PEKERJAAN TANAH
Start: Wed 91411ID: 3 Finish: Tue 10111Dur: 28 days
Res:
PEKERJAAN PONDASI
Start: Wed 92111ID: 4 Finish: Tue 10181Dur: 28 days
Res:
PEKERJAAN KONSTRUKSI BETON LANT
Start: Wed 92811ID: 5 Finish: Tue 12201Dur: 84 days
Comp: 0
C.1 LANTAI DASAR ELV. -4.250 - ELV. +
Start: Wed 92811ID: 6 Finish: Tue 10251Dur: 28 days
Res:
C.2 LANTAI 1 ELV. +0.005 - ELV. +4.150
Start: Wed 10511ID: 7 Finish: Tue 11111Dur: 28 days
Res:
C.3 LANTAI 2 ELV. +4.150 - ELV. +8.350
Start: Wed 10191ID: 8 Finish: Tue 11811Dur: 21 days
Res:
C.4 LANTAI 3 ELV. +8.350 - ELV. +12.55
Start: Wed 10261ID: 9 Finish: Tue 11151Dur: 21 days
Res:
C.5 LANTAI 4 ELV. +12.550 - ELV. +16.7
Start: Wed 11211ID: 10 Finish: Tue 11221Dur: 21 days
Res:
C.6 LANTAI 5 ELV. +16.750 - ELV. +21.2
Start: Wed 11911ID: 11 Finish: Tue 11291Dur: 21 days
Res:
C.7 LANTAI ATAP
Start: Wed 11211ID: 12 Finish: Tue 12201Dur: 49 days
Res:
PEKERJAAN ARSITEKTUR
Start: Wed 11211ID: 13 Finish: Tue 12271Dur: 56 days
Comp: 0
LANTAI DASAR
Start: Wed 11211ID: 14 Finish: Tue 12131Dur: 42 days
Comp: 0
A.1 PEK. DINDING
Start: Wed 11211ID: 15 Finish: Tue 11221Dur: 21 days
Res:
A.2 PEK. LANTAI
Start: Wed 11161ID: 16 Finish: Tue 11291Dur: 14 days
Res:
A.3 PEK. KUSEN LENGKAP
Start: Wed 11911ID: 17 Finish: Tue 11291Dur: 21 days
Res:
A.4 PEK. PLAFOND
Start: Wed 11911ID: 18 Finish: Tue 11221Dur: 14 days
Res:
A.5 PEK. PENGECATAN
Start: Wed 11301ID: 19 Finish: Tue 12131Dur: 14 days
Res:
LANTAI - 1
Start: Wed 11911ID: 20 Finish: Tue 12271Dur: 49 days
Comp: 0
B.1 PEK. DINDING
Start: Wed 11911ID: 21 Finish: Tue 11291Dur: 21 days
Res:
B.2 PEK. LANTAI
Start: Wed 11301ID: 22 Finish: Tue 12131Dur: 14 days
Res:
B.3 PEK. KUSEN LENGKAP
Start: Wed 11231ID: 23 Finish: Tue 12131Dur: 21 days
Res:
B.4 PEK. PLAFOND
Start: Wed 11301ID: 24 Finish: Tue 12131Dur: 14 days
Res:
B.5 PEK. SANITAIR
Start: Wed 12211ID: 25 Finish: Tue 12271Dur: 7 days
Res:
B.6 PEK. PENGECATAN
Start: Wed 12711ID: 26 Finish: Tue 12201Dur: 14 days
Res:
LANTAI - 2
Start: Wed 11301ID: 27 Finish: Tue 12201Dur: 21 days
Comp: 0
C.1 PEKERJAAN KUSEN LENGKAP
Start: Wed 11301ID: 28 Finish: Tue 12201Dur: 21 days
Res:
LANTAI - 3
Start: Wed 12711ID: 29 Finish: Tue 12271Dur: 21 days
Comp: 0
D.1 PEK. KUSEN LENGKAP
Start: Wed 12711ID: 30 Finish: Tue 12201Dur: 14 days
Res:
D.2 PEK. PENGECATAN
Start: Wed 12141ID: 31 Finish: Tue 12271Dur: 14 days
Res:
LANTAI - 4
Start: Wed 12141ID: 32 Finish: Tue 12271Dur: 14 days
Comp: 0
E.1 PEK. KUSEN LENGKAP
Start: Wed 12141ID: 33 Finish: Tue 12271Dur: 14 days
Res:
