PEKERJAAN KABEL TRAY PEKERJAAN FIRE ALARM PEKERJAAN SISTEM TELEPON PEKERJAAN RAK KABEL

PEKERJAAN TANAH Start: Wed 91411ID: 3 Finish: Tue 10111Dur: 28 days Res: PEKERJAAN PONDASI Start: Wed 92111ID: 4 Finish: Tue 10181Dur: 28 days Res: PEKERJAAN KONSTRUKSI BETON LANT Start: Wed 92811ID: 5 Finish: Tue 12201Dur: 84 days Comp: 0 C.1 LANTAI DASAR ELV. -4.250 - ELV. + Start: Wed 92811ID: 6 Finish: Tue 10251Dur: 28 days Res: C.2 LANTAI 1 ELV. +0.005 - ELV. +4.150 Start: Wed 10511ID: 7 Finish: Tue 11111Dur: 28 days Res: C.3 LANTAI 2 ELV. +4.150 - ELV. +8.350 Start: Wed 10191ID: 8 Finish: Tue 11811Dur: 21 days Res: C.4 LANTAI 3 ELV. +8.350 - ELV. +12.55 Start: Wed 10261ID: 9 Finish: Tue 11151Dur: 21 days Res: C.5 LANTAI 4 ELV. +12.550 - ELV. +16.7 Start: Wed 11211ID: 10 Finish: Tue 11221Dur: 21 days Res: C.6 LANTAI 5 ELV. +16.750 - ELV. +21.2 Start: Wed 11911ID: 11 Finish: Tue 11291Dur: 21 days Res: C.7 LANTAI ATAP Start: Wed 11211ID: 12 Finish: Tue 12201Dur: 49 days Res: PEKERJAAN ARSITEKTUR Start: Wed 11211ID: 13 Finish: Tue 12271Dur: 56 days Comp: 0 LANTAI DASAR Start: Wed 11211ID: 14 Finish: Tue 12131Dur: 42 days Comp: 0 A.1 PEK. DINDING Start: Wed 11211ID: 15 Finish: Tue 11221Dur: 21 days Res: A.2 PEK. LANTAI Start: Wed 11161ID: 16 Finish: Tue 11291Dur: 14 days Res: A.3 PEK. KUSEN LENGKAP Start: Wed 11911ID: 17 Finish: Tue 11291Dur: 21 days Res: A.4 PEK. PLAFOND Start: Wed 11911ID: 18 Finish: Tue 11221Dur: 14 days Res: A.5 PEK. PENGECATAN Start: Wed 11301ID: 19 Finish: Tue 12131Dur: 14 days Res: LANTAI - 1 Start: Wed 11911ID: 20 Finish: Tue 12271Dur: 49 days Comp: 0 B.1 PEK. DINDING Start: Wed 11911ID: 21 Finish: Tue 11291Dur: 21 days Res: B.2 PEK. LANTAI Start: Wed 11301ID: 22 Finish: Tue 12131Dur: 14 days Res: B.3 PEK. KUSEN LENGKAP Start: Wed 11231ID: 23 Finish: Tue 12131Dur: 21 days Res: B.4 PEK. PLAFOND Start: Wed 11301ID: 24 Finish: Tue 12131Dur: 14 days Res: B.5 PEK. SANITAIR Start: Wed 12211ID: 25 Finish: Tue 12271Dur: 7 days Res: B.6 PEK. PENGECATAN Start: Wed 12711ID: 26 Finish: Tue 12201Dur: 14 days Res: LANTAI - 2 Start: Wed 11301ID: 27 Finish: Tue 12201Dur: 21 days Comp: 0 C.1 PEKERJAAN KUSEN LENGKAP Start: Wed 11301ID: 28 Finish: Tue 12201Dur: 21 days Res: LANTAI - 3 Start: Wed 12711ID: 29 Finish: Tue 12271Dur: 21 days Comp: 0 D.1 PEK. KUSEN LENGKAP Start: Wed 12711ID: 30 Finish: Tue 12201Dur: 14 days Res: D.2 PEK. PENGECATAN Start: Wed 12141ID: 31 Finish: Tue 12271Dur: 14 days Res: LANTAI - 4 Start: Wed 12141ID: 32 Finish: Tue 12271Dur: 14 days Comp: 0 E.1 PEK. KUSEN LENGKAP Start: Wed 12141ID: 33 Finish: Tue 12271Dur: 14 days Res: LANTAI - RUANG MESIN Start: Wed 12141ID: 34 Finish: Tue 12271Dur: 14 days Comp: 0 F.1 PEKERJAAN LANTAI Start: Wed 12141ID: 35 Finish: Tue 12271Dur: 14 days Res: PEKERJAAN MEKANIKAL Start: Wed 10191ID: 36 Finish: Tue 12201Dur: 63 days Comp: 0

