SALURAN UDARA PEKERJAAN PERALATAN PANEL PEKERJAAN INSTALASI KABEL FEED PEKERJAAN ARMATUR LAMPU, SA PEKERJAAN INSTALASI FINAL PEKERJAAN KABEL TRAY PEKERJAAN FIRE ALARM PEKERJAAN SISTEM TELEPON PEKERJAAN RAK KABEL

PEKERJAAN TANAH Start: Wed 91411ID: 3 Finish: Tue 10111Dur: 28 days Res: PEKERJAAN PONDASI Start: Wed 92111ID: 4 Finish: Tue 10181Dur: 28 days Res: PEKERJAAN KONSTRUKSI BETON LANT Start: Wed 92811ID: 5 Finish: Tue 12201Dur: 84 days Comp: 0 C.1 LANTAI DASAR ELV. -4.250 - ELV. + Start: Wed 92811ID: 6 Finish: Tue 10251Dur: 28 days Res: C.2 LANTAI 1 ELV. +0.005 - ELV. +4.150 Start: Wed 10511ID: 7 Finish: Tue 11111Dur: 28 days Res: C.3 LANTAI 2 ELV. +4.150 - ELV. +8.350 Start: Wed 10191ID: 8 Finish: Tue 11811Dur: 21 days Res: C.4 LANTAI 3 ELV. +8.350 - ELV. +12.55 Start: Wed 10261ID: 9 Finish: Tue 11151Dur: 21 days Res: C.5 LANTAI 4 ELV. +12.550 - ELV. +16.7 Start: Wed 11211ID: 10 Finish: Tue 11221Dur: 21 days Res: C.6 LANTAI 5 ELV. +16.750 - ELV. +21.2 Start: Wed 11911ID: 11 Finish: Tue 11291Dur: 21 days Res: C.7 LANTAI ATAP Start: Wed 11211ID: 12 Finish: Tue 12201Dur: 49 days Res: PEKERJAAN ARSITEKTUR Start: Wed 11211ID: 13 Finish: Tue 12271Dur: 56 days Comp: 0 LANTAI DASAR Start: Wed 11211ID: 14 Finish: Tue 12131Dur: 42 days Comp: 0 A.1 PEK. DINDING Start: Wed 11211ID: 15 Finish: Tue 11221Dur: 21 days Res: A.2 PEK. LANTAI Start: Wed 11161ID: 16 Finish: Tue 11291Dur: 14 days Res: A.3 PEK. KUSEN LENGKAP Start: Wed 11911ID: 17 Finish: Tue 11291Dur: 21 days Res: A.4 PEK. PLAFOND Start: Wed 11911ID: 18 Finish: Tue 11221Dur: 14 days Res: A.5 PEK. PENGECATAN Start: Wed 11301ID: 19 Finish: Tue 12131Dur: 14 days Res: LANTAI - 1 Start: Wed 11911ID: 20 Finish: Tue 12271Dur: 49 days Comp: 0 B.1 PEK. DINDING Start: Wed 11911ID: 21 Finish: Tue 11291Dur: 21 days Res: B.2 PEK. LANTAI Start: Wed 11301ID: 22 Finish: Tue 12131Dur: 14 days Res: B.3 PEK. KUSEN LENGKAP Start: Wed 11231ID: 23 Finish: Tue 12131Dur: 21 days Res: B.4 PEK. PLAFOND Start: Wed 11301ID: 24 Finish: Tue 12131Dur: 14 days Res: B.5 PEK. SANITAIR Start: Wed 12211ID: 25 Finish: Tue 12271Dur: 7 days Res: B.6 PEK. PENGECATAN Start: Wed 12711ID: 26 Finish: Tue 12201Dur: 14 days Res: LANTAI - 2 Start: Wed 11301ID: 27 Finish: Tue 12201Dur: 21 days Comp: 0 C.1 PEKERJAAN KUSEN LENGKAP Start: Wed 11301ID: 28 Finish: Tue 12201Dur: 21 days Res: LANTAI - 3 Start: Wed 12711ID: 29 Finish: Tue 12271Dur: 21 days Comp: 0 D.1 PEK. KUSEN LENGKAP Start: Wed 12711ID: 30 Finish: Tue 12201Dur: 14 days Res: D.2 PEK. PENGECATAN Start: Wed 12141ID: 31 Finish: Tue 12271Dur: 14 days Res: LANTAI - 4 Start: Wed 12141ID: 32 Finish: Tue 12271Dur: 14 days Comp: 0 E.1 PEK. KUSEN LENGKAP Start: Wed 12141ID: 33 Finish: Tue 12271Dur: 14 days Res: LANTAI - RUANG MESIN Start: Wed 12141ID: 34 Finish: Tue 12271Dur: 14 days Comp: 0 F.1 PEKERJAAN LANTAI Start: Wed 12141ID: 35 Finish: Tue 12271Dur: 14 days Res: PEKERJAAN MEKANIKAL Start: Wed 10191ID: 36 Finish: Tue 12201Dur: 63 days Comp: 0