LANTAI - RUANG MESIN
Start: Wed 12141ID: 34 Finish: Tue 12271Dur: 14 days
Comp: 0
F.1 PEKERJAAN LANTAI
Start: Wed 12141ID: 35 Finish: Tue 12271Dur: 14 days
Res:
PEKERJAAN MEKANIKAL
Start: Wed 10191ID: 36 Finish: Tue 12201Dur: 63 days
Comp: 0
1. PEKERJAAN INSTALASI PLAMBING
Start: Wed 11211ID: 37 Finish: Tue 12611Dur: 35 days
Comp: 0
1.1 INSTALASI AIR BERSIH
Start: Wed 11211ID: 38 Finish: Tue 12611Dur: 35 days
Comp: 0
1.3 INSTALASI AIR BEKAS
Start: Wed 11211ID: 52 Finish: Tue 12611Dur: 35 days
Comp: 0
2. INSTALASI PEMIPAAN
Start: Wed 11211ID: 56 Finish: Tue 12131Dur: 42 days
Comp: 0
2.1 INSTALASI VENT
Start: Wed 11211ID: 57 Finish: Tue 12131Dur: 42 days
Comp: 0
2.2 INSTALASI AIR HUJAN
Start: Wed 11211ID: 59 Finish: Tue 12131Dur: 42 days
Comp: 0
MATERIAL BANTU
Start: Wed 11211ID: 67 Finish: Tue 12131Dur: 42 days
Res:
TESTING COMMISSIONING
Start: Wed 12711ID: 68 Finish: Tue 12201Dur: 14 days
Res:
3. INSTALASI TATA UDARA DAN SISTEM
Start: Wed 10191ID: 69 Finish: Tue 11291Dur: 42 days
Comp: 0
3.1 INSTALASI PEMIPAAN
Start: Wed 10261ID: 70 Finish: Tue 11291Dur: 35 days
Comp: 0
3.2 SALURAN UDARA
Start: Wed 10191ID: 72 Finish: Tue 11291Dur: 42 days
Comp: 0
MATERIAL BANTU
Start: Wed 10191ID: 74 Finish: Tue 12611Dur: 49 days
Res:
TESTING COMMISSIONING
Start: Wed 12711ID: 75 Finish: Tue 12131Dur: 7 days
Res:
PEKERJAAN ELEKTRIKAL
Start: Wed 10191ID: 76 Finish: Tue 12201Dur: 63 days
Comp: 0
5.1 PEKERJAAN PERALATAN PANEL
Start: Wed 11231ID: 77 Finish: Tue 12611Dur: 14 days
Res:
5.2 PEKERJAAN INSTALASI KABEL FEED
Start: Wed 10191ID: 78 Finish: Tue 11291Dur: 42 days
Res:
5.3 PEKERJAAN ARMATUR LAMPU, SA
Start: Wed 11301ID: 79 Finish: Tue 12201Dur: 21 days
Comp: 0
5.4 PEKERJAAN INSTALASI FINAL
Start: Wed 11911ID: 82 Finish: Tue 12611Dur: 28 days
Comp: 0
5.5 PEKERJAAN KABEL TRAY
Start: Wed 10261ID: 85 Finish: Tue 11291Dur: 35 days
Comp: 0
PEKERJAAN BANTU
Start: Wed 10261ID: 87 Finish: Tue 11291Dur: 35 days
Res:
TESTING COMMISSIONING
Start: Wed 11301ID: 88 Finish: Tue 12611Dur: 7 days
Res:
PEKERJAAN ELEKTRONIK
Start: Wed 10261ID: 89 Finish: Tue 12201Dur: 56 days
Comp: 0
5.6 PEKERJAAN FIRE ALARM
Start: Wed 11911ID: 90 Finish: Tue 12611Dur: 28 days
Comp: 0
5.7 PEKERJAAN SISTEM TELEPON
Start: Wed 11911ID: 97 Finish: Tue 12131Dur: 35 days
Comp: 0
5.8 PEKERJAAN RAK KABEL
Start: Wed 10261ID: 102 Finish: Tue 11291Dur: 35 days
Comp: 0
PEKERJAAN BANTU
Start: Wed 10261ID: 104 Finish: Tue 12131Dur: 49 days
Res:
TESTING COMMISSIONING
Start: Wed 12141ID: 105 Finish: Tue 12201Dur: 7 days
Res:
PEKERJAAN GWT GROUND WATER TA
Start: Wed 11161ID: 106 Finish: Tue 12131Dur: 28 days
Comp: 0
PEKERJAAN DINDING TURAP BATU KA
Start: Wed 11231ID: 113 Finish: Tue 12201Dur: 28 days
Res:
PEMASANGAN KABEL SEMENTARA DA
Start: Wed 11231ID: 114 Finish: Tue 12201Dur: 28 days
Res:
PEKERJAAN PENANGKAL PETIR SYSTEM
Start: Wed 12141ID: 115 Finish: Tue 12271Dur: 14 days
Res:
ROOF TANK KUBIKLE2 KOMPARTEME
Start: Wed 12211ID: 116 Finish: Tue 12271Dur: 7 days
Res:
PEKERJAAN STRUKTUR
Start: Wed 91411ID: 2 Finish: Tue 12201Dur: 98 days
Comp: 0
Instalasi Lantai Dasar
Start: Wed 11911ID: 41 Finish: Fri 111111Dur: 3 days
Res:
Instalasi Lantai 1
Start: Sat 111211ID: 42 Finish: Wed 1116 Dur: 5 days
Res:
Instalasi Lantai 2
Start: Thu 11171 ID: 43 Finish: Mon 1121 Dur: 5 days
Res:
Instalasi Lantai 3
Start: Tue 112211ID: 44 Finish: Sat 112611Dur: 5 days
Res:
Instalasi Lantai 4
Start: Sun 11271 ID: 45 Finish: Thu 12111Dur: 5 days
Res:
Instalasi Lantai 5 Ruang Mesin
Start: Fri 12211 ID: 46 Finish: Tue 12611Dur: 5 days
Res:
Pengadaan dan pemasangan unit
Start: Wed 11211ID: 48 Finish: Wed 1191 Dur: 8 days
Res:
Instalasi Site Plan
Start: Thu 11101 ID: 49 Finish: Thu 11171Dur: 8 days
Res:
Instalasi Lantai Dasar
Start: Fri 111811 ID: 50 Finish: Sat 112611Dur: 9 days
Res:
Instalasi Lantai 1
Start: Sun 112711ID: 51 Finish: Tue 12611Dur: 10 days
Res:
Instalasi Site Plan
Start: Wed 11211ID: 53 Finish: Fri 111111Dur: 10 days
Res:
Instalasi Lantai Dasar
Start: Sat 111211ID: 54 Finish: Mon 1121 Dur: 10 days
Res:
Instalasi Lantai 1
Start: Tue 112211ID: 55 Finish: Tue 12611Dur: 15 days
Res:
Instalasi Lantai 1
Start: Wed 11211ID: 58 Finish: Tue 12131Dur: 42 days
Res:
Instalasi Site Plan
Start: Wed 11211ID: 60 Finish: Sun 11611Dur: 5 days
Res:
Instalasi Lantai Dasar
Start: Mon 11711ID: 61 Finish: Sat 111211Dur: 6 days
Res:
Instalasi Lantai 1
Start: Sun 11131 ID: 62 Finish: Fri 111811Dur: 6 days
Res:
Instalasi Lantai 2
Start: Sat 111911ID: 63 Finish: Thu 11241Dur: 6 days
Res:
Instalasi Lantai 3
Start: Fri 112511 ID: 64 Finish: Wed 1130 Dur: 6 days
Res:
Instalasi Lantai 4
Start: Thu 12111 ID: 65 Finish: Tue 12611Dur: 6 days
Res:
Instalasi Lantai 5 Ruang Mesin
Start: Wed 12711ID: 66 Finish: Tue 12131Dur: 7 days
Res:
Instalasi Lantai 1
Start: Wed 10261ID: 71 Finish: Tue 11291Dur: 35 days
Res:
Instalasi Lantai 1
Start: Wed 10191ID: 73 Finish: Tue 11291Dur: 42 days
Res:
Pekerjaan Lantai Dasar
Start: Wed 11301ID: 80 Finish: Tue 12611Dur: 7 days
Res:
Pekerjaan Lantai 1
Start: Wed 12711ID: 81 Finish: Tue 12201Dur: 14 days
