Monthly Progress Report June 2013
Western I ndonesia National Roads I mprovement Project 37
Group Pack
No. Name of Sub-project
Technical Design Review Road Safety Audit Submitted to
PMU Post
-Review Site
Visting Full
-Review Technical
Report
13 SP.Rukis - TJ.Kemuning
Link No.006.0 completed completed completed
ongoing Technical Report
will be sumitted untuil 18th July 2013
AWP -3
14 Painan – Kambang
Link No.017.1 15
Sibolga – Bts TapSel Link No.016.1
completed completed completed ongoing
Full Technical Review Report is not completed
yet by CTC 16
Seblat – Ipuh Link No.010.0
17 Sp.Gng Kemala–Pg.Tampak
Link No.061.1 18
Mukomuko – Bts.Sumbar Link No.015.3
19 Lais - Bintuan
Link No.009.1 completed completed ongoing
- Full Technical Review is
not completed yet by CTC
20 Lubuk Alung – Sicincin
Link No.009.1 21
Lubuk Alung – Kuraitaji Link No.009.1
NEW
1 Jalan Sebelat – Ketahun
Link No.013.005 2
Betungan – Tais Link No.013.018
6.6 Environmental and Social Impact Issues 6.6.1. LARAP for Package No. 01 : Krui – Biha
The report was concurred by the World Bank on 4 January 2013. The draft Monitoring LARAP Report was prepared and submitted by the CTC to PMU on 27
March 2013. The report was then submitted to the Bank on 10 April 2013 and approved by the Bank on 18 April 2013. The package is ready for civil works contract
implementation. The Bank visited the site on 23 to 24 May 2013 regarding compensation payment process, interview with PAPs sampling only and other
information related to the land acquisition.
6.6.2. LARAP for Package No. 02 : Padang Sawah – Simpang Empat
The report was concurred by the World Bank on 13 January 2013. The draft Monitoring LARAP Report was prepared and submitted by the CTC to PMU on 27
March 2013. The report was then submitted to the Bank on 2 April 2013 and approved by the Bank on 18 April 2013. The package is ready for civil works contract
implementation. The Bank visited the site on 21 to 22 May 2013 regarding compensation payment process, interview with PAPs sampling only and other
information related to the land acquisition.
Monthly Progress Report June 2013
Western I ndonesia National Roads I mprovement Project 38
6.6.3. LARAP for Package No. 03 : Manggopoh – Padang Sawah
The report was concurred by the World Bank on 4 January 2013. The draft Monitoring LARAP Report was prepared and submitted by the CTC to PMU on 27
March 2013. The report was then submitted to the Bank on 2 April 2013 and approved by the Bank on 18 April 2013. The package is ready for civil works contract
implementation. The Bank visited the site on 21 to 22 May 2013 regarding compensation payment process, interview with PAPs sampling only and other
information related to the land acquisition.
6.6.4. LARAP for Package No. 04 : Ipuh – Bantal
The report was concurred by the World Bank on 10 December 2012. The Monitoring LARAP Report is being prepared by the CTC. A site visit to Subproject Ipuh-Bantal in
Bengkulu Province was conducted by Environmental Specialist during 13 – 15 March 2013 to check the status of land to be acquired, to estimate of land area which is
affected by the project and to identify the type of land asset affected by project to carry out interview with PAPs, to get information related land acquisition process and
to check the current status of the Appraisal Team readiness for payment of the land acquisition. The CTC found that the land and asset of PAPs have not been paid by
the project. Until the end of April 2013, the land acquisition process is still ongoing.
6.6.5. CTC Site Visit Related to the Land Acquisition
CTC conducted site visit to packages No.6 Lais – Bintunan, 11.6 km, No.11 Bantal – Mukomuko, 50.1 km, No.13 Sp.Rukis – Tj. Kemuning, 56 km, No.19.Psr. Pedati
– Kerkap, 24.5 km, No.18 Mukomuko – Batas Sumbar, 25.8 km, Seblat -Ketahun,
42.45 km, Betungan-Tais, 42.40 km in Bengkulu province on 18 to 21 June 2013
.
CTC checked the following current situation for: i road existing condition, ii status of land to be acquired, iii estimate of land square will be affected by project, and iv
type of land asset affected by project During interview with seperate of PAPs sampling, the CTC found that a the land and asset of PAPs have not been paid by
the project, and b the current status the project in preparing LARAP studies and organize for public consultation.
6.7 Management Information Systems
The Information Management Specialist has been mobilized. He started his assignment on the beginning of May 2013. During this month, he developed a letter database
system as described in section 5.3.2 above.
Letter Database System
The second step of management information system preparation is providing a letter database system. This system will help all administration issue in the WINRIP. This
system will include: i Recording all of letters information into the database system, ii Grouping letters into different of categories and folders that making it easy to find out
later, and iii the hard copy of letters will be stored in the letter shelves, and the soft copy will be saved into the File Storage server