Road Network Upgrading Projects of Dili-Liquica and Tibar-Gleno

Página 28 de 104 Government contribution initially estimated at 23.9 million. The loan has a Grace Period of 10 years, repayment period of 30 years and Annual Interest Rate of 0.7 for construction works and 0.01 for other consultancy services. The total project cost to be financed under the Loan Agreement with Japan International Cooperation Agency JICA was estimated at US92.6 million inclusive of government contribution of 23.9 million. However, since the signing of the Loan Agreement, the dollar value of the Yen has declined from JpY 76.8 per dollar at the time of Loan Agreement signing to JpY102 per dollar as of mid 2014. Also, on completion of the Detailed Engineering Design, it was found that the cost of the works was higher than estimated during loan negotiations. The total cost of the project is now 121.4 million of which 51.8 million will be sourced from the JICA Loan and 69.7 million will be from the IF. The first stage of the project concerns Detailed Engineering Design DED and studies. Three international offices of the Nippon Koei group of companies in Joint Venture were appointed to carry out the works and will continue as Supervision Engineers when construction commences which is expected to be towards the end of 2014. Pre-qualification of contractors for package 1 Hera-Manatuto road section is on-going which is expected to be finalized by 3rd quarter of 2014 and start of construction by first quarter of 2015. Package 2 Manatuto-Baucau road section is expected to start the project by 2 nd quarter of 2015. Procurement for this project has suffered significant delays because the Government was waiting the non-objection letter of JICA on the subject bidding documents and is waiting formal justification from the Government regarding the sourcing of the additional funds needed to complete the whole section. For 2015, a total budget of 11.5 million has been allocated to this project.

c. Road Climate Resilience Project of Solerema-Ainaro

This section is an important road connecting the main cities in the north to the southern districts of Ainaro, Covalima and Manufahi. A sum of 40.0 million has been borrowed from the World Bank for this project. The loan was signed in November 2013 and procurement of the contractors for the first three of four sections is nearly complete. The loan comprises two parts: an International Development Agency IDA Credit of 25.0 million and an International Bank for Reconstruction and Development IBRD Loan of 15.0 million. The IDA Credit has a grace period of five years, maturity period of 25 years and interest rate of 2, while the IBRD Loan has grace period of eight years, maturity period of 28 years and variable interest rate based on the LIBOR rate. The Government share of the funding is estimated at 52.0 million. For 2015, a total budget of 11.7 million has been allocated to this project.

d. Road Upgrading Project Manatuto-Natarbora

A second road project using loan assistance from the ADB concerns upgrading the North- South link between Manatuto and Natarbora. ADB financing comprises ADF loan of 10.0