Western I ndonesia National Roads I mprovement Project 6 - 1
6 PROJECT PERFORMANCE
6.1 World Bank and GOI Compliance
6.1.1 World Bank Missions
A World Bank supervision mission for implementation review took place on April 25, 2017 with the kick off and wrap up meetings, respectively.
6.1.2 Agreed Key Actions and Mission Plans during Recent World Bank Mission
Lists of the key actions monitored during the period are listed below.
No. Action
By Whom Update Status
June 25, 2017 New Deadline
25 April 2017
1. Send to the World Bank WB the contract modification request
for package 03 for additional stone masonry World Bank will
only approve it if TFAC findings for packages 2 and 3 are followed upcontractor complies with his defect liability.
PMU and CTC. After the follow-up by
the contractor of the TFAC findings of
packages 2 and 3
2. Send to the WB the request for contract modification and time
extension for package 05. PMU and CTC.
10 July 2017 3.
Stop works for 1.59 km where the roads crosses the protected forest until the IPPKH is obtained.
PMU and CTC. Done
4. Send to the WB the information on the alternative road
sections, length and traffic to redo the economic analysis for package 05.
PMU and CTC. Done
5. Inform the WB about the possibility use ABPN money to
construct the additional drainage under package 06 to avoid that water enters into a housing area.
PMU, CTC and DSC.
6. Provide feedback on the design changes in package 15.
WB After WB field visit in
early May 7.
Send to the WB report with the results of the investigation conducted by the Inspectorate General regarding the problem
of the undue invoice under package 14 and the follow up by Bina Marga.
PPK, PMU and CTC
May 20, 2017
8. Inform the WB about the outcome of the third show case for
package 12 PT LMA and PT. CTA and the measures to be taken if it fails.
PMU and CTC. 3
rd
Show Cause Meeting conducted.
End of July 2017
9. Send WB the DSC report with analysis that shows that the
solution is adequate given the deterioration of the pavement cracking one year after overlay for biking event- possible
problems underneath in package 20. DSC, PMU and
CTC. Mid-May 2017.
10. Inform the WB about the results of the second show case
meeting and the actions that will be taken in case it fails for package 21 cash flow problem, not sufficient capacity for
concrete drainage, etc.. DSC.
2
nd
Show Cause Meeting conducted.
May 17, 2017
11. Package 8 may need a variation order for a second lane for part
of the section. No deadline yet
provided 12.
Send to WB request for variation order of Package 17 include 2 new sections.
Not Required Mid-May 2017
13. Submit to the WB the request for final no-objection to the
contract for the slope stabilization, design, and management. PMU and CTC.
Done
Western I ndonesia National Roads I mprovement Project 6 - 2
14. Submit to the WB formally the procurement plan.
PMU and CTC. Done
15. Send to the WB the 2
nd
DSC contract modification for price escalation.
PMU and CTC. July 2017
July 2017 16.
Send to the WB formally the request for NOL to CTC contract amendment No. 5.
PMU and CTC. Done
17. Send to the WB the information on how the inundated spots
on the road of package 7 will be fixed. PMU and CTC.
18. Re-send to the WB the revised environmental management
and monitoring plan RKPPL for package 12, including info on AMP and stone crasher licenses.
• Done submit to WB
29 May 2017
19. Re-send to the WB the revised environmental management
and monitoring plan RKPPLs for package 21 with missing information.
• Done submit to WB
29 May 2017
20. Re-send to the WB the revised environmental management
and monitoring plans RKPPLs for packages 14 and 20 or the documentation showing that the licensing process was carried
out correctly. •
Done submit to WB 29 May 2017
21. Send to the WB environmental management and monitoring
plans RKPPLs for package 16. •
Done CTC submit to PMU on 2 June
2017 under process to WB
22. Revise RKPPLs monitoring reports to include all necessary
information, especially for packages 7 and 12 and send to the Bank.