Res:
Pekerjaan Lantai Dasar
Start: Wed 11911ID: 83 Finish: Tue 11221Dur: 14 days
Res:
Pekerjaan Lantai 1
Start: Wed 11231ID: 84 Finish: Tue 12611Dur: 14 days
Res:
Pekerjaan Lantai 1
Start: Wed 10261ID: 86 Finish: Tue 11291Dur: 35 days
Res:
Pengadaan dan pemasangan unit
Start: Wed 11911ID: 91 Finish: Sat 111211Dur: 4 days
Res:
Instalasi Lantai Dasar
Start: Sun 11131 ID: 92 Finish: Thu 11171Dur: 5 days
Res:
Instalasi Lantai 1
Start: Fri 111811 ID: 93 Finish: Tue 11221Dur: 5 days
Res:
Instalasi Kabel Feeder Fire Alarm
Start: Wed 11231ID: 94 Finish: Sat 112611Dur: 4 days
Res:
Instalasi Detector Fire Alarm Lantai Da
Start: Sun 11271 ID: 95 Finish: Thu 12111Dur: 5 days
Res:
Instalasi Detector Fire Alarm Lantai 1
Start: Fri 12211 ID: 96 Finish: Tue 12611Dur: 5 days
Res:
Pengadaan dan pemasangan sistem te
Start: Wed 11911ID: 98 Finish: Tue 11151Dur: 7 days
Res:
Pengadaan dan pemasangan outlet te
Start: Wed 11161ID: 99 Finish: Wed 1123 Dur: 8 days
Res:
Instalasi Kabel Feeder Telepon
Start: Thu 11241 ID: 100 Finish: Sat 12311 Dur: 10 days
Res:
Instalasi Outlet Telepon
Start: Sun 12411 ID: 101 Finish: Tue 12131Dur: 10 days
Res:
Pekerjaan Lantai 1
Start: Wed 10261ID: 103 Finish: Tue 11291Dur: 35 days
Res:
Pekerjaan Ground Water Tank GWT
Start: Wed 11161ID: 107 Finish: Tue 12131Dur: 28 days
Res:
Pekerjaan Rumah Pompa
Start: Wed 11161ID: 108 Finish: Tue 12131Dur: 28 days
Comp: 0
Pekerjaan Struktur
Start: Wed 11161ID: 109 Finish: Tue 11221Dur: 7 days
Res:
Pekerjaan Finishing
Start: Wed 11231ID: 110 Finish: Tue 11291Dur: 7 days
Res:
Pekerjaan Elektrikal dan Mekanikal
Start: Wed 11301ID: 111 Finish: Tue 12611Dur: 7 days
Res:
Pekerjaan Kusen dan Pintu
Start: Wed 12711ID: 112 Finish: Tue 12131Dur: 7 days
Res:
Pengadaan dan pemasangan unit
Start: Wed 11211ID: 39 Finish: Fri 11411 Dur: 3 days
Res:
1.2 INSTALASI AIR KOTOR
Start: Wed 11211ID: 47 Finish: Tue 12611Dur: 35 days
Comp: 0
Instalasi Site Plan
Start: Sat 11511 ID: 40 Finish: Tue 11811Dur: 4 days
Res:
PEKERJAAN PERSIAPAN
Start: Wed 9711 ID: 1 Finish: Tue 92711Dur: 21 days
Res:
Critical Noncritical
Critical Milestone Milestone
Critical Summary Summary
Critical Inserted Inserted
Critical Marked Marked
Critical External External
Project Summary Highlighted Critical
Highlighted Noncritical Page 1
Project: Proyek Perpustakaan Date: Mon 72312
MINGGU KE :
TANGGAL :
NO ITEM PEKERJAAN
SATUAN VOLUME PEKERJAAN
BOBOT TOTAL S KEMAJUAN PEKERJAAN BOBOT
Bobot Bobot
SD MINGGU INI SD
Minggu Lalu Minggu Ini
Minggu Lalu Minggu Ini
MINGGU INI I.
