ID Task
Mode Task Name
Duration Start
Finish Predecessors
Successors 1
PEKERJAAN PERSIAPAN 21 days
Wed 9711 Tue 92711
3SS+7 days
2
PEKERJAAN STRUKTUR 98 days
Wed 91411 Tue 122011
3
PEKERJAAN TANAH 28 days
Wed 91411 Tue 101111 1SS+7 days 4SS+7 days
4
PEKERJAAN PONDASI 28 days
Wed 92111 Tue 101811 3SS+7 days 6SS+7 days,78
5
PEKERJAAN KONSTRUKSI BETON LANTAI 1 sd 3 84 days Wed 92811 Tue 122011
6
C.1 LANTAI DASAR ELV. -4.250 - ELV. +0.005 28 days
Wed 92811 Tue 102511 4SS+7 days 7SS+7 days,15FS+7 days
7
C.2 LANTAI 1 ELV. +0.005 - ELV. +4.150 28 days
Wed 10511 Tue 11111 6SS+7 days 8SS+14 days,21FS+7 days,60,61FS+5 days,71FS-7 days,73FS-14
8
C.3 LANTAI 2 ELV. +4.150 - ELV. +8.350 21 days
Wed 101911Tue 11811 7SS+14 days 9SS+7 days,28FS+21 days,62FS+4 days
9
C.4 LANTAI 3 ELV. +8.350 - ELV. +12.550 21 days
Wed 102611Tue 111511 8SS+7 days 10SS+7 days,30FS+21 days,63FS+3 days
10
C.5 LANTAI 4 ELV. +12.550 - ELV. +16.750 21 days
Wed 11211 Tue 112211 9SS+7 days 11SS+7 days,33FS+21 days,12SS,64FS+2 days,77
11
C.6 LANTAI 5 ELV. +16.750 - ELV. +21.250 21 days
Wed 11911 Tue 112911 10SS+7 days 35FS+14 days,65FS+1 day,66FS+7 days,91SS,98SS,107SS+7 da
12
C.7 LANTAI ATAP 49 days
Wed 11211 Tue 122011 10SS,66FF+7 days 91SS+7 days,98SS+7 days,116,115FS-7 days
13
PEKERJAAN ARSITEKTUR 56 days
Wed 11211 Tue 122711
14
LANTAI DASAR 42 days
Wed 11211 Tue 121311
15
A.1 PEK. DINDING 21 days
Wed 11211 Tue 112211 6FS+7 days 17SS+7 days,18SS+7 days,39SS,48SS,53SS,80FS+7 days,83FF,9
16
A.2 PEK. LANTAI 14 days
Wed 111611Tue 112911 18SS+7 days 41SS-7 days,50SS+2 days,54SS-4 days
17
A.3 PEK. KUSEN LENGKAP 21 days
Wed 11911 Tue 112911 15SS+7 days 19
18
A.4 PEK. PLAFOND 14 days
Wed 11911 Tue 112211 15SS+7 days 16SS+7 days,19,80FS+7 days,83FF
19
A.5 PEK. PENGECATAN 14 days
Wed 113011Tue 121311 18,17
20
LANTAI - 1 49 days
Wed 11911 Tue 122711
21
B.1 PEK. DINDING 21 days
Wed 11911 Tue 112911 7FS+7 days,73FF,71F 22,23SS+14 days,24SS+21 days,26FS+7 days,58SS-7 days,84FS
22
B.2 PEK. LANTAI 14 days
Wed 113011Tue 121311 21,51FF+7 days,55FF 25FS+7 days,42SS-18 days
23
B.3 PEK. KUSEN LENGKAP 21 days
Wed 112311Tue 121311 21SS+14 days 25FS+7 days
24
B.4 PEK. PLAFOND 14 days
Wed 113011Tue 121311 21SS+21 days,84FF+725FS+7 days
25
B.5 PEK. SANITAIR 7 days
Wed 122111Tue 122711 22FS+7 days,23FS+7
26
B.6 PEK. PENGECATAN 14 days
Wed 12711 Tue 122011 21FS+7 days 25
27
LANTAI - 2 21 days
Wed 113011Tue 122011
28
C.1 PEKERJAAN KUSEN LENGKAP 21 days
Wed 113011Tue 122011 8FS+21 days
29
LANTAI - 3 21 days
Wed 12711 Tue 122711
30
D.1 PEK. KUSEN LENGKAP 14 days
Wed 12711 Tue 122011 9FS+21 days 31SS+7 days
31