• Done submit to WB
29 May 2017
23. Implement action plan on how to avoid spills in base camps
and improve base camp management in all packages with problems
• May
31 July 2017 On process
24. Cary out HIVAIDS workshops.
PMUCTC DSC.
• Packages 08, 20,
and 21: Done •
Packages 16: May 2017
• Done on 15 May
2017
25. Provide us with a list of the package with base camp
management issues oil spills, inadequate drainage, specifying the main
PMUCTC Done email to WB on
2 May 2017
26. training on base camp management for contactors, DSC, PPK
WB Done on 11, 18 22
May 2017
27. PMUCTC will instruct DSC to send a letter to DSC asking to
take the necessary measures among others based on 1. above to improve base camp management by a certain date and will
ask to include photos PMUCTC
On Process CTC email draft letter to PMU on
5 June 2017
28. CTC will do some control visits and report to the Bank
PMUCTC Mid of July 2017
29. CTC will have to figure out what role BLH and the
environmental department of Bina Marga can play to improve performance since this is against the local laws as well
Subdit LKJPMUCTC
Is being coordinated 30.
Letter to the contractors informing them that they are violating the rules
DGHPMUCTC Done the list of letters
email to WB on 6 June 2017
31. Send to the WB the final LARAP document for package 05
signed by the relevant Government authority. PMU and CTC.
Done March 10, 2017
32. Send to the WB the permission letter from the Forestry
Department for package 05. PMU and CTC.
Under administration process in Forestry
Department. Early of Sep 2017
Western I ndonesia National Roads I mprovement Project 6 - 3
33. Contract the appraisal team for package 08, 20, and 21 to
reassess the affected assets. PMU and CTC.
Done 34.
Request the additional budget necessary to carry out all LARAPs compensation payments in 2017.
PMU. Done
35. Submit to the WB LARAPs monitoring reports for packages 07,
08, 12, 13, 14, 15, 17, 20, and 21. PMU and CTC.
• Packages 7, 12, 13,
14 : Done. •
Packages 8, 17, 20, 21: No date
provided yet 36.
Send to the WB the LARAP implementation report for the remedial action in package 05.
PMU and CTC. Delayed
• End of May 2017
37. Completely follow up on the FY2015 audit findings, and send
report to the WB. PMU and CTC.
Done 38.
Submit to the WB the 2016 financial audit report. PMU and CTC.
Done 39.
Submit to the WB the quarterly IFR for the period October to December 2016.
PMU. Done
March 20, 2017 40.
Submit to the WB the quarterly IFR for the period January to March 2017.
PMU. Done
41. Request additional counterpart funds for the 2017
implementation. PMU.
Done
42. Send to the WB the TFAC response for packages 20, 21, 14
PMUDSC CTC.
• Package 14: Under
process •
Package 20: Informal June 5,
2017 Package 21:
Informal June 15, 2017
•
43. Inform the WB when we will receive the follow up to TFAC
findings for packages 3 never received a feedback - concrete drainage broken, asphalt start waving, and 2 asphalt
already broken. •
Mid-May 2017.
44. Send to the WB the TFAC response for packages 05, 06, 08, 13,
15, and 17. PMUDSC
CTC. •
Package 05: Done March 31, 2017
• Package 06: Done
March 20, 2017 •
Package 08: Done March 31, 2017
• Package 13: Done
March 20, 2017 •
Package 15: Done March 31, 2017
• Package 17: Done
March 20, 2017 45.
Send to the WB informally the draft restructuring proposal. PMUCTCWB.
• June 2017
46. Next supervision mission document progress in terms of
cancelled component C WB
• August 2017
47. Submit regularly to the WB the quarterly progress reports.
PMU. This activity must be
carried out every calendar quarter.
48. Update the newsletter quarterly, including the list of contracts,
implementation progress, project related workshops, and number, typology and status of complaints.
PMU. This activity must be
carried out every calendar quarter.
49. Send the quarterly newsletter to the civil society forum in each
project province in hard copy or through an electronic mailing system.
PMU. This activity must be
carried out every calendar quarter.