/ CHAPTER 6 PENGEMBANGAN ENERGI DALAM MENDUKUNG PERTUMBUHAN EKONOMI NASIONAL / ENERGY DEVELOPMENT FOR SUPPORTING NATIONAL ECONOMIC GROWTH

BAB 6 / CHAPTER 6 PENGEMBANGAN ENERGI DALAM MENDUKUNG PERTUMBUHAN EKONOMI NASIONAL / ENERGY DEVELOPMENT FOR SUPPORTING NATIONAL ECONOMIC GROWTH

Outlook Energi Indonesia 2012

6.1 Penambahan Kapasitas / Capacity Development Tabel 6.1 Proyeksi penambahan kapasitas /

Table 6.1 Projection of capacity development

Kapasitas Terpasang /

2011 - 2020 2021 - 2030 Infrastruktur /

Dasar / MP3EI Dasar / MP3EI

Base Kilang Minyak / Oil Refinery

Base

400 400 1200 Kilang LPG / LPG Plant

3.3 0.9 1 0 0 Kilang LNG / LNG Plant

MTPA

42.1 10.3 10.3 0 0 Receiving Terminal

MTPA

0 15 20 15 17 SPBG / CNG Filling Station

MTPA

1 36 46 40 32 Pelabuhan Batubara / Coal Port

MMSCFD

359 274 552 Kilang Pencairan Batubara / Coal Liquefaction Plant

0 0 0 100 100 Sumber / Source: MEMR (2008), PLN (2009, 2010), Kristijo dan Nugroho (2009), Soesilo (2009),

MBSD

Hadiwidjoyo (2011), Hermantoro (2010), Saryono (2010), Sojitz (2008).

In line with energy supply growth in penyediaan energi di masa depan maka

Sejalan dengan

pertumbuhan

the future, additional capacity will be akan diperlukan penambahan kapasitas

needed in key infrastructure facilities for infrastruktur penting bagi penyediaan

energy suppy, such as refineries, LPG plant, energi seperti kilang minyak, kilang LPG,

LNG plant, Floating Storage Receiving Unit kilang LNG, terminal penerima LNG

(FSRU), coal port and coal liquefaction terapung (FSRU), pelabuhan batubara

plant. The facilities that are urgently dan kilang pencairan batubara. Fasilitas

needed to secure energy supply in the yang sangat diperlukan segera dalam

future include oil refineries with pengembangan energi masa depan

additional capacity up to 70% (Base adalah kilang minyak masing-masing

scenario) and 138% (MP3EI scenario), dengan penambahan kapasitas mencapai

respectively. In addition, construction of 70% (Skenario Dasar) dan 138%

FSRU are needed to enable LNG import in (Skenario MP3EI). Disamping itu,

the future to secure gas supply in the penambahan FSRU diperlukan untuk

future with additional capacity up to 30 memungkinkan pasokan LNG impor

MTPA (Base scenario) and 37 MTPA untuk mendukung pasokan gas domestik

(MP3EI scenario).

sebesar 30 MTPA (Skenario Dasar) dan

37 MTPA (Skenario MP3EI)

Outlook Energi Indonesia 2012

Gambar 6.1 Proyeksi penambahan kapasitas pembangkit listrik / Figure 6.1

Projection of electricity generation capacity development

160 EBT Lainnya / Other NRE PP

140 Nuklir / Nuclear PP

120 Hidro / Hydro PP

100 Panas bumi / Geothermal PP Pembangkit Minyak / Oil fueled PP

Pembangkit Gas / Gas Fired PP 60

PLTU-Batubara / Coal Fired PP 40

Total

Dasar / Base

MP3EI

Dasar / Base

MP3EI

2011-2020

2021-2030

Pada kurun waktu 2011 sampai During 2011 – 2030 period, dengan 2030 diperlukan tambahan

additional electricity generation capacity kapasitas pembangkit listrik sesuai

will be needed up to 133 GW and 199 GW skenario Dasar maupun MP3EI masing-

according to the Base scenario and MP3EI masing mencapai 133 GW dan 199 GW,

scenario, respectively. Construction of new dimana pembangkit berbahan bakar

coal based power plant will dominate the batubara akan mendominasi dengan

supply of electrcity in the future reaching pangsa dikisaran 65% (skenario Dasar)

up to 65% (Base scenario) and 75% dan 75% (skenario MP3EI). Sedangkan

(MP3EI scenario). Meanwhile additional pembangkit berbasis EBT mempunyai

construction of NRE based power plants pangsa lebih dari mencapai 20% dari

have a prospect to contribute around 20% total penambahan kapasitas hingga 2030.

from total generation capacity by 2030.

Outlook Energi Indonesia 2012

6.2 Penambahan Investasi / Investment Development Gambar 6.2 Perbandingan investasi infrastruktur energi /

Figure 6.2 Comparison of investments in energy infrastruktur

70,000 SPBG / CNG Filling Station

60,000 Terminal Penerima LNG / LNG Receiving Terminal

Kilang LNG / LNG Plant

o n li

Kilang LPG / LPG Plant

il M

S D 28,929

Pelabuhan Batubara / Coal Port

Kilang Pencairan Batubara / Coal

Ju

Liquefaction Plant 20,000

Kilang Minyak / Oil Refinery

Total

Dasar / Base MP3EI / MP3EI Dasar / BASE MP3EI / MP3EI

2011 - 2020

2021 - 2030

Investasi yang diperlukan untuk Investments are required for penambahan

construction of new infrastructure infrastruktur penting dalam penyediaan

kapasitas

fasilitas

facisilites in energy supply reaching up to energi mencapai 47 milyar USD (skenario

47 billion USD (Base scenario) and 76 Dasar) dan 76 milyar USD (skenario

billion USD (MP3EI scenario). Most of the MP3EI). Sebagian besar kebutuhan

investments are needed to construct investasi diperlukan untuk penambahan

additional capacity for oil refineries kapasitas kilang minyak (sekitar 60%)

(approximately 60%) to meet domestic oil dalam rangka memenuhi kebutuhan BBM

fuels demand in the future. domestik di masa depan.

Outlook Energi Indonesia 2012

Gambar 6.3 Perbandingan investasi pembangkit listrik / Figure 6.3

Comparison of investments in power generation capacity

200,000

190,245

180,000 EBT Lainnya / Other NRE PP

160,000 Nuklir / Nuclear

140,000 Hidro / Hydro PP

120,000

112,774

Panas bumi / Geothermal PP

o li il

100,000 Pembangkit Minyak / Oil fueled PP

M / 83,550

D 80,000 76,054 Pembangkit Gas / Gas Fired PP

PLTU-Batubara / Coal Fired PP

Total

20,000

Dasar / Base

MP3EI

Dasar / Base

MP3EI

2011-2020

2021-2030

Total investasi untuk penambahan Total investments in constructing kapasitas pembangkit listrik di masa

additional power generation will reach depan mencapai 188 milyar USD

188 billion USD (Base Scenario) and 276 (Skenario Dasar) dan 276 milyar USD

billion USD (MP3EI Scenario). Most of the (Skenario MP3EI). Sebagian besar

investments will be for constructing investasi di pembangkit listrik adalah

addition capacity for coal power plants untuk pembangunan PLTU Batubara

(approximately 60%). (sekitar 60%)