23 CD 32.89 WINRIP DOC MPR CTC MPR No.54 2017 06 20170630 00493

Western I ndonesia National Roads I mprovement Project 4 - 6 The completion date of this works is 10, July 2017. Hence, the contractor has proposed the extension of time for unsettled land acquisition of segment No. 2, about 18 km and segment No. 3, about 2 km as of the end of May 2017. Details of the work progress are shown in ANNEX P-13 Executive Summary Reports. Package No. 14: Painan - Kambang The Progress as of this month is achieved of 32.89 against the scheduled 37.80 having slippage rate - 4.91. The progress of Asphalt pavement of this month is only 1.42 which is much less than the previous month, 8.89 because of a little working areas for Asphalt paving works. Nevertheless this month progress of preparatory work like pavement widening shoulders, granular pavement were done in very small areas. The contractor is repeatly advised to increase the work forces for widening teams to accommodate the progress of Asphalt paving works. ANNEX P-14 Executive Summary Report shows the complete details of the project. Package No. 15: Sibolga Bts. Tapsel The progress as of this month is only 43.75 against the scheduled, 84.69 having slippage rate -40.94. The main reasons of delayed progress are unsettled land acquisition, 12.9 km and delay of relocating the utilities of electrical poles PLN and water pipes PDAM. The contractor had being advised to propose for design changes of typical sections in accordance with site situations utilizing the existing ROW Ave. 11m width for the areas which are situated un very densely populated road. Detailed and work progresses of the contract package are shown in ANNEX P-15 Executive Summary Report . Package No. 16: Seblat Ipuh This month progress has been achieved of 3.43 against the scheduled, 3.63 and the accumulated progress as of this months is 12.11 against the scheduled, 10.7 having ahead progress, 1.33. The progress of this month was made with various works like Drainage, Earthworks, Structures, etc. But the pavement works are no progress. The contractor has to concentrate for early start of asphalt paving works which is most major weight of the works reached at 53.56 from the total. ANNEX P-16 Executive Summary Report shows the complete details and work progress of the project. Package No. 17 : Sp. Gunung Kemala Pg. Tampak The progress of this month is achieved of 4.80 against the scheduled, 4.02 having ahead of 0.78. Ac wearing course was started is this month and the working areas for AC-WC is in large stretches which could be constructed for 2 or 3 month. The contractor should start for the minor works and shoulder final layer as soon as AC-WC completion ANNEX P-17 Executive Summary Report shows the complete details and work progress of the project.