PEKERJAAN KABEL TRAY 35 days PEKERJAAN FIRE ALARM 28 days PEKERJAAN SISTEM TELEPON 35 days INSTALASI AIR BERSIH INSTALASI VENT INSTALASI PEMIPAAN

ID Task Mode Task Name Duration Start Finish Predecessors Successors 1 PEKERJAAN PERSIAPAN 21 days Wed 9711 Tue 92711 3SS+7 days 2 PEKERJAAN STRUKTUR 98 days Wed 91411 Tue 122011 3 PEKERJAAN TANAH 28 days Wed 91411 Tue 101111 1SS+7 days 4SS+7 days 4 PEKERJAAN PONDASI 28 days Wed 92111 Tue 101811 3SS+7 days 6SS+7 days,78 5 PEKERJAAN KONSTRUKSI BETON LANTAI 1 sd 3 84 days Wed 92811 Tue 122011 6 C.1 LANTAI DASAR ELV. -4.250 - ELV. +0.005 28 days Wed 92811 Tue 102511 4SS+7 days 7SS+7 days,15FS+7 days 7 C.2 LANTAI 1 ELV. +0.005 - ELV. +4.150 28 days Wed 10511 Tue 11111 6SS+7 days 8SS+14 days,21FS+7 days,60,61FS+5 days,71FS-7 days,73FS-14 8 C.3 LANTAI 2 ELV. +4.150 - ELV. +8.350 21 days Wed 101911Tue 11811 7SS+14 days 9SS+7 days,28FS+21 days,62FS+4 days 9 C.4 LANTAI 3 ELV. +8.350 - ELV. +12.550 21 days Wed 102611Tue 111511 8SS+7 days 10SS+7 days,30FS+21 days,63FS+3 days 10 C.5 LANTAI 4 ELV. +12.550 - ELV. +16.750 21 days Wed 11211 Tue 112211 9SS+7 days 11SS+7 days,33FS+21 days,12SS,64FS+2 days,77 11 C.6 LANTAI 5 ELV. +16.750 - ELV. +21.250 21 days Wed 11911 Tue 112911 10SS+7 days 35FS+14 days,65FS+1 day,66FS+7 days,91SS,98SS,107SS+7 da 12 C.7 LANTAI ATAP 49 days Wed 11211 Tue 122011 10SS,66FF+7 days 91SS+7 days,98SS+7 days,116,115FS-7 days 13 PEKERJAAN ARSITEKTUR 56 days Wed 11211 Tue 122711 14 LANTAI DASAR 42 days Wed 11211 Tue 121311 15 A.1 PEK. DINDING 21 days Wed 11211 Tue 112211 6FS+7 days 17SS+7 days,18SS+7 days,39SS,48SS,53SS,80FS+7 days,83FF,9 16 A.2 PEK. LANTAI 14 days Wed 111611Tue 112911 18SS+7 days 41SS-7 days,50SS+2 days,54SS-4 days 17 A.3 PEK. KUSEN LENGKAP 21 days Wed 11911 Tue 112911 15SS+7 days 19 18 A.4 PEK. PLAFOND 14 days Wed 11911 Tue 112211 15SS+7 days 16SS+7 days,19,80FS+7 days,83FF 19 A.5 PEK. PENGECATAN 14 days Wed 113011Tue 121311 18,17 20 LANTAI - 1 49 days Wed 11911 Tue 122711 21 B.1 PEK. DINDING 21 days Wed 11911 Tue 112911 7FS+7 days,73FF,71F 22,23SS+14 days,24SS+21 days,26FS+7 days,58SS-7 days,84FS 22 B.2 PEK. LANTAI 14 days Wed 113011Tue 121311 21,51FF+7 days,55FF 25FS+7 days,42SS-18 days 23 B.3 PEK. KUSEN LENGKAP 21 days Wed 112311Tue 121311 21SS+14 days 25FS+7 days 24 B.4 PEK. PLAFOND 14 days Wed 113011Tue 121311 21SS+21 days,84FF+725FS+7 days 25 B.5 PEK. SANITAIR 7 days Wed 122111Tue 122711 22FS+7 days,23FS+7 26 B.6 PEK. PENGECATAN 14 days Wed 12711 Tue 122011 21FS+7 days 25 27 LANTAI - 2 21 days Wed 113011Tue 122011 28 C.1 PEKERJAAN KUSEN LENGKAP 21 days Wed 113011Tue 122011 8FS+21 days 29 LANTAI - 3 21 days Wed 12711 Tue 122711 30 D.1 PEK. KUSEN LENGKAP 14 days Wed 12711 Tue 122011 9FS+21 days 31SS+7 days 31 D.2 PEK. PENGECATAN 14 days Wed 121411Tue 122711 30SS+7 days 32 LANTAI - 4 14 days Wed 121411Tue 122711 33 E.1 PEK. KUSEN LENGKAP 14 days Wed 121411Tue 122711 10FS+21 days 34 LANTAI - RUANG MESIN 14 days Wed 121411Tue 122711 35 F.1 PEKERJAAN LANTAI 14 days Wed 121411Tue 122711 11FS+14 days,46FF+2 36 PEKERJAAN MEKANIKAL 63 days Wed 101911Tue 122011 37