D.2 PEK. PENGECATAN 14 days
Wed 121411Tue 122711 30SS+7 days
32
LANTAI - 4 14 days
Wed 121411Tue 122711
33
E.1 PEK. KUSEN LENGKAP 14 days
Wed 121411Tue 122711 10FS+21 days
34
LANTAI - RUANG MESIN 14 days
Wed 121411Tue 122711
35
F.1 PEKERJAAN LANTAI 14 days
Wed 121411Tue 122711 11FS+14 days,46FF+2
36
PEKERJAAN MEKANIKAL 63 days
Wed 101911Tue 122011
37
1. PEKERJAAN INSTALASI PLAMBING 35 days
Wed 11211 Tue 12611
38
1.1 INSTALASI AIR BERSIH 35 days
Wed 11211 Tue 12611
39
Pengadaan dan pemasangan unit 3 days
Wed 11211 Fri 11411 15SS
40,48SS,67SS
40
Instalasi Site Plan 4 days
Sat 11511 Tue 11811 39
41
41
Instalasi Lantai Dasar 3 days
Wed 11911 Fri 111111 40,16SS-7 days 42
42
Instalasi Lantai 1 5 days
Sat 111211 Wed 11161141,22SS-18 days 43
43
Instalasi Lantai 2 5 days
Thu 111711 Mon 11211142 44
44
Instalasi Lantai 3 5 days
Tue 112211 Sat 112611 43 45
45
Instalasi Lantai 4 5 days
Sun 112711 Thu 12111 44 46
46
Instalasi Lantai 5 Ruang Mesin 5 days
Fri 12211 Tue 12611 45
35FF+21 days
47
1.2 INSTALASI AIR KOTOR 35 days
Wed 11211 Tue 12611
48
Pengadaan dan pemasangan unit 8 days
Wed 11211 Wed 11911 15SS,39SS 49,53SS,67SS
49
Instalasi Site Plan 8 days
Thu 111011 Thu 111711 48 50
50
Instalasi Lantai Dasar 9 days
Fri 111811 Sat 112611 49,16SS+2 days 51
51
Instalasi Lantai 1 10 days
Sun 112711 Tue 12611 50 22FF+7 days
52
1.3 INSTALASI AIR BEKAS 35 days
Wed 11211 Tue 12611
53
Instalasi Site Plan 10 days
Wed 11211 Fri 111111 15SS,48SS 54,67SS
54
Instalasi Lantai Dasar 10 days
Sat 111211 Mon 11211153,16SS-4 days 55
55
Instalasi Lantai 1 15 days
Tue 112211 Tue 12611 54 22FF+7 days
56
2. INSTALASI PEMIPAAN 42 days
Wed 11211 Tue 121311
57
2.1 INSTALASI VENT 42 days
Wed 11211 Tue 121311
58
Instalasi Lantai 1 42 days
Wed 11211 Tue 121311 21SS-7 days 67SS
59
2.2 INSTALASI AIR HUJAN 42 days
Wed 11211 Tue 121311
60
Instalasi Site Plan 5 days
Wed 11211 Sun 11611 7
61,67SS
61
Instalasi Lantai Dasar 6 days
Mon 11711 Sat 111211 60,7FS+5 days 62
62
Instalasi Lantai 1 6 days
Sun 111311 Fri 111811 61,8FS+4 days 63
63
Instalasi Lantai 2 6 days
Sat 111911 Thu 112411 62,9FS+3 days 64
64
Instalasi Lantai 3 6 days
Fri 112511 Wed 11301163,10FS+2 days 65
65
Instalasi Lantai 4 6 days
Thu 12111 Tue 12611 64,11FS+1 day 66
66
Instalasi Lantai 5 Ruang Mesin 7 days
Wed 12711 Tue 121311 65,11FS+7 days 12FF+7 days
67
MATERIAL BANTU 42 days
Wed 11211 Tue 121311 39SS,48SS,53SS,58SS 68FS-7 days
68
TESTING COMMISSIONING 14 days
Wed 12711 Tue 122011 67FS-7 days
69
3. INSTALASI TATA UDARA DAN SISTEM VENTILASI UDARA
42 days Wed
101911 Tue 112911
70
3.1 INSTALASI PEMIPAAN 35 days
Wed 102611Tue 112911
71
