Monthly Progress Report June 2013
Western I ndonesia National Roads I mprovement Project 36
Date Activity
explanation and visited the site of No.1 KRUI~BIHA in order to monitor procurement processes and provide support to the civil works procurement committees for contract package
from 12th June 2013 to 14th June 2013 in Lampung province.
from 18 June 2013 to 21 June 2013
Site Visit for 6 packages of AWP-2 in Bengkulu province
The CTC technical review teamsenior highway engineer, senior road safety auditor, highway engineer visited 4 project sites in Bengkulu for carrying out road inventory, alignment,
pavement condition and moving traffic survey, from 18th June 2013 to 21th June 2013. During this visit, survey work was carried along with the PPK and Bina Marga officials. Meetings were
also held in P2JN office at end of the site visits.
•
Project List for Site Visiting 4 Pacakges in Bengkulu
- No.11 BANTAL - MUKOMUKO Link No.015.2, Bengkulu Province
- No.13 SP.RUKIS - TJ.KEMUNING Link No.006.0 , Bengkulu Province
- NO.6 PS.PEDATI - KERKAP Link No.010.0 , Bengkulu Province
- No. 19 LAIS - BINTUAN Link No.009.1 , Bengkulu Province
from 1 June 2013 to 30 June 2013
Full Technical Review for DED of AWP-2 in Bengkulu province
Design Full Technical Review of 2 packages which are WINRIP AWP-2 in bengkulu province has carried out by the CTC technical review teamsenior highway engineer, senior road safety
auditor. Now, the CTC team are preparing the report which is comment and recommendation for identified issues of each package through the overall technical review design preview, site
visit and full technical review. This comments and recommendation report will be comprised with technical review both road engineering and road safety. And it will be prepared until 18th
July 2013 by CTC technical review team.
•
Project List for Full Technical Review 2 Pacakges in Bengkulu
- No.11 BANTAL - MUKOMUKO Link No.015.2, Bengkulu Province
- No.13 SP.RUKIS - TJ.KEMUNING Link No.006.0 , Bengkulu Province
6.5.2 Current status of the project for technical field as of 30 June 2013.
The details of Progress of Technical Design Reviewing in aspect of road safety audit as of the end of June 2013 is included as Appendix B.
Technical Design Review Road Safety Audit Report Status
Group Pack
No. Name of Sub-project
Technical Design Review Road Safety Audit Submitted to
PMU Post
-Review Site
Visting Full
-Review Technical
Report
AWP -2
5 Sp.Rampa – Poriaha
Link No.015.xx completed completed completed
ongoing Full Technical Review
Report is not completed yet by CTC
6 PS.Pedati - Kerkap
Link No.010.0 completed completed ongoing
- Full Technical Review is
not completed yet by CTC
7 Indrapura – Tapan
Link No.019.0 8
Bts.Pariaman – Manggopoh Link No.024.0
9 Rantau Tijang – Kota Agung
Link No.026.1 10
Sp.Empat – Sp. Air Balam Link No.034.1
11 Bantal - Mukomuko
Link No.015.2 completed completed completed
ongoing Technical Report
will be sumitted untuil 18
th
July 2013 12
Kambang – Indrapura Link No.017.2
Monthly Progress Report June 2013
Western I ndonesia National Roads I mprovement Project 37
Group Pack
No. Name of Sub-project
Technical Design Review Road Safety Audit Submitted to
PMU Post
-Review Site
Visting Full
-Review Technical
Report
13 SP.Rukis - TJ.Kemuning
Link No.006.0 completed completed completed
ongoing Technical Report
will be sumitted untuil 18th July 2013
AWP -3
14 Painan – Kambang
Link No.017.1 15
Sibolga – Bts TapSel Link No.016.1
completed completed completed ongoing
Full Technical Review Report is not completed
yet by CTC 16
Seblat – Ipuh Link No.010.0
17 Sp.Gng Kemala–Pg.Tampak
Link No.061.1 18
Mukomuko – Bts.Sumbar Link No.015.3
19 Lais - Bintuan
Link No.009.1 completed completed ongoing
- Full Technical Review is
not completed yet by CTC
20 Lubuk Alung – Sicincin
Link No.009.1 21
Lubuk Alung – Kuraitaji Link No.009.1
NEW
1 Jalan Sebelat – Ketahun
Link No.013.005 2
Betungan – Tais Link No.013.018
6.6 Environmental and Social Impact Issues 6.6.1. LARAP for Package No. 01 : Krui – Biha
The report was concurred by the World Bank on 4 January 2013. The draft Monitoring LARAP Report was prepared and submitted by the CTC to PMU on 27
March 2013. The report was then submitted to the Bank on 10 April 2013 and approved by the Bank on 18 April 2013. The package is ready for civil works contract
implementation. The Bank visited the site on 23 to 24 May 2013 regarding compensation payment process, interview with PAPs sampling only and other
information related to the land acquisition.
6.6.2. LARAP for Package No. 02 : Padang Sawah – Simpang Empat
The report was concurred by the World Bank on 13 January 2013. The draft Monitoring LARAP Report was prepared and submitted by the CTC to PMU on 27
March 2013. The report was then submitted to the Bank on 2 April 2013 and approved by the Bank on 18 April 2013. The package is ready for civil works contract
implementation. The Bank visited the site on 21 to 22 May 2013 regarding compensation payment process, interview with PAPs sampling only and other
information related to the land acquisition.