1. PEKERJAAN INSTALASI PLAMBING 35 days

Wed 11211 Tue 12611 38

1.1 INSTALASI AIR BERSIH 35 days

Wed 11211 Tue 12611 39 Pengadaan dan pemasangan unit 3 days Wed 11211 Fri 11411 15SS 40,48SS,67SS 40 Instalasi Site Plan 4 days Sat 11511 Tue 11811 39 41 41 Instalasi Lantai Dasar 3 days Wed 11911 Fri 111111 40,16SS-7 days 42 42 Instalasi Lantai 1 5 days Sat 111211 Wed 11161141,22SS-18 days 43 43 Instalasi Lantai 2 5 days Thu 111711 Mon 11211142 44 44 Instalasi Lantai 3 5 days Tue 112211 Sat 112611 43 45 45 Instalasi Lantai 4 5 days Sun 112711 Thu 12111 44 46 46 Instalasi Lantai 5 Ruang Mesin 5 days Fri 12211 Tue 12611 45 35FF+21 days 47

1.2 INSTALASI AIR KOTOR 35 days

Wed 11211 Tue 12611 48 Pengadaan dan pemasangan unit 8 days Wed 11211 Wed 11911 15SS,39SS 49,53SS,67SS 49 Instalasi Site Plan 8 days Thu 111011 Thu 111711 48 50 50 Instalasi Lantai Dasar 9 days Fri 111811 Sat 112611 49,16SS+2 days 51 51 Instalasi Lantai 1 10 days Sun 112711 Tue 12611 50 22FF+7 days 52

1.3 INSTALASI AIR BEKAS 35 days

Wed 11211 Tue 12611 53 Instalasi Site Plan 10 days Wed 11211 Fri 111111 15SS,48SS 54,67SS 54 Instalasi Lantai Dasar 10 days Sat 111211 Mon 11211153,16SS-4 days 55 55 Instalasi Lantai 1 15 days Tue 112211 Tue 12611 54 22FF+7 days 56

2. INSTALASI PEMIPAAN 42 days

Wed 11211 Tue 121311 57

2.1 INSTALASI VENT 42 days

Wed 11211 Tue 121311 58 Instalasi Lantai 1 42 days Wed 11211 Tue 121311 21SS-7 days 67SS 59

2.2 INSTALASI AIR HUJAN 42 days

Wed 11211 Tue 121311 60 Instalasi Site Plan 5 days Wed 11211 Sun 11611 7 61,67SS 61 Instalasi Lantai Dasar 6 days Mon 11711 Sat 111211 60,7FS+5 days 62 62 Instalasi Lantai 1 6 days Sun 111311 Fri 111811 61,8FS+4 days 63 63 Instalasi Lantai 2 6 days Sat 111911 Thu 112411 62,9FS+3 days 64 64 Instalasi Lantai 3 6 days Fri 112511 Wed 11301163,10FS+2 days 65 65 Instalasi Lantai 4 6 days Thu 12111 Tue 12611 64,11FS+1 day 66 66 Instalasi Lantai 5 Ruang Mesin 7 days Wed 12711 Tue 121311 65,11FS+7 days 12FF+7 days 67 MATERIAL BANTU 42 days Wed 11211 Tue 121311 39SS,48SS,53SS,58SS 68FS-7 days 68 TESTING COMMISSIONING 14 days Wed 12711 Tue 122011 67FS-7 days 69

