Package No.10 Sp. Empat

Western I ndonesia National Roads I mprovement Project 1 - 7 During this reporting month of June 2016, Contract Agreement has been executed on June 1, 2016 between Pejabat Pembuat Komitmen 6 PPK 6 on behalf of the Government Of Indonesia GOI as the Employeer and PT. Nindya Karya Persero Wilayah I, the Contractor, for a contract amount of Rp. 113,818,300,000 and contract period of 540 calendar days and 730 calendar days defects liability period. Copy of the signed Contract Agreement was submitted on June 15, 2016 to World Bank requesting no objection on the agreement and issuance of Form 384 for disbursement. The Bank pose no objection to the agreement and issued on June 21, 2016 the Form 384. However, the Bank noted minor mistake on the Bill of Quantity, specifically the sub- total amount for Structure which should be corrected as Rp. 1,898,058,025 instead of Rp. 1,876,996,780 and to be reflected on the summary of contract amount. It is expected that advance payment to the Contractor will be released anytime this coming month of July 2016 as well as the issuance of Notice To Proceed NTP to commence the works.

5. Package No.21 Lubuk Alung - Kuraitaji AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road lenght covers 16.80 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As mentioned in last month progress report, the Ministry of PWH issued letter on May 3, 2016 accepting the Bid Evaluation Report BER and recommendation for award of contract to the evaluated lowest responsive bidder, PT. Multi Structure, for a corrected contract amount of Rp.126,301,990,000. During this reporting month of June 2016, Contract Agreement has been executed on June 1, 2016 between Pejabat Pembuat Komitmen 10 PPK on behalf of the Government of Indonesia GOI, the Employeer and PT. Multi Structure, the Contractor, for a contract amount of Rp. 126,301,990,000 and contract time of 540 calendar days and 730 calendar days defects liability period. Copy of the signed Contract Agreement was submitted on June 15, 2016 to World Bank requesting no objection on the agreement and issuance of Form 384 for disbursement. The Bank pose no objection to the agreement and issued on June 21, 2016 the Form 384. It is expected that advance payment to the Contractor will be released anytime this coming month of July 2016 as well as the issuance of Notice To Proceed NTP to Commence the works.