PEKERJAAN PERSIAPAN DAN PENUNJANG
1 Pekerjaan pengukuran dan pemasangan bowplank m1
117.65 0.0882
0.0000 0.0000
0.0000 2 Pekerjaan pembersihan lokasi
m2 3202.00
0.2050 0.0000
0.1025 50
50 0.1025
3 Direksikeet uk. 3,6 x 7,2 = 25,92 m2 m2
25.92 0.2392
0.0000 0.1196
50 50
0.1196 4 Pagar pengaman proyek
m1 233.46
0.4485 0.0000
0.3364 75
75 0.3364
5 Air kerja lot
1.00 0.0329
0.0000 0.0016
5 5
0.0016 6 Listrik kerja
lot 1.00
0.0424 0.0000
0.0021 5
5 0.0021
7 Foto proyek ls
3.00 0.0056
0.0000 0.0003
5 5
0.0003 8 Pekerjaan jalan masuk ke site
m1 25.00
0.0260 0.0000
0.0130 50
50 0.0130
9 Pembuatan Dam sementara pekerjaan khusus diarea lot
1.00 1.1350
0.0000 0.2838
25 25
0.2838 kolom yang masuk ke area sungai
SUB TOTAL PEKERJAAN PERSIAPAN DAN PENUNJANG 2.2228
0.0000 0.8593
0.8593 II. PEKERJAAN STRUKTUR
A. PEK. TANAH 1 Galian tanah untuk pile cap dan tie beam
m3 358.76
0.0824 2 Urugan tanah kembali sisa galian
m3 200.24
0.0220 3 Urugan tanah dari luar proyek
m3 155.00
0.1813 4 Urugan pasir di bawah pile cap, tie beam dan plat tebal 10 cm
m3 37.67
0.0839 5 Lantai kerja tebal 5 cm dibawah pile cap, tie beam dan plat lantai
m3 15.54
0.1123 0.4819
0.0000 0.0000
0.0000 B. PEK. PONDASI
1 Pondasi tiang pancang minipile M25 segi empat K 500 m
2208.00 4.3459
2 Potong tiang pancang ttk
184.00 0.1601
3 Mobilisasi alat pancang unit
1.00 0.2439
4 Pile cap P-1 60 x 60 x 60 m3
0.86 0.0381
5 Pile cap P-2 135 x 60 x 65 m3
0.51 0.0289
6 Pile cap P-4 135 x 135 x 85 m3
12.39 0.2937
7 Pile cap P-8 190 x 210 x 120 m3
28.73 0.7225
8 Pile cap P-9 210 x 210 x 120 m3
52.92 1.2152
9 Pit lift - Lantai pit lift
m3 5.12
0.1926 - Dinding pit lift
m3 4.00
0.1223 10 Tie beam TB 1 40 x 60
m3 20.16
0.5360 11 Tie beam TB 2 35 x 80
m3 11.14
0.3559 12 Tie beam TB 3 35 x 80
m3 18.14
0.5794 13 Tie beam TB 4 35 x 55
m3 9.24
0.2965 14 Tie beam TB 5 20 x 45
m3 1.94
0.0869 9.2179
0.0000 0.0000
0.0000 C. PEK. KONSTRUKSI BETON
C.1 LANTAI DASAR ELV. -4.250 - ELV. +0.005
1 Kolom K1K 65 x 65 m3
39.04 1.5913
2 Kolom K4 20 x 40 m3
0.67 0.0485
3 Kolom KL 20 x 40 x 40 Lift m3
2.02 0.1432
4 Kolom B1 40 x 80 m3
9.18 0.4347
5 Kolom B2 35 x 75 m3
15.02 0.6032
6 Kolom B3 50 x 80 m3
23.09 1.3886
7 Kolom B5 35 x 75 m3
16.54 0.8125
8 Kolom B6 45 x 45 m3
20.25 1.0681
9 Kolom B7 30 x 45 m3
22.14 1.4178
10 Kolom B8 25 x 45 m3
14.85 0.8984
11 Kolom B9 20 x 40 m3
7.04 0.5313