1. PEKERJAAN INSTALASI PLAMBING

Start: Wed 11211ID: 37 Finish: Tue 12611Dur: 35 days Comp: 0

1.1 INSTALASI AIR BERSIH

Start: Wed 11211ID: 38 Finish: Tue 12611Dur: 35 days Comp: 0

1.3 INSTALASI AIR BEKAS

Start: Wed 11211ID: 52 Finish: Tue 12611Dur: 35 days Comp: 0

2. INSTALASI PEMIPAAN

Start: Wed 11211ID: 56 Finish: Tue 12131Dur: 42 days Comp: 0

2.1 INSTALASI VENT

Start: Wed 11211ID: 57 Finish: Tue 12131Dur: 42 days Comp: 0

2.2 INSTALASI AIR HUJAN

Start: Wed 11211ID: 59 Finish: Tue 12131Dur: 42 days Comp: 0 MATERIAL BANTU Start: Wed 11211ID: 67 Finish: Tue 12131Dur: 42 days Res: TESTING COMMISSIONING Start: Wed 12711ID: 68 Finish: Tue 12201Dur: 14 days Res:

3. INSTALASI TATA UDARA DAN SISTEM

Start: Wed 10191ID: 69 Finish: Tue 11291Dur: 42 days Comp: 0

3.1 INSTALASI PEMIPAAN

Start: Wed 10261ID: 70 Finish: Tue 11291Dur: 35 days Comp: 0

3.2 SALURAN UDARA

Start: Wed 10191ID: 72 Finish: Tue 11291Dur: 42 days Comp: 0 MATERIAL BANTU Start: Wed 10191ID: 74 Finish: Tue 12611Dur: 49 days Res: TESTING COMMISSIONING Start: Wed 12711ID: 75 Finish: Tue 12131Dur: 7 days Res: PEKERJAAN ELEKTRIKAL Start: Wed 10191ID: 76 Finish: Tue 12201Dur: 63 days Comp: 0

5.1 PEKERJAAN PERALATAN PANEL

Start: Wed 11231ID: 77 Finish: Tue 12611Dur: 14 days Res:

5.2 PEKERJAAN INSTALASI KABEL FEED

Start: Wed 10191ID: 78 Finish: Tue 11291Dur: 42 days Res:

5.3 PEKERJAAN ARMATUR LAMPU, SA

Start: Wed 11301ID: 79 Finish: Tue 12201Dur: 21 days Comp: 0

5.4 PEKERJAAN INSTALASI FINAL

Start: Wed 11911ID: 82 Finish: Tue 12611Dur: 28 days Comp: 0

5.5 PEKERJAAN KABEL TRAY

Start: Wed 10261ID: 85 Finish: Tue 11291Dur: 35 days Comp: 0 PEKERJAAN BANTU Start: Wed 10261ID: 87 Finish: Tue 11291Dur: 35 days Res: TESTING COMMISSIONING Start: Wed 11301ID: 88 Finish: Tue 12611Dur: 7 days Res: PEKERJAAN ELEKTRONIK Start: Wed 10261ID: 89 Finish: Tue 12201Dur: 56 days Comp: 0

