All activities which have undertaken during this month Date

Monthly Progress Report June 2013 Western I ndonesia National Roads I mprovement Project 36 Date Activity explanation and visited the site of No.1 KRUI~BIHA in order to monitor procurement processes and provide support to the civil works procurement committees for contract package from 12th June 2013 to 14th June 2013 in Lampung province. from 18 June 2013 to 21 June 2013 Site Visit for 6 packages of AWP-2 in Bengkulu province The CTC technical review teamsenior highway engineer, senior road safety auditor, highway engineer visited 4 project sites in Bengkulu for carrying out road inventory, alignment, pavement condition and moving traffic survey, from 18th June 2013 to 21th June 2013. During this visit, survey work was carried along with the PPK and Bina Marga officials. Meetings were also held in P2JN office at end of the site visits. • Project List for Site Visiting 4 Pacakges in Bengkulu - No.11 BANTAL - MUKOMUKO Link No.015.2, Bengkulu Province - No.13 SP.RUKIS - TJ.KEMUNING Link No.006.0 , Bengkulu Province - NO.6 PS.PEDATI - KERKAP Link No.010.0 , Bengkulu Province - No. 19 LAIS - BINTUAN Link No.009.1 , Bengkulu Province from 1 June 2013 to 30 June 2013 Full Technical Review for DED of AWP-2 in Bengkulu province Design Full Technical Review of 2 packages which are WINRIP AWP-2 in bengkulu province has carried out by the CTC technical review teamsenior highway engineer, senior road safety auditor. Now, the CTC team are preparing the report which is comment and recommendation for identified issues of each package through the overall technical review design preview, site visit and full technical review. This comments and recommendation report will be comprised with technical review both road engineering and road safety. And it will be prepared until 18th July 2013 by CTC technical review team. • Project List for Full Technical Review 2 Pacakges in Bengkulu - No.11 BANTAL - MUKOMUKO Link No.015.2, Bengkulu Province - No.13 SP.RUKIS - TJ.KEMUNING Link No.006.0 , Bengkulu Province

6.5.2 Current status of the project for technical field as of 30 June 2013.

The details of Progress of Technical Design Reviewing in aspect of road safety audit as of the end of June 2013 is included as Appendix B. Technical Design Review Road Safety Audit Report Status Group Pack No. Name of Sub-project Technical Design Review Road Safety Audit Submitted to PMU Post -Review Site Visting Full -Review Technical Report AWP -2 5 Sp.Rampa – Poriaha Link No.015.xx completed completed completed ongoing Full Technical Review Report is not completed yet by CTC 6 PS.Pedati - Kerkap Link No.010.0 completed completed ongoing - Full Technical Review is not completed yet by CTC 7 Indrapura – Tapan Link No.019.0 8 Bts.Pariaman – Manggopoh Link No.024.0 9 Rantau Tijang – Kota Agung Link No.026.1 10 Sp.Empat – Sp. Air Balam Link No.034.1 11 Bantal - Mukomuko Link No.015.2 completed completed completed ongoing Technical Report will be sumitted untuil 18 th July 2013 12 Kambang – Indrapura Link No.017.2 Monthly Progress Report June 2013 Western I ndonesia National Roads I mprovement Project 37 Group Pack No. Name of Sub-project Technical Design Review Road Safety Audit Submitted to PMU Post -Review Site Visting Full -Review Technical Report 13 SP.Rukis - TJ.Kemuning Link No.006.0 completed completed completed ongoing Technical Report will be sumitted untuil 18th July 2013 AWP -3 14 Painan – Kambang Link No.017.1 15 Sibolga – Bts TapSel Link No.016.1 completed completed completed ongoing Full Technical Review Report is not completed yet by CTC 16 Seblat – Ipuh Link No.010.0 17 Sp.Gng Kemala–Pg.Tampak Link No.061.1 18 Mukomuko – Bts.Sumbar Link No.015.3 19 Lais - Bintuan Link No.009.1 completed completed ongoing - Full Technical Review is not completed yet by CTC 20 Lubuk Alung – Sicincin Link No.009.1 21 Lubuk Alung – Kuraitaji Link No.009.1 NEW 1 Jalan Sebelat – Ketahun Link No.013.005 2 Betungan – Tais Link No.013.018 6.6 Environmental and Social Impact Issues 6.6.1. LARAP for Package No. 01 : Krui – Biha The report was concurred by the World Bank on 4 January 2013. The draft Monitoring LARAP Report was prepared and submitted by the CTC to PMU on 27 March 2013. The report was then submitted to the Bank on 10 April 2013 and approved by the Bank on 18 April 2013. The package is ready for civil works contract implementation. The Bank visited the site on 23 to 24 May 2013 regarding compensation payment process, interview with PAPs sampling only and other information related to the land acquisition.

6.6.2. LARAP for Package No. 02 : Padang Sawah – Simpang Empat

The report was concurred by the World Bank on 13 January 2013. The draft Monitoring LARAP Report was prepared and submitted by the CTC to PMU on 27 March 2013. The report was then submitted to the Bank on 2 April 2013 and approved by the Bank on 18 April 2013. The package is ready for civil works contract implementation. The Bank visited the site on 21 to 22 May 2013 regarding compensation payment process, interview with PAPs sampling only and other information related to the land acquisition.