Instalasi Lantai 1 35 days
Wed 102611Tue 112911 7FS-7 days 21FF
72
3.2 SALURAN UDARA 42 days
Wed 101911Tue 112911
73
Instalasi Lantai 1 42 days
Wed 101911Tue 112911 7FS-14 days 74SS,21FF
74
MATERIAL BANTU 49 days
Wed 101911Tue 12611 73SS 75
75
TESTING COMMISSIONING 7 days
Wed 12711 Tue 121311 74
76
PEKERJAAN ELEKTRIKAL 63 days
Wed 101911Tue 122011
77
5.1 PEKERJAAN PERALATAN PANEL 14 days
Wed 112311Tue 12611 10,78FS-7 days
78
5.2 PEKERJAAN INSTALASI KABEL FEEDER 42 days
Wed 101911Tue 112911 4 87SS+7 days,77FS-7 days,103SS+7 days
79
5.3 PEKERJAAN ARMATUR LAMPU, SAKLAR, DAN STOP KONTAK
21 days Wed
113011 Tue 122011
80
Pekerjaan Lantai Dasar 7 days
Wed 113011Tue 12611 15FS+7 days,18FS+7 81
81
Pekerjaan Lantai 1 14 days
Wed 12711 Tue 122011 80
82
5.4 PEKERJAAN INSTALASI FINAL 28 days
Wed 11911 Tue 12611
83
Pekerjaan Lantai Dasar 14 days
Wed 11911 Tue 112211 15FF,7FS+7 days,18F 84,103SS-14 days
84
Pekerjaan Lantai 1 14 days
Wed 112311Tue 12611 83,21FS-7 days 24FF+7 days
85
5.5 PEKERJAAN KABEL TRAY 35 days
Wed 102611Tue 112911
86
Pekerjaan Lantai 1 35 days
Wed 102611Tue 112911 7FS-7 days 103SS
87
PEKERJAAN BANTU 35 days
Wed 102611Tue 112911 78SS+7 days 88,104SS
88
TESTING COMMISSIONING 7 days
Wed 113011Tue 12611 87
89
PEKERJAAN ELEKTRONIK 56 days
Wed 102611Tue 122011
90
5.6 PEKERJAAN FIRE ALARM 28 days
Wed 11911 Tue 12611
91
Pengadaan dan pemasangan unit 4 days
Wed 11911 Sat 111211 11SS,12SS+7 days 92
92
Instalasi Lantai Dasar 5 days
Sun 111311 Thu 111711 91,15SS+11 days 93
93
Instalasi Lantai 1 5 days
Fri 111811 Tue 112211 92,21SS+9 days 94
94
Instalasi Kabel Feeder Fire Alarm 4 days
Wed 112311Sat 112611 93 95
95
Instalasi Detector Fire Alarm Lantai Dasar 5 days
Sun 112711 Thu 12111 94,15FS+4 days 96
96
Instalasi Detector Fire Alarm Lantai 1 5 days
Fri 12211 Tue 12611 95,21FS+2 days
24FF+7 days
97
5.7 PEKERJAAN SISTEM TELEPON 35 days
Wed 11911 Tue 121311
98
Pengadaan dan pemasangan sistem telepon 7 days
Wed 11911 Tue 111511 11SS,12SS+7 days 99,115
99
Pengadaan dan pemasangan outlet telepon 8 days
Wed 111611Wed 11231198,21SS+7 days 100,101FS+10 days
100
Instalasi Kabel Feeder Telepon 10 days
Thu 112411 Sat 12311 99
101
101
Instalasi Outlet Telepon 10 days
Sun 12411 Tue 121311 100,99FS+10 days
24FF
102
5.8 PEKERJAAN RAK KABEL 35 days
Wed 102611Tue 112911
103
Pekerjaan Lantai 1 35 days
Wed 102611Tue 112911 78SS+7 days,83SS-14 104SS
104
PEKERJAAN BANTU 49 days
Wed 102611Tue 121311 87SS,103SS 105
105
TESTING COMMISSIONING 7 days
Wed 121411Tue 122011 104
106
PEKERJAAN GWT GROUND WATER TANK DAN RUMAH POMPA
28 days Wed
111611 Tue 121311
107
