All activities which have undertaken during this month

Monthly Progress Report October 2013 Western I ndonesia National Roads I mprovement Project 42 - No.7 INDRAPURA - TAPAN Link No.019.0, West Sumatra Province - No.8 BTS.PARIAMAN - MANGGOPOH Link No.024.0 , West Sumatra Province - No.10 SP.EMPAT – SP.AIR BALAM Link No.034.1 , West Sumatra Province - No.12 KEMBANG- INDRAPURA Link No.017.2 , West Sumatra Province from 29 October 2013 to 30 October 2013 Attendance the Meeting for WINRIP Pre Implementation Review Mission including Progress Status Procurement plan at Ministry of Public Works World Bank office. The CTC teamTeam leaders, senior highway engineer, senior road safety auditor, highway engineer joined the Ministry of Public Works meeting with the PMU to discuss about WINRIP Pre Implementation Review Mission of Civil Works which is included Progress Status procurement plan, at the Ministry of Public Works World Bank Office on 29th~30th October 2013 in Jakarta.

6.5.2 Current status of the project for technical field as of 31 October 2013.

The details of Progress of Technical Design Reviewing in aspect of road safety audit as of the end of October 2013 is included as Appendix B. Technical Design Review Road Safety Audit Report Status Group Pack No. Name of Sub-project Technical Design Review Road Safety Audit Submitted to PMU Post -Review Site Visting Full -Review Technical Report AWP -2 5 Sp.Rampa – Poriaha Link No.015.xx completed completed completed completed Final Technical Report is resubmitted on 17th September 2013 6 PS.Pedati - Kerkap Link No.010.0 completed completed completed completed Final Technical Report is submitted on 17th September 2013 7 Indrapura – Tapan Link No.019.0 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 27th September 2013 8 Bts.Pariaman – Manggopoh Link No.024.0 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 27th September 2013 9 Rantau Tijang – Kota Agung Link No.026.1 10 Sp.Empat – Sp. Air Balam Link No.034.1 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 27th September 2013 11 Bantal - Mukomuko Link No.015.2 completed completed completed completed Final Technical Report is resubmitted on 16th August 2013 12 Kambang – Indrapura Link No.017.2 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 27th September 2013 13 SP.Rukis - TJ.Kemuning Link No.006.0 completed completed completed completed Final Technical Report is resubmitted on 16th August 2013 AWP -3 14 Painan – Kambang Link No.017.1 15 Sibolga – Bts TapSel Link No.016.1 completed completed completed completed Final Technical Report is submitted on 23th September 2013 16 Seblat – Ipuh Link No.010.0 17 Sp.Gng Kemala–Pg.Tampak Link No.061.1 18 Mukomuko – Bts.Sumbar Link No.015.3 19 Lais - Bintuan Link No.009.1 completed completed completed completed Final Technical Report is submitted on 17th September 2013 Monthly Progress Report October 2013 Western I ndonesia National Roads I mprovement Project 43 Group Pack No. Name of Sub-project Technical Design Review Road Safety Audit Submitted to PMU Post -Review Site Visting Full -Review Technical Report 20 Lubuk Alung – Sicincin Link No.009.1 21 Lubuk Alung – Kuraitaji Link No.009.1 NEW 1 Jalan Sebelat – Ketahun Link No.013.005 2 Betungan – Tais Link No.013.018 Additional technical discussion which is for 4 packagesNo.7 No.8 No.10 No.12 will be progressed with BINTEK DSC in order to finalize for technical advisory by CTC , from 11 November 2013 to 15 November 2013. 6.6 Environmental and Social Impact Issues 6.6.1. LARAP Study Report for Package No. 13 : Sp. Rukis – Tj. Kemuning The CTC was revised the LARAP report and submit to PMU on 29 October 2013, PMU will process the report to Bank

6.6.2. LARAP Study Report for Package No. 15 : Sibolga – Bts. Tapsel

The CTC was revised LARAP Report and submitted to PMU on 15 October 2013 and to the Bank on 22 October 2013 then the Bank approval on 18 October 2013. The bidding process can start for this package.

6.6.3. LARAP Study Report for Package No. 16 : Sebelat - Ipuh

The CTC was revised the LARAP report and submit to PMU on 29 October 2013, PMU will process the report to Bank

6.6.4. LARAP Study Report for Package No. 19 : Lais - Bintunan

The CTC was revised the LARAP report and submit to PMU on 29 October 2013, PMU will process the report to Bank

6.7 Management Information System

In October 2013, we continued to build WebGIS. Here we have developing WebGIS application, test the system and integration with the WINRIP website. And in the same month we also cleaned up of computer viruses at CTC-WINRIP office.