3. INSTALASI TATA UDARA DAN SISTEM VENTILASI UDARA

42 days Wed 101911 Tue 112911 70

3.1 INSTALASI PEMIPAAN 35 days

Wed 102611Tue 112911 71 Instalasi Lantai 1 35 days Wed 102611Tue 112911 7FS-7 days 21FF 72

3.2 SALURAN UDARA 42 days

Wed 101911Tue 112911 73 Instalasi Lantai 1 42 days Wed 101911Tue 112911 7FS-14 days 74SS,21FF 74 MATERIAL BANTU 49 days Wed 101911Tue 12611 73SS 75 75 TESTING COMMISSIONING 7 days Wed 12711 Tue 121311 74 76 PEKERJAAN ELEKTRIKAL 63 days Wed 101911Tue 122011 77 5.1 PEKERJAAN PERALATAN PANEL 14 days Wed 112311Tue 12611 10,78FS-7 days 78 5.2 PEKERJAAN INSTALASI KABEL FEEDER 42 days Wed 101911Tue 112911 4 87SS+7 days,77FS-7 days,103SS+7 days 79

5.3 PEKERJAAN ARMATUR LAMPU, SAKLAR, DAN STOP KONTAK

21 days Wed 113011 Tue 122011 80 Pekerjaan Lantai Dasar 7 days Wed 113011Tue 12611 15FS+7 days,18FS+7 81 81 Pekerjaan Lantai 1 14 days Wed 12711 Tue 122011 80 82

5.4 PEKERJAAN INSTALASI FINAL 28 days

Wed 11911 Tue 12611 83 Pekerjaan Lantai Dasar 14 days Wed 11911 Tue 112211 15FF,7FS+7 days,18F 84,103SS-14 days 84 Pekerjaan Lantai 1 14 days Wed 112311Tue 12611 83,21FS-7 days 24FF+7 days 85

5.5 PEKERJAAN KABEL TRAY 35 days

Wed 102611Tue 112911 86 Pekerjaan Lantai 1 35 days Wed 102611Tue 112911 7FS-7 days 103SS 87 PEKERJAAN BANTU 35 days Wed 102611Tue 112911 78SS+7 days 88,104SS 88 TESTING COMMISSIONING 7 days Wed 113011Tue 12611 87 89 PEKERJAAN ELEKTRONIK 56 days Wed 102611Tue 122011 90

5.6 PEKERJAAN FIRE ALARM 28 days

Wed 11911 Tue 12611 91 Pengadaan dan pemasangan unit 4 days Wed 11911 Sat 111211 11SS,12SS+7 days 92 92 Instalasi Lantai Dasar 5 days Sun 111311 Thu 111711 91,15SS+11 days 93 93 Instalasi Lantai 1 5 days Fri 111811 Tue 112211 92,21SS+9 days 94 94 Instalasi Kabel Feeder Fire Alarm 4 days Wed 112311Sat 112611 93 95 95 Instalasi Detector Fire Alarm Lantai Dasar 5 days Sun 112711 Thu 12111 94,15FS+4 days 96 96 Instalasi Detector Fire Alarm Lantai 1 5 days Fri 12211 Tue 12611 95,21FS+2 days 24FF+7 days 97

5.7 PEKERJAAN SISTEM TELEPON 35 days

Wed 11911 Tue 121311 98 Pengadaan dan pemasangan sistem telepon 7 days Wed 11911 Tue 111511 11SS,12SS+7 days 99,115 99 Pengadaan dan pemasangan outlet telepon 8 days Wed 111611Wed 11231198,21SS+7 days 100,101FS+10 days 100 Instalasi Kabel Feeder Telepon 10 days Thu 112411 Sat 12311 99 101 101 Instalasi Outlet Telepon 10 days Sun 12411 Tue 121311 100,99FS+10 days 24FF 102

