Civil Works Progress WINRIP DOC MPR CTC MPR No.54 2017 06 20170630 00493
Western I ndonesia National Roads I mprovement Project 4 - 5
Package No. 5 : Sp. Rampa Poriaha
The progress as of this month is only achieved of 62.37 against the scheduled 99.43. The completion date is 20, July 2017, thus the contractor is under preparation of another contract
amendment for the increase of contract value and the extension of time.
ANNEX P-5 Executive Summary Report shows the Contractor s Progress Schedule. Package No. 6 : Kerkap
Ps. Pedati
The contract package is completed on January 28, 2017 and provisionally handed over to the Employer and currently under Defects Notification Period until after two 2 years reckoned from the issuance of TOC.
ANNEX P-6 Executive Summary Report shows the complete details of the contract package. Package No. 7: Indrapura
Tapan
This month progress is sharply increased of 5.41 comparing the previous month progress, 1.59. Nevertheless the main reason of improved progress was due to suspended working time for crusher plants
allowed by the local people. However the completion date of the works is 30, August 2017, hence the contractor is preparing of the contract amendment of contract value and the extension of time including
additional works of 4 km which is situated in the project road.
ANNEX P-7 Executive Summary Report shows the complete details of the contract package. Package No. 8 : Bts. Kota Pariaman - Manggopoh
The progress as of this reporting month is achieved of 74.73 against the scheduled 73.96 having a little ahead 0.77.
Currently unsettled land acquisition, 133 paps is critical issue hampering remaining progress of the works
ANNEX P-8 Executive Summary Report shows the complete details of the contract package. Package No. 11 : Bantal - Mukomuko
The completion date is on 26, May 2017 and the inspection for the provisional hand-over is already done and the process verbal has been issued on 19, May 2017.
For more detailed of the Contract Package, refer to ANNEX P-11 Executive Summary Report . Package No. 12 : Kambang - Indrapura
The progress as of this month achieved of only 11.93 against the scheduled 77.90 having much lagged behind, -65.97.
The main reasons for delayed progress are likely same as before. The Contractor is doing his duty without any significant improvement of site operation inspite of huge delay of progress.
The client is still looking for a resolution about how to handle the contractor in accordance with the contract conditions and what to be the most realistic provisions and measures to be taken.
Details of the Contract Package are shown in ANNEX P-12 Executive Summary Report . Package No. 13 : Sp. Rukis
Tj. Kemuning
The progress as of this month, 50.29 is much lagged behind the scheduled, 97.87.
Western I ndonesia National Roads I mprovement Project 4 - 6
The completion date of this works is 10, July 2017. Hence, the contractor has proposed the extension of time for unsettled land acquisition of segment No. 2, about 18 km and segment No. 3, about 2 km as of the
end of May 2017.
Details of the work progress are shown in ANNEX P-13 Executive Summary Reports. Package No. 14: Painan - Kambang
The Progress as of this month is achieved of 32.89 against the scheduled 37.80 having slippage rate - 4.91.
The progress of Asphalt pavement of this month is only 1.42 which is much less than the previous month, 8.89 because of a little working areas for Asphalt paving works. Nevertheless this month progress of
preparatory work like pavement widening shoulders, granular pavement were done in very small areas. The contractor is repeatly advised to increase the work forces for widening teams to accommodate the
progress of Asphalt paving works.
ANNEX P-14 Executive Summary Report shows the complete details of the project. Package No. 15: Sibolga Bts. Tapsel
The progress as of this month is only 43.75 against the scheduled, 84.69 having slippage rate -40.94. The main reasons of delayed progress are unsettled land acquisition, 12.9 km and delay of relocating the
utilities of electrical poles PLN and water pipes PDAM.
The contractor had being advised to propose for design changes of typical sections in accordance with site situations utilizing the existing ROW Ave. 11m width for the areas which are situated un very densely
populated road.
Detailed and work progresses of the contract package are shown in ANNEX P-15 Executive Summary Report .
Package No. 16: Seblat Ipuh
This month progress has been achieved of 3.43 against the scheduled, 3.63 and the accumulated progress as of this months is 12.11 against the scheduled, 10.7 having ahead progress, 1.33.
The progress of this month was made with various works like Drainage, Earthworks, Structures, etc. But the pavement works are no progress.
The contractor has to concentrate for early start of asphalt paving works which is most major weight of the works reached at 53.56 from the total.
ANNEX P-16 Executive Summary Report shows the complete details and work progress of the project. Package No. 17 : Sp. Gunung Kemala
Pg. Tampak
The progress of this month is achieved of 4.80 against the scheduled, 4.02 having ahead of 0.78. Ac wearing course was started is this month and the working areas for AC-WC is in large stretches which
could be constructed for 2 or 3 month.
The contractor should start for the minor works and shoulder final layer as soon as AC-WC completion
ANNEX P-17 Executive Summary Report shows the complete details and work progress of the project.