Package No.10 Sp. Empat
Western I ndonesia National Roads I mprovement Project 1 - 7
During this reporting month of June 2016, Contract Agreement has been executed on June 1, 2016 between Pejabat Pembuat Komitmen 6 PPK 6 on behalf of the
Government Of Indonesia GOI as the Employeer and PT. Nindya Karya Persero Wilayah I, the Contractor, for a contract amount of Rp. 113,818,300,000 and contract
period of 540 calendar days and 730 calendar days defects liability period.
Copy of the signed Contract Agreement was submitted on June 15, 2016 to World Bank requesting no objection on the agreement and issuance of Form 384 for
disbursement.
The Bank pose no objection to the agreement and issued on June 21, 2016 the Form 384.
However, the Bank noted minor mistake on the Bill of Quantity, specifically the sub- total amount for Structure which should be corrected as Rp. 1,898,058,025 instead of
Rp. 1,876,996,780 and to be reflected on the summary of contract amount.
It is expected that advance payment to the Contractor will be released anytime this coming month of July 2016 as well as the issuance of Notice To Proceed NTP to
commence the works.