs and priorities of local development for RAD-GRK document development; c. Providing directions and agreement on Terms of Reference and Budget Plan RAB for RAD-GRK development; d. Submitting inal draft of RAD-GRK documents that have been prepared to the Secretariat of RAD-GRK at the central level for review of its completeness; e. Revising and completing inal draft of RAD-GRK documents that have been reviewed, for its enactment into Governor’s Regulation Pergub; f. Submitting the Pergub on RAD-GRK to the Minister of National Development Planning PPN Head of Bappenas and Minister of Internal Affairs.

2. Working Units are tasked with:

a. Formulating the scope of key substance of RAD-GRK documents according to the task sectors; b. Identifying and doing initial analysis, search, collection of materials, data and information needed to related parties data sources for developing key substance of RAD-GRK according to the task sectors; c. Conducting data processing and analysis on collected data and information for developing key substance of RAD-GRK according to the task sectors; d. Developing key substance of RAD-GRK document according to the format and structure systematization available in the guideline see Chapter 2,according to the task sectors; e. Making schedule and work plan of Working Group activities according to the task sectors; f. Submitting results of RAD-GRK key substance development according to the task sectors to Chairs through Secretary of Coordinating Team for RAD-GRK Development for consolidation with results of other working groups in order to produce a Provincial RAD-GRK document;

4.3. Work Mechanism

1. Coordinating Team organizes plenary sessions and work meetings according to the needs during the RAD-GRK development; 2. Working groups organize technical meetings according to the schedule and needs during the RAD-GRK development; 3. Head of Bappeda acting as Secretary of Coordinating Team consolidate the development of RAD-GRK documents that are prepared by each Working Group; 4. Final draft of RAD-GRK which has been developed by Provincial RAD- Local Action Plan for Green House Gas Emission Reduction RAD-GRK Guideline for Developing 24 GRK Coordinating Team will be consulted with the Secretariat for RAN- GRK at the central level before its enactment by Governors.

4.4. Schedule of RAD-GRK Development

Work schedule of RAD-GRK documents that will be carried out by Coordinating Team and Working Groups of RAD-GRK development can be seen in Table 4.2. No Activities Tasks Which Month 1-2 3-4 5-6 7-8 9

I. PREPARATION PHASE

1 Initial Preparation a. Team Formation TK b. Plenary Session I: Direction and Preparation TK, Pokja 2 Initial Identiication Pokja 3 Technical Preparation Pokja 4 Public Consultation: Preparation for TK, RAD-GRK Development Pokja,PM II.DATA COLLECTION PHASE 5 General Data and Information Pokja 6 Technical Data and Information Pokja 7 Data Collection of Public Institutions Pokja 8 Data Collection on People and Business Actors’ Institutions Pokja III.CALCULATION PHASE 9 Calculation of Baseline emission Pokja 10 Proposed Mitigation Actions Pokja 11 Local Institutional Mapping Pokja IV.ACTION PLAN FORMULATION PHASE 12 Consolidation of Pokja’s results a. Plenary Session II: Pokja’s results TK,Pokja b. Public Consultation: Inputs for TK, Action Plan Formulation Pokja, PM 13 Determination of Priority Scale TK, Pokja 14 Determination of GHG Emission Reduction Targets TK, Pokja 15 Formulation of RAD-GRK Implementation Strategies TK, Pokja

V. DETERMINATION

PHASE 16 Draft of Governor’s Regulation TK 17 Enactment of Governor’s Regulation TK 18 Dissemination of RAD-GRK TP, TT, PM NOTES: TK = Coordinating Team; Pokja = Working Group, PM = People’s Representatives Table 4.2. Schedule for RAD- GRK Document Development.