Pekerjaan Ground Water Tank GWT 28 days
Wed 111611Tue 121311 11SS+7 days 116FS+7 days,109SS,113SS+7 days,114SS+7 days
108
Pekerjaan Rumah Pompa 28 days
Wed 111611Tue 121311
109
Pekerjaan Struktur 7 days
Wed 111611Tue 112211 107SS 110
110
Pekerjaan Finishing 7 days
Wed 112311Tue 112911 109 111
111
Pekerjaan Elektrikal dan Mekanikal 7 days
Wed 113011Tue 12611 110 112
112
Pekerjaan Kusen dan Pintu 7 days
Wed 12711 Tue 121311 111 116FS+7 days
113
PEKERJAAN DINDING TURAP BATU KALI 28 days
Wed 112311Tue 122011 107SS+7 days
114
PEMASANGAN KABEL SEMENTARA DARI PERPUSTAKAAN LAMA KE SDP PERPUSTAKAAN
28 days Wed
112311 Tue 122011 107SS+7 days
115
PEKERJAAN PENANGKAL PETIR SYSTEM ELEKTROSTATIS
14 days Wed
121411 Tue 122711 98,12FS-7 days
116
ROOF TANK KUBIKLE2 KOMPARTEMEN 7 days
Wed 122111Tue 122711 107FS+7 days,112FS+
1220
1213
1227
1227 1227
1227 1220
1213
1129
1220
1220
T W
T F
S S
M T
W T
F S
S M
T W
T F
S S
M T
W T
F S
S M
T W
T F
S S
M T
W T
F S
S M
T W
T F
S S
M T
W T
F S
S M
T W
T F
S S
M T
W T
F S
S M
T W
T F
S S
M T
W T
F S
S M
T W
T F
S S
M T
W T
F S
S M
T W
T F
S S
M T
W T
F S
S M
T W
T F
11 Sep 11, 11
Sep 18, 11 Sep 25, 11
Oct 2, 11 Oct 9, 11
Oct 16, 11 Oct 23, 11
Oct 30, 11 Nov 6, 11
Nov 13, 11 Nov 20, 11
Nov 27, 11 Dec 4, 11
Dec 11, 11 Dec 18, 11
Dec 25, 11
Task Split
Milestone Summary
Project Summary External Tasks
External Milestone Inactive Task
Inactive Milestone Inactive Summary
Manual Task Duration-only
Manual Summary Rollup Manual Summary
Start-only Finish-only
Deadline Critical
Critical Split Progress
Page 1 Project: Proyek Perpustakaan
Date: Mon 72312
PEKERJAAN TANAH
Start: Wed 91411ID: 3 Finish: Tue 10111Dur: 28 days
Res:
PEKERJAAN PONDASI
Start: Wed 92111ID: 4 Finish: Tue 10181Dur: 28 days
Res:
PEKERJAAN KONSTRUKSI BETON LANT
Start: Wed 92811ID: 5 Finish: Tue 12201Dur: 84 days
Comp: 0
C.1 LANTAI DASAR ELV. -4.250 - ELV. +
Start: Wed 92811ID: 6 Finish: Tue 10251Dur: 28 days
Res:
C.2 LANTAI 1 ELV. +0.005 - ELV. +4.150
Start: Wed 10511ID: 7 Finish: Tue 11111Dur: 28 days
Res:
C.3 LANTAI 2 ELV. +4.150 - ELV. +8.350
Start: Wed 10191ID: 8 Finish: Tue 11811Dur: 21 days
Res:
C.4 LANTAI 3 ELV. +8.350 - ELV. +12.55
Start: Wed 10261ID: 9 Finish: Tue 11151Dur: 21 days
Res:
C.5 LANTAI 4 ELV. +12.550 - ELV. +16.7
Start: Wed 11211ID: 10 Finish: Tue 11221Dur: 21 days
Res:
C.6 LANTAI 5 ELV. +16.750 - ELV. +21.2
Start: Wed 11911ID: 11 Finish: Tue 11291Dur: 21 days
Res:
C.7 LANTAI ATAP
Start: Wed 11211ID: 12 Finish: Tue 12201Dur: 49 days
Res:
PEKERJAAN ARSITEKTUR
Start: Wed 11211ID: 13 Finish: Tue 12271Dur: 56 days
Comp: 0
LANTAI DASAR
Start: Wed 11211ID: 14 Finish: Tue 12131Dur: 42 days