5.6 PEKERJAAN FIRE ALARM

Start: Wed 11911ID: 90 Finish: Tue 12611Dur: 28 days Comp: 0

5.7 PEKERJAAN SISTEM TELEPON

Start: Wed 11911ID: 97 Finish: Tue 12131Dur: 35 days Comp: 0

5.8 PEKERJAAN RAK KABEL

Start: Wed 10261ID: 102 Finish: Tue 11291Dur: 35 days Comp: 0 PEKERJAAN BANTU Start: Wed 10261ID: 104 Finish: Tue 12131Dur: 49 days Res: TESTING COMMISSIONING Start: Wed 12141ID: 105 Finish: Tue 12201Dur: 7 days Res: PEKERJAAN GWT GROUND WATER TA Start: Wed 11161ID: 106 Finish: Tue 12131Dur: 28 days Comp: 0 PEKERJAAN DINDING TURAP BATU KA Start: Wed 11231ID: 113 Finish: Tue 12201Dur: 28 days Res: PEMASANGAN KABEL SEMENTARA DA Start: Wed 11231ID: 114 Finish: Tue 12201Dur: 28 days Res: PEKERJAAN PENANGKAL PETIR SYSTEM Start: Wed 12141ID: 115 Finish: Tue 12271Dur: 14 days Res: ROOF TANK KUBIKLE2 KOMPARTEME Start: Wed 12211ID: 116 Finish: Tue 12271Dur: 7 days Res: PEKERJAAN STRUKTUR Start: Wed 91411ID: 2 Finish: Tue 12201Dur: 98 days Comp: 0 Instalasi Lantai Dasar Start: Wed 11911ID: 41 Finish: Fri 111111Dur: 3 days Res: Instalasi Lantai 1 Start: Sat 111211ID: 42 Finish: Wed 1116 Dur: 5 days Res: Instalasi Lantai 2 Start: Thu 11171 ID: 43 Finish: Mon 1121 Dur: 5 days Res: Instalasi Lantai 3 Start: Tue 112211ID: 44 Finish: Sat 112611Dur: 5 days Res: Instalasi Lantai 4 Start: Sun 11271 ID: 45 Finish: Thu 12111Dur: 5 days Res: Instalasi Lantai 5 Ruang Mesin Start: Fri 12211 ID: 46 Finish: Tue 12611Dur: 5 days Res: Pengadaan dan pemasangan unit Start: Wed 11211ID: 48 Finish: Wed 1191 Dur: 8 days Res: Instalasi Site Plan Start: Thu 11101 ID: 49 Finish: Thu 11171Dur: 8 days Res: Instalasi Lantai Dasar Start: Fri 111811 ID: 50 Finish: Sat 112611Dur: 9 days Res: Instalasi Lantai 1 Start: Sun 112711ID: 51 Finish: Tue 12611Dur: 10 days Res: Instalasi Site Plan Start: Wed 11211ID: 53 Finish: Fri 111111Dur: 10 days Res: Instalasi Lantai Dasar Start: Sat 111211ID: 54 Finish: Mon 1121 Dur: 10 days Res: Instalasi Lantai 1 Start: Tue 112211ID: 55 Finish: Tue 12611Dur: 15 days Res: Instalasi Lantai 1 Start: Wed 11211ID: 58 Finish: Tue 12131Dur: 42 days Res: Instalasi Site Plan Start: Wed 11211ID: 60 Finish: Sun 11611Dur: 5 days Res: Instalasi Lantai Dasar Start: Mon 11711ID: 61 Finish: Sat 111211Dur: 6 days Res: Instalasi Lantai 1 Start: Sun 11131 ID: 62 Finish: Fri 111811Dur: 6 days Res: Instalasi Lantai 2 Start: Sat 111911ID: 63 Finish: Thu 11241Dur: 6 days