Monthly Progress Report October 2013
Western I ndonesia National Roads I mprovement Project 42
- No.7 INDRAPURA - TAPAN Link No.019.0, West Sumatra Province
- No.8 BTS.PARIAMAN - MANGGOPOH Link No.024.0 , West Sumatra Province
- No.10 SP.EMPAT – SP.AIR BALAM Link No.034.1 , West Sumatra Province
- No.12 KEMBANG- INDRAPURA Link No.017.2 , West Sumatra Province
from 29 October 2013
to 30 October 2013
Attendance the Meeting for WINRIP Pre Implementation Review Mission including Progress Status Procurement plan at Ministry of Public Works World Bank office.
The CTC teamTeam leaders, senior highway engineer, senior road safety auditor, highway engineer joined the Ministry of Public Works meeting with the PMU to discuss about WINRIP Pre
Implementation Review Mission of Civil Works which is included Progress Status procurement plan, at the Ministry of Public Works World Bank Office on 29th~30th October 2013 in Jakarta.
6.5.2 Current status of the project for technical field as of 31 October 2013.
The details of Progress of Technical Design Reviewing in aspect of road safety audit as of the end of October 2013 is included as Appendix B.
Technical Design Review Road Safety Audit Report Status Group
Pack No.
Name of Sub-project Technical Design Review Road Safety Audit
Submitted to PMU
Post -Review
Site Visting
Full -Review
Technical Report
AWP -2
5 Sp.Rampa – Poriaha
Link No.015.xx completed completed completed
completed Final Technical Report is
resubmitted on 17th September 2013
6 PS.Pedati - Kerkap
Link No.010.0 completed completed completed
completed Final Technical Report is
submitted on 17th September 2013
7 Indrapura – Tapan
Link No.019.0 -
By DSC -
By DSC -
By DSC Technical
Advisory Final Technical Advisory is
submitted on 27th September 2013
8 Bts.Pariaman – Manggopoh
Link No.024.0 -
By DSC -
By DSC -
By DSC Technical
Advisory Final Technical Advisory is
submitted on 27th September 2013
9 Rantau Tijang – Kota Agung
Link No.026.1 10
Sp.Empat – Sp. Air Balam Link No.034.1
- By DSC
- By DSC
- By DSC
Technical Advisory
Final Technical Advisory is submitted
on 27th September 2013 11
Bantal - Mukomuko Link No.015.2
completed completed completed completed
Final Technical Report is resubmitted
on 16th August 2013 12
Kambang – Indrapura Link No.017.2
- By DSC
- By DSC
- By DSC
Technical Advisory
Final Technical Advisory is submitted
on 27th September 2013 13
SP.Rukis - TJ.Kemuning Link No.006.0
completed completed completed completed
Final Technical Report is resubmitted
on 16th August 2013
AWP -3
14 Painan – Kambang
Link No.017.1 15
Sibolga – Bts TapSel Link No.016.1
completed completed completed completed
Final Technical Report is submitted
on 23th September 2013
16 Seblat – Ipuh
Link No.010.0 17
Sp.Gng Kemala–Pg.Tampak Link No.061.1
18 Mukomuko – Bts.Sumbar
Link No.015.3 19
Lais - Bintuan Link No.009.1
completed completed completed completed
Final Technical Report is submitted
on 17th September 2013
Monthly Progress Report October 2013
Western I ndonesia National Roads I mprovement Project 43
Group Pack
No. Name of Sub-project
Technical Design Review Road Safety Audit Submitted to
PMU Post
-Review Site
Visting Full
-Review Technical
Report
20 Lubuk Alung – Sicincin
Link No.009.1 21
Lubuk Alung – Kuraitaji Link No.009.1
NEW
1 Jalan Sebelat – Ketahun
Link No.013.005 2
Betungan – Tais Link No.013.018
Additional technical discussion which is for 4 packagesNo.7 No.8 No.10 No.12 will be progressed with BINTEK DSC in order to finalize for technical advisory by CTC , from 11 November 2013 to 15 November 2013.
6.6 Environmental and Social Impact Issues 6.6.1.
LARAP Study Report for Package No. 13 : Sp. Rukis – Tj. Kemuning
The CTC was revised the LARAP report and submit to PMU on 29 October 2013, PMU will process the report to Bank
6.6.2. LARAP Study Report for Package No. 15 : Sibolga – Bts. Tapsel
The CTC was revised LARAP Report and submitted to PMU on 15 October 2013 and to the Bank on 22 October 2013 then the Bank approval on 18 October 2013.
The bidding process can start for this package.
6.6.3. LARAP Study Report for Package No. 16 : Sebelat - Ipuh
The CTC was revised the LARAP report and submit to PMU on 29 October 2013, PMU will process the report to Bank
6.6.4. LARAP Study Report for Package No. 19 : Lais - Bintunan
The CTC was revised the LARAP report and submit to PMU on 29 October 2013, PMU will process the report to Bank
6.7 Management Information System
In October 2013, we continued to build WebGIS. Here we have developing WebGIS application, test the system and integration with the WINRIP website. And in the same
month we also cleaned up of computer viruses at CTC-WINRIP office.