Comp: 0
A.1 PEK. DINDING
Start: Wed 11211ID: 15 Finish: Tue 11221Dur: 21 days
Res:
A.2 PEK. LANTAI
Start: Wed 11161ID: 16 Finish: Tue 11291Dur: 14 days
Res:
A.3 PEK. KUSEN LENGKAP
Start: Wed 11911ID: 17 Finish: Tue 11291Dur: 21 days
Res:
A.4 PEK. PLAFOND
Start: Wed 11911ID: 18 Finish: Tue 11221Dur: 14 days
Res:
A.5 PEK. PENGECATAN
Start: Wed 11301ID: 19 Finish: Tue 12131Dur: 14 days
Res:
LANTAI - 1
Start: Wed 11911ID: 20 Finish: Tue 12271Dur: 49 days
Comp: 0
B.1 PEK. DINDING
Start: Wed 11911ID: 21 Finish: Tue 11291Dur: 21 days
Res:
B.2 PEK. LANTAI
Start: Wed 11301ID: 22 Finish: Tue 12131Dur: 14 days
Res:
B.3 PEK. KUSEN LENGKAP
Start: Wed 11231ID: 23 Finish: Tue 12131Dur: 21 days
Res:
B.4 PEK. PLAFOND
Start: Wed 11301ID: 24 Finish: Tue 12131Dur: 14 days
Res:
B.5 PEK. SANITAIR
Start: Wed 12211ID: 25 Finish: Tue 12271Dur: 7 days
Res:
B.6 PEK. PENGECATAN
Start: Wed 12711ID: 26 Finish: Tue 12201Dur: 14 days
Res:
LANTAI - 2
Start: Wed 11301ID: 27 Finish: Tue 12201Dur: 21 days
Comp: 0
C.1 PEKERJAAN KUSEN LENGKAP
Start: Wed 11301ID: 28 Finish: Tue 12201Dur: 21 days
Res:
LANTAI - 3
Start: Wed 12711ID: 29 Finish: Tue 12271Dur: 21 days
Comp: 0
D.1 PEK. KUSEN LENGKAP
Start: Wed 12711ID: 30 Finish: Tue 12201Dur: 14 days
Res:
D.2 PEK. PENGECATAN
Start: Wed 12141ID: 31 Finish: Tue 12271Dur: 14 days
Res:
LANTAI - 4
Start: Wed 12141ID: 32 Finish: Tue 12271Dur: 14 days
Comp: 0
E.1 PEK. KUSEN LENGKAP
Start: Wed 12141ID: 33 Finish: Tue 12271Dur: 14 days
Res:
LANTAI - RUANG MESIN
Start: Wed 12141ID: 34 Finish: Tue 12271Dur: 14 days
Comp: 0
F.1 PEKERJAAN LANTAI
Start: Wed 12141ID: 35 Finish: Tue 12271Dur: 14 days
Res:
PEKERJAAN MEKANIKAL
Start: Wed 10191ID: 36 Finish: Tue 12201Dur: 63 days
Comp: 0
1. PEKERJAAN INSTALASI PLAMBING
Start: Wed 11211ID: 37 Finish: Tue 12611Dur: 35 days
Comp: 0
1.1 INSTALASI AIR BERSIH
Start: Wed 11211ID: 38 Finish: Tue 12611Dur: 35 days
Comp: 0
1.3 INSTALASI AIR BEKAS
Start: Wed 11211ID: 52 Finish: Tue 12611Dur: 35 days
Comp: 0
2. INSTALASI PEMIPAAN
Start: Wed 11211ID: 56 Finish: Tue 12131Dur: 42 days
Comp: 0
2.1 INSTALASI VENT
Start: Wed 11211ID: 57 Finish: Tue 12131Dur: 42 days
Comp: 0
2.2 INSTALASI AIR HUJAN
Start: Wed 11211ID: 59 Finish: Tue 12131Dur: 42 days
Comp: 0
MATERIAL BANTU
Start: Wed 11211ID: 67 Finish: Tue 12131Dur: 42 days
Res:
TESTING COMMISSIONING
Start: Wed 12711ID: 68 Finish: Tue 12201Dur: 14 days
Res:
3. INSTALASI TATA UDARA DAN SISTEM
Start: Wed 10191ID: 69 Finish: Tue 11291Dur: 42 days
Comp: 0
3.1 INSTALASI PEMIPAAN
Start: Wed 10261ID: 70 Finish: Tue 11291Dur: 35 days
Comp: 0
3.2 SALURAN UDARA