12 Kolom B9K 20 x 40 m3
11.52 0.9060
13 Kolom B10 20 x 40 m3
7.68 0.5768
14 Kolom B10K 20 x 40 m3
0.96 0.0755
15 Plat lantai t. 80 mm ; elv. -4.250 m3
28.68 1.4163
16 Plat lantai t. 150 mm ; elv. -4.250 m3
14.14 0.4433
17 Plat lantai t. 12 cm ; elv. 0.05 m3
57.30 2.0915
18 Plat tangga utama m3
1.83 0.0629
19 Plat bordes tangga utama m3
0.29 0.0112
14.5211 0.0000
0.0000 0.0000
C.2LANTAI 1 ELV. +0.005 - ELV. +4.12 5
1 Kolom K1 d. 50 cm m3
21.72 1.1256
2 Kolom K2 60 x 60 m3
18.14 0.9270
3 Kolom K3 60x 60 m3
12.10 0.4713
4 Kolom K4 20 x 40 m3
0.67 0.0489
5 Kolom KL 20 x 40 x 40 Lift m3
2.02 0.1440
6 Kolom B1 40 x 80 m3
12.24 0.5795
7 Kolom B2 35 x 75 m3
19.85 0.7970
8 Kolom B3 50 x 80 m3
30.60 1.8404
9 Kolom B5K 35 x 75 m3
16.54 0.8224
10 Kolom B6 45 x 45 m3
10.13 0.5390
11 Kolom B7 30 x 45 m3
22.14 1.4332
12 Kolom B8 25 x 45 m3
14.85 0.9092
13 Kolom B9 20 x 40 m3
3.52 0.2689
14 Kolom B9K 20 x 40 m3
5.76 0.4584
15 Kolom B10 20 x 40 m3
6.68 0.5077
16 Kolom B10K 20 x 40 m3
0.48 0.0382
17 Plat lantai t. 12 cm ; elv. 4.125 m3
124.26 4.5995
18 Plat tangga m3
1.83 0.0636
19 Plat bordes tangga utama m3
0.29 0.0114
15.58520.0000 0.0000
0.0000 C.3 LANTAI 2 ELV. +4.125 - ELV. +8.350
1 Kolom K1A d. 50 cm m3
14.16 0.7369
2 Kolom K3A 55 x 55 m3
10.16 0.4242
3 Kolom K4 20 x 40 m3
0.67 0.0491
4 Kolom KL 20 x 40 x 40 Lift m3
2.02 0.1443
5 Kolom B5 35 x 75 m3
16.54 0.8218
6 Kolom B6 45 x 45 m3
10.13 0.5413
7 Kolom B7 30 x 45 m3
22.14 1.4377
8 Kolom B8 25 x 45 m3
14.85 0.9125
9 Kolom B9 20 x 40 m3
3.52 0.2699
10 Kolom B9K 20 x 40 m3
5.76 0.4600
11 Kolom B10 20 x 40 m3
4.16 0.3173
12 Kolom B10K 20 x 40 m3
0.48 0.0383
13 Plat lantai t. 12 cm ; elv. 8.350 m3
62.16 2.3118
14 Plat tangga m3
1.83 0.0638
15 Plat bordes tangga utama m3
0.29 0.0114
8.5403 0.0000
0.0000 0.0000
C.4 LANTAI 3 ELV. +8.350 - ELV. +12.550
1 Kolom K1B d. 35 cm m3
3.23 0.2366
2 Kolom K3B 55 x 55 m3
10.16 0.4246
3 Kolom K4 20 x 40 m3
0.67 0.0491
4 Kolom KL 20 x 40 x 40 Lift m3
2.02 0.1445
5 Kolom B4 25 x 35 m3
11.38 0.7388
6 Kolom B5 35 x 75 m3
16.54 0.8230
7 Kolom B6 45 x 45 m3
10.13 0.5420
8 Kolom B7 30 x 45 m3
22.14 1.4399
9 Kolom B8 25 x 45 m3
12.15 0.7479
10 Kolom B9 20 x 40 m3
3.52 0.2704
11 Kolom B9K 20 x 40 m3
5.76 0.4608
12 Kolom B10 20 x 40 m3
4.16 0.3179
13 Kolom B10K 20 x 40 m3
0.48 0.0385
RINCIAN PROGRES MINGGUAN PEKERJAAN GEDUNG PERPUSTAKAAN
1 7-13 SEPTEMBER
