Menghitung interaksi gaya aksial dan momen lentur

Tabel 4.13 Hasil Perhitungan Mux Beban P rencana P mati Pu ton Mux ton.m Muy ton.m Mntu ato Mltu ton ton ton 1,2D+1,6L 18Pu.L 112Pu.L ton.m Mux ton.m 1 1 1.32 3.182 0.795 0.530 1.803 3.699 2 2 1.32 4.782 1.195 0.797 2.710 5.560 3 3 1.32 6.382 1.595 1.064 3.616 7.421 4 4 1.32 7.982 1.995 1.330 4.523 9.282 5 5 1.32 9.582 2.395 1.597 5.430 11.144 6 6 1.32 11.182 2.795 1.864 6.336 13.006 7 7 1.32 12.782 3.195 2.130 7.243 14.868 8 8 1.32 14.382 3.595 2.397 8.150 16.730 9 9 1.32 15.982 3.995 2.664 9.056 18.593 10 10 1.32 17.582 4.395 2.930 9.963 20.456 11 11 1.32 19.182 4.795 3.197 10.870 22.320 12 12 1.32 20.782 5.195 3.464 11.776 24.184 13 13 1.32 22.382 5.595 3.730 12.683 26.048 14 14 1.32 23.982 5.995 3.997 13.590 27.912 15 15 1.32 25.582 6.395 4.264 14.496 29.777 16 16 1.32 27.182 6.795 4.530 15.403 31.642 17 17 1.32 28.782 7.195 4.797 16.310 33.508 18 18 1.32 30.382 7.595 5.064 17.216 35.374 19 19 1.32 31.982 7.995 5.330 18.123 37.240 20 20 1.32 33.582 8.395 5.597 19.030 39.106 21 21 1.32 35.182 8.795 5.864 19.936 40.973 Tabel 4.14 Hasil perhitungan interaksi gaya aksial dan momen lentur Beban Nu ton Sb X Sb Y syarat Kriteria Ketentuan ton NuΦ.Nn NuΦ.Nn Pers. 1 Pers. 2 1 3.1818 0.0298 0.0349 0.2 0.122 1 2 4.7818 0.0448 0.0525 0.2 0.184 1 3 6.3818 0.0597 0.0701 0.2 0.245 1 4 7.9818 0.0747 0.0877 0.2 0.307 1 5 9.5818 0.0897 0.1052 0.2 0.368 1 6 11.1818 0.1046 0.1228 0.2 0.430 1 7 12.7818 0.1196 0.1404 0.2 0.491 1 8 14.3818 0.1346 0.1580 0.2 0.552 1 9 15.9818 0.1496 0.1755 0.2 0.614 1 10 17.5818 0.1645 0.1931 0.2 0.675 1 11 19.1818 0.1795 0.2107 0.2 0.737 1 12 20.7818 0.1945 0.2282 0.2 0.798 1 13 22.3818 0.2095 0.2458 ≥ 0.2 0.881 ≤ 1 14 23.9818 0.2244 0.2634 ≥ 0.2 0.944 ≤ 1 15 25.5818 0.2394 0.2810 ≥ 0.2 1.007 ≤ 1 16 27.1818 0.2544 0.2985 ≥ 0.2 1.070 ≤ 1 17 28.7818 0.2694 0.3161 ≥ 0.2 1.132 ≤ 1 18 30.3818 0.2843 0.3337 ≥ 0.2 1.195 ≤ 1 19 31.9818 0.2993 0.3513 ≥ 0.2 1.258 ≤ 1 20 33.5818 0.3143 0.3688 ≥ 0.2 1.321 ≤ 1 21 35.1818 0.3292 0.3864 ≥ 0.2 1.384 ≤ 1

4.3.2.2 Portal Balok Melintang

Diketahui : Bentang 1 meter Data Profil : WF 300.150.9.9 Beban Mati D : 1318,15 kg = 1,32 ton lihat tabel 4.8 Beban hidup L : ditentukan lihat tabel 4.9 Pu = 1,2 D + 1,6 L lihat tabel 4.9

4.3.2.2.1 Pencarian penampang kompaktak kompak cek klasifikasi profil

Untuk fy = 240 Mpa Kompak λp λr √ 10,973 √ 33,094 √ 108,444 √ 164,602 Mp = Zx . Fy = 13,723 ton.m Zx perlu = 571779 mm3 Syarat → Mp Muϕ

4.3.2.2.2 Parameter

Lateral Torsional Buckling LTB berdasarkan F2 AISC 2010 C = 0,85 Komponen struktur dengan ujung kaku ⁄ ⁄