5.8 PEKERJAAN RAK KABEL 35 days

Wed 102611Tue 112911 103 Pekerjaan Lantai 1 35 days Wed 102611Tue 112911 78SS+7 days,83SS-14 104SS 104 PEKERJAAN BANTU 49 days Wed 102611Tue 121311 87SS,103SS 105 105 TESTING COMMISSIONING 7 days Wed 121411Tue 122011 104 106 PEKERJAAN GWT GROUND WATER TANK DAN RUMAH POMPA 28 days Wed 111611 Tue 121311 107 Pekerjaan Ground Water Tank GWT 28 days Wed 111611Tue 121311 11SS+7 days 116FS+7 days,109SS,113SS+7 days,114SS+7 days 108 Pekerjaan Rumah Pompa 28 days Wed 111611Tue 121311 109 Pekerjaan Struktur 7 days Wed 111611Tue 112211 107SS 110 110 Pekerjaan Finishing 7 days Wed 112311Tue 112911 109 111 111 Pekerjaan Elektrikal dan Mekanikal 7 days Wed 113011Tue 12611 110 112 112 Pekerjaan Kusen dan Pintu 7 days Wed 12711 Tue 121311 111 116FS+7 days 113 PEKERJAAN DINDING TURAP BATU KALI 28 days Wed 112311Tue 122011 107SS+7 days 114 PEMASANGAN KABEL SEMENTARA DARI PERPUSTAKAAN LAMA KE SDP PERPUSTAKAAN 28 days Wed 112311 Tue 122011 107SS+7 days 115 PEKERJAAN PENANGKAL PETIR SYSTEM ELEKTROSTATIS 14 days Wed 121411 Tue 122711 98,12FS-7 days 116 ROOF TANK KUBIKLE2 KOMPARTEMEN 7 days Wed 122111Tue 122711 107FS+7 days,112FS+ 1220 1213 1227 1227 1227 1227 1220 1213 1129 1220 1220 T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F 11 Sep 11, 11 Sep 18, 11 Sep 25, 11 Oct 2, 11 Oct 9, 11 Oct 16, 11 Oct 23, 11 Oct 30, 11 Nov 6, 11 Nov 13, 11 Nov 20, 11 Nov 27, 11 Dec 4, 11 Dec 11, 11 Dec 18, 11 Dec 25, 11 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Critical Critical Split Progress Page 1 Project: Proyek Perpustakaan Date: Mon 72312 PEKERJAAN TANAH Start: Wed 91411ID: 3 Finish: Tue 10111Dur: 28 days Res: PEKERJAAN PONDASI Start: Wed 92111ID: 4 Finish: Tue 10181Dur: 28 days Res: PEKERJAAN KONSTRUKSI BETON LANT Start: Wed 92811ID: 5 Finish: Tue 12201Dur: 84 days Comp: 0 C.1 LANTAI DASAR ELV. -4.250 - ELV. + Start: Wed 92811ID: 6 Finish: Tue 10251Dur: 28 days Res: C.2 LANTAI 1 ELV. +0.005 - ELV. +4.150 Start: Wed 10511ID: 7 Finish: Tue 11111Dur: 28 days Res: C.3 LANTAI 2 ELV. +4.150 - ELV. +8.350 Start: Wed 10191ID: 8 Finish: Tue 11811Dur: 21 days Res: C.4 LANTAI 3 ELV. +8.350 - ELV. +12.55 Start: Wed 10261ID: 9 Finish: Tue 11151Dur: 21 days Res: C.5 LANTAI 4 ELV. +12.550 - ELV. +16.7 Start: Wed 11211ID: 10 Finish: Tue 11221Dur: 21 days Res: C.6 LANTAI 5 ELV. +16.750 - ELV. +21.2 Start: Wed 11911ID: 11 Finish: Tue 11291Dur: 21 days Res: C.7 LANTAI ATAP Start: Wed 11211ID: 12 Finish: Tue 12201Dur: 49 days Res: PEKERJAAN ARSITEKTUR Start: Wed 11211ID: 13 Finish: Tue 12271Dur: 56 days Comp: 0 LANTAI DASAR Start: Wed 11211ID: 14 Finish: Tue 12131Dur: 42 days Comp: 0 A.1 PEK. DINDING Start: Wed 11211ID: 15 Finish: Tue 11221Dur: 21 days Res: A.2 PEK. LANTAI Start: Wed 11161ID: 16 Finish: Tue 11291Dur: 14 days Res: A.3 PEK. KUSEN LENGKAP Start: Wed 11911ID: 17 Finish: Tue 11291Dur: 21 days Res: A.4 PEK. PLAFOND Start: Wed 11911ID: 18 Finish: Tue 11221Dur: 14 days Res: A.5 PEK. PENGECATAN Start: Wed 11301ID: 19 Finish: Tue 12131Dur: 14 days Res: LANTAI - 1 Start: Wed 11911ID: 20 Finish: Tue 12271Dur: 49 days Comp: 0 B.1 PEK. DINDING Start: Wed 11911ID: 21 Finish: Tue 11291Dur: 21 days Res: B.2 PEK. LANTAI Start: Wed 11301ID: 22 Finish: Tue 12131Dur: 14 days Res: B.3 PEK. KUSEN LENGKAP Start: Wed 11231ID: 23 Finish: Tue 12131Dur: 21 days Res: B.4 PEK. PLAFOND Start: Wed 11301ID: 24 Finish: Tue 12131Dur: 14 days Res: B.5 PEK. SANITAIR Start: Wed 12211ID: 25 Finish: Tue 12271Dur: 7 days Res: B.6 PEK. PENGECATAN Start: Wed 12711ID: 26 Finish: Tue 12201Dur: 14 days Res: LANTAI - 2 Start: Wed 11301ID: 27 Finish: Tue 12201Dur: 21 days Comp: 0 C.1 PEKERJAAN KUSEN LENGKAP Start: Wed 11301ID: 28 Finish: Tue 12201Dur: 21 days Res: LANTAI - 3 Start: Wed 12711ID: 29 Finish: Tue 12271Dur: 21 days Comp: 0 D.1 PEK. KUSEN LENGKAP Start: Wed 12711ID: 30 Finish: Tue 12201Dur: 14 days Res: D.2 PEK. PENGECATAN Start: Wed 12141ID: 31 Finish: Tue 12271Dur: 14 days Res: LANTAI - 4 Start: Wed 12141ID: 32 Finish: Tue 12271Dur: 14 days Comp: 0 E.1 PEK. KUSEN LENGKAP Start: Wed 12141ID: 33 Finish: Tue 12271Dur: 14 days Res: LANTAI - RUANG MESIN Start: Wed 12141ID: 34 Finish: Tue 12271Dur: 14 days Comp: 0 F.1 PEKERJAAN LANTAI Start: Wed 12141ID: 35 Finish: Tue 12271Dur: 14 days Res: PEKERJAAN MEKANIKAL Start: Wed 10191ID: 36 Finish: Tue 12201Dur: 63 days Comp: 0