Res: Instalasi Lantai 3 Start: Fri 112511 ID: 64 Finish: Wed 1130 Dur: 6 days Res: Instalasi Lantai 4 Start: Thu 12111 ID: 65 Finish: Tue 12611Dur: 6 days Res: Instalasi Lantai 5 Ruang Mesin Start: Wed 12711ID: 66 Finish: Tue 12131Dur: 7 days Res: Instalasi Lantai 1 Start: Wed 10261ID: 71 Finish: Tue 11291Dur: 35 days Res: Instalasi Lantai 1 Start: Wed 10191ID: 73 Finish: Tue 11291Dur: 42 days Res: Pekerjaan Lantai Dasar Start: Wed 11301ID: 80 Finish: Tue 12611Dur: 7 days Res: Pekerjaan Lantai 1 Start: Wed 12711ID: 81 Finish: Tue 12201Dur: 14 days Res: Pekerjaan Lantai Dasar Start: Wed 11911ID: 83 Finish: Tue 11221Dur: 14 days Res: Pekerjaan Lantai 1 Start: Wed 11231ID: 84 Finish: Tue 12611Dur: 14 days Res: Pekerjaan Lantai 1 Start: Wed 10261ID: 86 Finish: Tue 11291Dur: 35 days Res: Pengadaan dan pemasangan unit Start: Wed 11911ID: 91 Finish: Sat 111211Dur: 4 days Res: Instalasi Lantai Dasar Start: Sun 11131 ID: 92 Finish: Thu 11171Dur: 5 days Res: Instalasi Lantai 1 Start: Fri 111811 ID: 93 Finish: Tue 11221Dur: 5 days Res: Instalasi Kabel Feeder Fire Alarm Start: Wed 11231ID: 94 Finish: Sat 112611Dur: 4 days Res: Instalasi Detector Fire Alarm Lantai Da Start: Sun 11271 ID: 95 Finish: Thu 12111Dur: 5 days Res: Instalasi Detector Fire Alarm Lantai 1 Start: Fri 12211 ID: 96 Finish: Tue 12611Dur: 5 days Res: Pengadaan dan pemasangan sistem te Start: Wed 11911ID: 98 Finish: Tue 11151Dur: 7 days Res: Pengadaan dan pemasangan outlet te Start: Wed 11161ID: 99 Finish: Wed 1123 Dur: 8 days Res: Instalasi Kabel Feeder Telepon Start: Thu 11241 ID: 100 Finish: Sat 12311 Dur: 10 days Res: Instalasi Outlet Telepon Start: Sun 12411 ID: 101 Finish: Tue 12131Dur: 10 days Res: Pekerjaan Lantai 1 Start: Wed 10261ID: 103 Finish: Tue 11291Dur: 35 days Res: Pekerjaan Ground Water Tank GWT Start: Wed 11161ID: 107 Finish: Tue 12131Dur: 28 days Res: Pekerjaan Rumah Pompa Start: Wed 11161ID: 108 Finish: Tue 12131Dur: 28 days Comp: 0 Pekerjaan Struktur Start: Wed 11161ID: 109 Finish: Tue 11221Dur: 7 days Res: Pekerjaan Finishing Start: Wed 11231ID: 110 Finish: Tue 11291Dur: 7 days Res: Pekerjaan Elektrikal dan Mekanikal Start: Wed 11301ID: 111 Finish: Tue 12611Dur: 7 days Res: Pekerjaan Kusen dan Pintu Start: Wed 12711ID: 112 Finish: Tue 12131Dur: 7 days Res: Pengadaan dan pemasangan unit Start: Wed 11211ID: 39 Finish: Fri 11411 Dur: 3 days Res:

1.2 INSTALASI AIR KOTOR