Lampiran 3. Laporan perkembangan pekerjaan mingguan pembangunan gedung perpustakaan Proyek X oleh PT. ABC
14 Plat lantai t. 12 cm ; elv. 12.550 m3
40.20 1.4988
15 Plat tangga m3
1.83 0.0639
16 Plat bordes tangga utama m3
0.29 0.0114
7.8081 0.0000
0.0000 0.0000
C.5 LANTAI 4 ELV. +12.550 - ELV. +16.750
1 Kolom K1B d. 35 cm m3
3.23 0.2392
2 Kolom K3C d. 25 cm m3
1.65 0.1032
3 Kolom K4 20 x 40 m3
0.67 0.0445
4 Kolom KL 20 x 40 x 40 Lift m3
2.02 0.1449
5 Kolom B6 45 x 45 m3
10.13 0.5435
6 Kolom B7A 0.15 x 0.5 m3
9.75 0.7298
7 Kolom B8A 25 x 45 m3
12.15 0.7503
8 Kolom B9 20 x 40 m3
3.52 0.2713
9 Kolom B9K 20 x 40 m3
5.76 0.4624
10 Kolom B10 20 x 40 m3
4.16 0.3190
11 Kolom B10K 20 x 40 m3
0.48 0.0385
12 Plat lantai t. 12 cm ; elv. 16.750 m3
40.20 1.5049
13 Plat tangga m3
1.83 0.0641
14 Plat bordes tangga utama m3
0.29 0.0114
5.2270 0.0000
0.0000 0.0000
C.6 LANTAI LMR ELV. +16.750 - ELV. +21.250
1 Kolom K1B d. 35 cm m3
3.23 0.2397
2 Kolom K4 20 x 40 m3
0.67 0.0494
3 Kolom KL 20 x 40 x 40 Lift m3
2.02 0.1456
4 Kolom B6 45 x 45 m3
7.09 0.3829
5 Kolom B9 20 x 40 m3
3.52 0.2729
6 Kolom B9K 20 x 40 m3
5.76 0.4651
7 Kolom B10 20 x 40 m3
4.16 0.3208
8 Kolom B10K 20 x 40 m3
0.48 0.0388
9 Plat DAK t.12 cm ; elev. 21.250 m3
11.52 0.3958
2.3110 0.0000
0.0000 0.0000
C.7 LANTAI ATAP
1 Kolom KP9 Pipa baja 8 kg
10348.80 2.1757
2 Balok pipa d. 8 kg
14886.93 3.1298
3 Plat t. 14 mm kg
361.65 0.0516
4 Plat t. 8 mm kg
361.44 0.0515
5 Anchor Bolt d. 19 mm bh
64.00 0.0230
6 Cat ex. Kansai kg
25958.82 0.2196
5.65120.0000 0.0000
0.0000 SUB TOTAL PEKERJAAN STRUKTUR
69.3437 0.0000
0.0000 0.0000
III. PEKERJAAN ARSITEKTUR A. LANTAI DASAR
A.1 PEK. DINDING
1 Dinding hebel t. 10 cm + MU 380 m2
481.14 0.4738
2 Plesteran dinding MU 100 t. 10 mm m2
962.28 0.4604
3 Acian MU 200 t. 3 mm m2
962.28 0.2349
4 Kolom praktis 10 x 10 m
52.21 0.0380
5 Balok lintel 10 x 15 m
132.39 0.1224
6 Finishing kolom MU 200 m2
177.59 0.0433
7 Railing pagar pipa hitam finishing cat m
46.00 0.0708
8 Railing tangga pipa hitam finishing cat m
10.00 0.0154
1.4590 0.0000
0.0000 0.0000
A.2PEK. LANTAI
1 Keramik 3030 DN putih m2
105.61 0.0898
2 Keramik 3030 DN putih tangga m2
21.69 0.0184
3 Stair nozing keramik 7 x 40 cm m
31.05 0.0260
0.13420.0000 0.0000
0.0000 A.3 PEK. KUSEN LENGKAP
1 SD1 unit
1.00 0.0477
2 FD1 unit
1.00 0.0260
3 ADW1 unit
1.00 0.0394
4 ADW2 unit
1.00 0.0609
5 ADW3 unit