1. PEKERJAAN INSTALASI PLAMBING

Start: Wed 11211ID: 37 Finish: Tue 12611Dur: 35 days Comp: 0

1.1 INSTALASI AIR BERSIH

Start: Wed 11211ID: 38 Finish: Tue 12611Dur: 35 days Comp: 0

1.3 INSTALASI AIR BEKAS

Start: Wed 11211ID: 52 Finish: Tue 12611Dur: 35 days Comp: 0

2. INSTALASI PEMIPAAN

Start: Wed 11211ID: 56 Finish: Tue 12131Dur: 42 days Comp: 0

2.1 INSTALASI VENT

Start: Wed 11211ID: 57 Finish: Tue 12131Dur: 42 days Comp: 0

2.2 INSTALASI AIR HUJAN

Start: Wed 11211ID: 59 Finish: Tue 12131Dur: 42 days Comp: 0 MATERIAL BANTU Start: Wed 11211ID: 67 Finish: Tue 12131Dur: 42 days Res: TESTING COMMISSIONING Start: Wed 12711ID: 68 Finish: Tue 12201Dur: 14 days Res:

3. INSTALASI TATA UDARA DAN SISTEM

Start: Wed 10191ID: 69 Finish: Tue 11291Dur: 42 days Comp: 0

3.1 INSTALASI PEMIPAAN

Start: Wed 10261ID: 70 Finish: Tue 11291Dur: 35 days Comp: 0

3.2 SALURAN UDARA

Start: Wed 10191ID: 72 Finish: Tue 11291Dur: 42 days Comp: 0 MATERIAL BANTU Start: Wed 10191ID: 74 Finish: Tue 12611Dur: 49 days Res: TESTING COMMISSIONING Start: Wed 12711ID: 75 Finish: Tue 12131Dur: 7 days Res: PEKERJAAN ELEKTRIKAL Start: Wed 10191ID: 76 Finish: Tue 12201Dur: 63 days Comp: 0

5.1 PEKERJAAN PERALATAN PANEL

Start: Wed 11231ID: 77 Finish: Tue 12611Dur: 14 days Res:

5.2 PEKERJAAN INSTALASI KABEL FEED

Start: Wed 10191ID: 78 Finish: Tue 11291Dur: 42 days Res:

5.3 PEKERJAAN ARMATUR LAMPU, SA

Start: Wed 11301ID: 79 Finish: Tue 12201Dur: 21 days Comp: 0

5.4 PEKERJAAN INSTALASI FINAL

Start: Wed 11911ID: 82 Finish: Tue 12611Dur: 28 days Comp: 0

5.5 PEKERJAAN KABEL TRAY

Start: Wed 10261ID: 85 Finish: Tue 11291Dur: 35 days Comp: 0 PEKERJAAN BANTU Start: Wed 10261ID: 87 Finish: Tue 11291Dur: 35 days Res: TESTING COMMISSIONING Start: Wed 11301ID: 88 Finish: Tue 12611Dur: 7 days Res: PEKERJAAN ELEKTRONIK Start: Wed 10261ID: 89 Finish: Tue 12201Dur: 56 days Comp: 0

