Western I ndonesia National Roads I mprovement Project 4 - 14
4.6.2.2 Social Issues
1. Monitoring Report of the LARAP Package No. 1
: Krui Biha
Province : Lampung
A. Previous Status : •
LARAP implementation documents approved by World Bank on January 4, 2013 •
Monitoring Report No.1 revised approved by World Bank on June 26, 2013 •
Monitoring Report No.2 approved by World Bank on October 20, 2015. B. Pending Issues, Concern and Actions
• No more issue, LARAP fully completed.
C. Update during this reporting month of June 2016 a Construction completed in January 20, 2016.
b Total PAP = 2,815 ; Compensated = 2,815 ; Percent complete = 100.
2. Monitoring Report of the LARAP Package No. 2
: Padang Sawah Sp. Empat
Province : Sumatera Barat
A. Previous Status : •
LARAP documents approved by World Bank on January 13, 2013 •
Monitoring Report No.1 revised approved by World Bank on July 19, 2013 •
Additional LARAP Implementation documents approved by World Bank on July 21, 2014 •
Monitoring Report No.2 approved by World Bank on Feb. 12, 2015 B. Pending Issues, Concern and Actions
a Compensation for 24 PAP along the road link is under compensation payment process by Local Government of West Sumatera Province
b Price negotiation between the Land Acquisition Committee and the remaining 1 PAP along Air Gadang Bridge is still to be finalized.
C. Update during this reporting month of June 2016 a Construction completed in April 19, 2016.
b Total PAP = 466 ; Compensated = 442 ; Percent complete = 94,85. c No update this period
3. Monitoring Report of the LARAP Package No. 3
: Manggopoh Padang Sawah
Province : Sumatera Barat
A. Previous Status : •
LARAP documents approved by World Bank on January 4, 2013 •
Monitoring Reports No.1, 2, 3, 4 and 5 already approved and World Bank issued No Objection Letter NOL.
• Monitoring Report for the remaining 1 PAP already submitted to WB
B. Pending Issues, Concerns and Actions
Western I ndonesia National Roads I mprovement Project 4 - 15
• No more issue, LARAP fully completed.
C. Update during this reporting month of June 2016 a Construction completed on March 17, 2016.
b Total PAP = 1,338 ; Compensated = 1,338 ; Percen complete = 100.
4. Monitoring Report of the LARAP Package No. 4
: Ipuh Bantal
Province : Bengkulu
A. Previous Status : •
LARAP documents approved by World Bank on December 10, 2012 •
Monitoring Report No.1, 2 and 3 already approved and No Objection Letter NOL were issued by World Bank
B. Pending Issues, Concern and Actions •
No more issue, LARAP fully completed. C. Update during this reporting month of June 2016
a Construction completed in April 11, 2016. b Total PAP = 261 ; Compensated = 261 ; Percent complete = 100.
5. Monitoring Report of the LARAP Package No. 5
: Sp. Rampa Poriaha
Province : Sumatera Utara
A. Previous Status : •
LARAP documents approved by World Bank on September 16, 2013. •
World Bank accepted the revised LARAP documents and issued No Objection Letter on November 12, 2013 to the action plan implementation of the LARAP.
• Additional LARAP documents approved by World Bank on January 8, 2016.
B. Pending Issues, Concern and Actions a Still to be submitted is the implementation report from Satker of the completed relocation
of the kiosk. b Existing permit on forest land for road project from Ministry of Forest still need to be
clarified.. c Monitoring Report for the LARAP implementation of the completed relocation of the kiosk
still to be prepared for submission to World Bank. d Monitoring Report for the compensation payments of the 68 PAP still to be prepared for
submission to WB. C. Update during this reporting month of June 2016
a Documents for the payments of the 68 PAPs are under preparation. b Total PAP = 71 ; Compensated = 68; Percent Complete = 96.
6. Monitoring Report of the LARAP Package No. 6
: Pasar Pedati - Kerkap Province
: Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2015 a No Objection Letter on the revised LARAP documents for