1. PEKERJAAN INSTALASI PLAMBING

Start: Wed 11211ID: 37 Finish: Tue 12611Dur: 35 days Comp: 0

1.1 INSTALASI AIR BERSIH

Start: Wed 11211ID: 38 Finish: Tue 12611Dur: 35 days Comp: 0

1.3 INSTALASI AIR BEKAS

Start: Wed 11211ID: 52 Finish: Tue 12611Dur: 35 days Comp: 0

2. INSTALASI PEMIPAAN

Start: Wed 11211ID: 56 Finish: Tue 12131Dur: 42 days Comp: 0

2.1 INSTALASI VENT

Start: Wed 11211ID: 57 Finish: Tue 12131Dur: 42 days Comp: 0

2.2 INSTALASI AIR HUJAN

Start: Wed 11211ID: 59 Finish: Tue 12131Dur: 42 days Comp: 0 MATERIAL BANTU Start: Wed 11211ID: 67 Finish: Tue 12131Dur: 42 days Res: TESTING COMMISSIONING Start: Wed 12711ID: 68 Finish: Tue 12201Dur: 14 days Res:

3. INSTALASI TATA UDARA DAN SISTEM

Start: Wed 10191ID: 69 Finish: Tue 11291Dur: 42 days Comp: 0

3.1 INSTALASI PEMIPAAN

Start: Wed 10261ID: 70 Finish: Tue 11291Dur: 35 days Comp: 0

3.2 SALURAN UDARA