5.6 PEKERJAAN FIRE ALARM

Start: Wed 11911ID: 90 Finish: Tue 12611Dur: 28 days Comp: 0

5.7 PEKERJAAN SISTEM TELEPON

Start: Wed 11911ID: 97 Finish: Tue 12131Dur: 35 days Comp: 0

5.8 PEKERJAAN RAK KABEL

Start: Wed 10261ID: 102 Finish: Tue 11291Dur: 35 days Comp: 0 PEKERJAAN BANTU Start: Wed 10261ID: 104 Finish: Tue 12131Dur: 49 days Res: TESTING COMMISSIONING Start: Wed 12141ID: 105 Finish: Tue 12201Dur: 7 days Res: PEKERJAAN GWT GROUND WATER TA Start: Wed 11161ID: 106 Finish: Tue 12131Dur: 28 days Comp: 0 PEKERJAAN DINDING TURAP BATU KA Start: Wed 11231ID: 113 Finish: Tue 12201Dur: 28 days Res: PEMASANGAN KABEL SEMENTARA DA Start: Wed 11231ID: 114 Finish: Tue 12201Dur: 28 days Res: PEKERJAAN PENANGKAL PETIR SYSTEM Start: Wed 12141ID: 115 Finish: Tue 12271Dur: 14 days Res: ROOF TANK KUBIKLE2 KOMPARTEME Start: Wed 12211ID: 116 Finish: Tue 12271Dur: 7 days Res: PEKERJAAN STRUKTUR Start: Wed 91411ID: 2 Finish: Tue 12201Dur: 98 days Comp: 0 Instalasi Lantai Dasar Start: Wed 11911ID: 41 Finish: Fri 111111Dur: 3 days Res: Instalasi Lantai 1 Start: Sat 111211ID: 42 Finish: Wed 1116 Dur: 5 days Res: Instalasi Lantai 2 Start: Thu 11171 ID: 43 Finish: Mon 1121 Dur: 5 days Res: Instalasi Lantai 3 Start: Tue 112211ID: 44 Finish: Sat 112611Dur: 5 days Res: Instalasi Lantai 4 Start: Sun 11271 ID: 45 Finish: Thu 12111Dur: 5 days Res: Instalasi Lantai 5 Ruang Mesin Start: Fri 12211 ID: 46 Finish: Tue 12611Dur: 5 days Res: Pengadaan dan pemasangan unit Start: Wed 11211ID: 48 Finish: Wed 1191 Dur: 8 days Res: Instalasi Site Plan Start: Thu 11101 ID: 49 Finish: Thu 11171Dur: 8 days Res: Instalasi Lantai Dasar Start: Fri 111811 ID: 50 Finish: Sat 112611Dur: 9 days Res: Instalasi Lantai 1 Start: Sun 112711ID: 51 Finish: Tue 12611Dur: 10 days Res: Instalasi Site Plan Start: Wed 11211ID: 53 Finish: Fri 111111Dur: 10 days Res: Instalasi Lantai Dasar Start: Sat 111211ID: 54 Finish: Mon 1121 Dur: 10 days Res: Instalasi Lantai 1 Start: Tue 112211ID: 55 Finish: Tue 12611Dur: 15 days Res: Instalasi Lantai 1 Start: Wed 11211ID: 58 Finish: Tue 12131Dur: 42 days Res: Instalasi Site Plan Start: Wed 11211ID: 60 Finish: Sun 11611Dur: 5 days Res: Instalasi Lantai Dasar Start: Mon 11711ID: 61 Finish: Sat 111211Dur: 6 days Res: Instalasi Lantai 1 Start: Sun 11131 ID: 62 Finish: Fri 111811Dur: 6 days Res: Instalasi Lantai 2 Start: Sat 111911ID: 63 Finish: Thu 11241Dur: 6 days Res: Instalasi Lantai 3 Start: Fri 112511 ID: 64 Finish: Wed 1130 Dur: 6 days Res: Instalasi Lantai 4 Start: Thu 12111 ID: 65 Finish: Tue 12611Dur: 6 days Res: Instalasi Lantai 5 Ruang Mesin Start: Wed 12711ID: 66 Finish: Tue 12131Dur: 7 days Res: Instalasi Lantai 1 Start: Wed 10261ID: 71 Finish: Tue 11291Dur: 35 days Res: Instalasi Lantai 1 Start: Wed 10191ID: 73 Finish: Tue 11291Dur: 42 days Res: Pekerjaan Lantai Dasar Start: Wed 11301ID: 80 Finish: Tue 12611Dur: 7 days Res: Pekerjaan Lantai 1 Start: Wed 12711ID: 81 Finish: Tue 12201Dur: 14 days Res: Pekerjaan Lantai Dasar Start: Wed 11911ID: 83 Finish: Tue 11221Dur: 14 days Res: Pekerjaan Lantai 1 Start: Wed 11231ID: 84 Finish: Tue 12611Dur: 14 days Res: Pekerjaan Lantai 1 Start: Wed 10261ID: 86 Finish: Tue 11291Dur: 35 days Res: Pengadaan dan pemasangan unit Start: Wed 11911ID: 91 Finish: Sat 111211Dur: 4 days Res: Instalasi Lantai Dasar Start: Sun 11131 ID: 92 Finish: Thu 11171Dur: 5 days Res: Instalasi Lantai 1 Start: Fri 111811 ID: 93 Finish: Tue 11221Dur: 5 days Res: Instalasi Kabel Feeder Fire Alarm Start: Wed 11231ID: 94 Finish: Sat 112611Dur: 4 days Res: Instalasi Detector Fire Alarm Lantai Da Start: Sun 11271 ID: 95 Finish: Thu 12111Dur: 5 days Res: Instalasi Detector Fire Alarm Lantai 1 Start: Fri 12211 ID: 96 Finish: Tue 12611Dur: 5 days Res: Pengadaan dan pemasangan sistem te Start: Wed 11911ID: 98 Finish: Tue 11151Dur: 7 days Res: Pengadaan dan pemasangan outlet te Start: Wed 11161ID: 99 Finish: Wed 1123 Dur: 8 days Res: Instalasi Kabel Feeder Telepon Start: Thu 11241 ID: 100 Finish: Sat 12311 Dur: 10 days Res: Instalasi Outlet Telepon Start: Sun 12411 ID: 101 Finish: Tue 12131Dur: 10 days Res: Pekerjaan Lantai 1 Start: Wed 10261ID: 103 Finish: Tue 11291Dur: 35 days Res: Pekerjaan Ground Water Tank GWT Start: Wed 11161ID: 107 Finish: Tue 12131Dur: 28 days Res: Pekerjaan Rumah Pompa Start: Wed 11161ID: 108 Finish: Tue 12131Dur: 28 days Comp: 0 Pekerjaan Struktur Start: Wed 11161ID: 109 Finish: Tue 11221Dur: 7 days Res: Pekerjaan Finishing Start: Wed 11231ID: 110 Finish: Tue 11291Dur: 7 days Res: Pekerjaan Elektrikal dan Mekanikal Start: Wed 11301ID: 111 Finish: Tue 12611Dur: 7 days Res: Pekerjaan Kusen dan Pintu Start: Wed 12711ID: 112 Finish: Tue 12131Dur: 7 days Res: Pengadaan dan pemasangan unit Start: Wed 11211ID: 39 Finish: Fri 11411 Dur: 3 days Res:

1.2 INSTALASI AIR KOTOR