/ CHAPTER 6 PENGEMBANGAN ENERGI DALAM MENDUKUNG PERTUMBUHAN EKONOMI NASIONAL / ENERGY DEVELOPMENT FOR SUPPORTING NATIONAL ECONOMIC GROWTH
BAB 6 / CHAPTER 6 PENGEMBANGAN ENERGI DALAM MENDUKUNG PERTUMBUHAN EKONOMI NASIONAL / ENERGY DEVELOPMENT FOR SUPPORTING NATIONAL ECONOMIC GROWTH
Outlook Energi Indonesia 2012
6.1 Penambahan Kapasitas / Capacity Development Tabel 6.1 Proyeksi penambahan kapasitas /
Table 6.1 Projection of capacity development
Kapasitas Terpasang /
2011 - 2020 2021 - 2030 Infrastruktur /
Dasar / MP3EI Dasar / MP3EI
Base Kilang Minyak / Oil Refinery
Base
400 400 1200 Kilang LPG / LPG Plant
3.3 0.9 1 0 0 Kilang LNG / LNG Plant
MTPA
42.1 10.3 10.3 0 0 Receiving Terminal
MTPA
0 15 20 15 17 SPBG / CNG Filling Station
MTPA
1 36 46 40 32 Pelabuhan Batubara / Coal Port
MMSCFD
359 274 552 Kilang Pencairan Batubara / Coal Liquefaction Plant
0 0 0 100 100 Sumber / Source: MEMR (2008), PLN (2009, 2010), Kristijo dan Nugroho (2009), Soesilo (2009),
MBSD
Hadiwidjoyo (2011), Hermantoro (2010), Saryono (2010), Sojitz (2008).
In line with energy supply growth in penyediaan energi di masa depan maka
Sejalan dengan
pertumbuhan
the future, additional capacity will be akan diperlukan penambahan kapasitas
needed in key infrastructure facilities for infrastruktur penting bagi penyediaan
energy suppy, such as refineries, LPG plant, energi seperti kilang minyak, kilang LPG,
LNG plant, Floating Storage Receiving Unit kilang LNG, terminal penerima LNG
(FSRU), coal port and coal liquefaction terapung (FSRU), pelabuhan batubara
plant. The facilities that are urgently dan kilang pencairan batubara. Fasilitas
needed to secure energy supply in the yang sangat diperlukan segera dalam
future include oil refineries with pengembangan energi masa depan
additional capacity up to 70% (Base adalah kilang minyak masing-masing
scenario) and 138% (MP3EI scenario), dengan penambahan kapasitas mencapai
respectively. In addition, construction of 70% (Skenario Dasar) dan 138%
FSRU are needed to enable LNG import in (Skenario MP3EI). Disamping itu,
the future to secure gas supply in the penambahan FSRU diperlukan untuk
future with additional capacity up to 30 memungkinkan pasokan LNG impor
MTPA (Base scenario) and 37 MTPA untuk mendukung pasokan gas domestik
(MP3EI scenario).
sebesar 30 MTPA (Skenario Dasar) dan
37 MTPA (Skenario MP3EI)
Outlook Energi Indonesia 2012
Gambar 6.1 Proyeksi penambahan kapasitas pembangkit listrik / Figure 6.1
Projection of electricity generation capacity development
160 EBT Lainnya / Other NRE PP
140 Nuklir / Nuclear PP
120 Hidro / Hydro PP
100 Panas bumi / Geothermal PP Pembangkit Minyak / Oil fueled PP
Pembangkit Gas / Gas Fired PP 60
PLTU-Batubara / Coal Fired PP 40
Total
Dasar / Base
MP3EI
Dasar / Base
MP3EI
2011-2020
2021-2030
Pada kurun waktu 2011 sampai During 2011 – 2030 period, dengan 2030 diperlukan tambahan
additional electricity generation capacity kapasitas pembangkit listrik sesuai
will be needed up to 133 GW and 199 GW skenario Dasar maupun MP3EI masing-
according to the Base scenario and MP3EI masing mencapai 133 GW dan 199 GW,
scenario, respectively. Construction of new dimana pembangkit berbahan bakar
coal based power plant will dominate the batubara akan mendominasi dengan
supply of electrcity in the future reaching pangsa dikisaran 65% (skenario Dasar)
up to 65% (Base scenario) and 75% dan 75% (skenario MP3EI). Sedangkan
(MP3EI scenario). Meanwhile additional pembangkit berbasis EBT mempunyai
construction of NRE based power plants pangsa lebih dari mencapai 20% dari
have a prospect to contribute around 20% total penambahan kapasitas hingga 2030.
from total generation capacity by 2030.
Outlook Energi Indonesia 2012
6.2 Penambahan Investasi / Investment Development Gambar 6.2 Perbandingan investasi infrastruktur energi /
Figure 6.2 Comparison of investments in energy infrastruktur
70,000 SPBG / CNG Filling Station
60,000 Terminal Penerima LNG / LNG Receiving Terminal
Kilang LNG / LNG Plant
o n li
Kilang LPG / LPG Plant
il M
S D 28,929
Pelabuhan Batubara / Coal Port
Kilang Pencairan Batubara / Coal
Ju
Liquefaction Plant 20,000
Kilang Minyak / Oil Refinery
Total
Dasar / Base MP3EI / MP3EI Dasar / BASE MP3EI / MP3EI
2011 - 2020
2021 - 2030
Investasi yang diperlukan untuk Investments are required for penambahan
construction of new infrastructure infrastruktur penting dalam penyediaan
kapasitas
fasilitas
facisilites in energy supply reaching up to energi mencapai 47 milyar USD (skenario
47 billion USD (Base scenario) and 76 Dasar) dan 76 milyar USD (skenario
billion USD (MP3EI scenario). Most of the MP3EI). Sebagian besar kebutuhan
investments are needed to construct investasi diperlukan untuk penambahan
additional capacity for oil refineries kapasitas kilang minyak (sekitar 60%)
(approximately 60%) to meet domestic oil dalam rangka memenuhi kebutuhan BBM
fuels demand in the future. domestik di masa depan.
Outlook Energi Indonesia 2012
Gambar 6.3 Perbandingan investasi pembangkit listrik / Figure 6.3
Comparison of investments in power generation capacity
200,000
190,245
180,000 EBT Lainnya / Other NRE PP
160,000 Nuklir / Nuclear
140,000 Hidro / Hydro PP
120,000
112,774
Panas bumi / Geothermal PP
o li il
100,000 Pembangkit Minyak / Oil fueled PP
M / 83,550
D 80,000 76,054 Pembangkit Gas / Gas Fired PP
PLTU-Batubara / Coal Fired PP
Total
20,000
Dasar / Base
MP3EI
Dasar / Base
MP3EI
2011-2020
2021-2030
Total investasi untuk penambahan Total investments in constructing kapasitas pembangkit listrik di masa
additional power generation will reach depan mencapai 188 milyar USD
188 billion USD (Base Scenario) and 276 (Skenario Dasar) dan 276 milyar USD
billion USD (MP3EI Scenario). Most of the (Skenario MP3EI). Sebagian besar
investments will be for constructing investasi di pembangkit listrik adalah
addition capacity for coal power plants untuk pembangunan PLTU Batubara
(approximately 60%). (sekitar 60%)
67
Outlook Energi Indonesia 2012
Halaman kosong / blank page
68
Outlook Energi Indonesia 2012