1.00 0.0675
6 ADW4 unit
1.00 0.0578
7 BV1 unit
4.00 0.0494
8 BV2 unit
1.00 0.0103
9 BV3 unit
1.00 0.0103
10 Handrall pagar type R-5 bh
1.00 0.2752
0.6445 0.0000
0.0000 0.0000
A.4 PEK. PLAFOND
1 Plafond beton expose finishing m2
105.61 0.0258
0.0258 0.0000
0.0000 0.0000
A.5 PEK. PENGECATAN
1 Cat dinding Vinilex 3x m2
962.28 0.2163
2 Cat plafond beton expose Vinilex 3x m2
117.97 0.0305
3 Cat kolom dan balok m2
117.59 0.0399
0.2867 0.0000
0.0000 0.0000
SUB TOTAL PEKERJAAN ARSITEKTUR LANTAI DASAR 2.5502
0.0000 0.0000
0.0000 B. LANTAI - 1
B.1 PEK. DINDING
1 Dinding hebel t. 10 cm + MU 380 m2
514.88 0.5164
2 Plesteran dinding MU 100 dan acian MU 200 m2
1029.76 0.5126
3 Acian MU 200 t. 3 mm m2
1029.76 0.2663
4 Keramik dinding 2025 KMWC m2
144.69 0.1664
5 Kolom praktis 10 x 10 m
55.87 0.0414
6 Balok lintel 10 x 15 m
141.67 0.1339
7 Finishing kolom MU 200 m2
244.79 0.0633
8 Railing tangga pipa hitam finishing cat m
82.00 0.1263
1.8266 0.0000
0.0000 0.0000
B.2PEK. LANTAI
1 Floor hardener 3 kgm2 m2
40.50 0.0338
2 Lantai karpet koridor m2
340.00 0.8393
3 Keramik 3030 DN putih tangga m2
21.69 0.0189
4 Stair nozing keramik 7 x 40 cm m
31.05 0.0260
5 Keramik 2020 KMWC m2
32.09 0.0287
0.9467 0.0000
0.0000 0.0000
B.3 PEK. KUSEN LENGKAP 1 AD3
unit 3.00
0.0775 2 AD4
unit 2.00
0.1028 3 FD1
unit 5.00
0.1311 4 PVC
unit 5.00
0.0417 5 Partisi gypsum rangka metal stud galvalume
m2 30.60
0.0382 6 ADW5
m2 2.00
0.3278 7 AW2
bh 5.00
0.8384 8 AD2
bh 2.00
0.2191 9 Handrall pagar type R-1
bh 5.00
0.2755 10 Handrall pagar type R-2
bh 2.00
0.1024 2.1545
0.0000 0.0000
0.0000 B.4 PEK. PLAFOND
1 Plafond gypsum + rangka m2
196.00 0.2302
2 Plafond acoustik + rangka m2
159.00 0.1502
0.3804 0.0000
0.0000 0.0000
B.5 PEK. SANITAIR
1 Closed duduk ex TOTO bh
5.00 0.1259
2 Washtafel LW 230 J bh
6.00 0.0858
3 Urinoir bh
3.00 0.0680
4 Jet spray bh
3.00 0.0146
5 Floor drain bh
6.00 0.0096
6 Kaca cermin ukuran 2600 x 1200 mm tinggi bh
2.00 0.0063
0.31020.0000 0.0000
0.0000 B.6 PEK. PENGECATAN
1 Cat dinding Vinilex 3x m2
1152.16 0.2701
2 Cat plafond beton kaisiboard Vinilex 3x m2
196.00 0.0537
3 Cat kolom m2
244.79 0.0574
0.38120.0000 0.0000
0.0000 SUB TOTAL PEKERJAAN ARSITEKTUR LANTAI - 1
5.9996 0.0000
0.0000 0.0000
C. LANTAI - 2 C.1 PEK. KUSEN LENGKAP
1 Partisi gypsum rangka metal stud galvalume m2
96.16 0.1208
2 ADW5 unit
1.00 0.1644
3 ADW5 unit
1.00 0.1644