Estimate OE of Rp. 457,568,535,000 while the 2
nd
lowest bid is quoted by PT. Lancar Jaya M.A.
PT. LTA Joint Operation in the amount of Rp. 358,650,419,000 or 21.62 lower than the Owner s Estimate OE.
Bid Evaluation Report BER is under final preparation by the Procurement Committee and expected to be finalized on or before the 2
nd
week of September 2015.
Procurement of the Last Four 4 Civil Works Contract Packages
Status of the last four 4 remaining contract packages which are scheduled for procurement during the last half of the Year 2015 are as follows:
-
Package No.14 Painan - Kambang AWP-3
DED drawings and associated bidding documents were finalized and for submission to World Bank.
-
Package No.16 Seblat - Ipuh AWP-3
Revised DED drawings and Owner s Estimate were finalized and submitted to World Bank for final review and issuance of the Objection Letter NOL. Other associated
bidding documents are under final preparation.
-
Package No.20 Lubuk Alung - Sicincin AWP-3
Revised DED drawings and Owner s Estimate were finalized and submitted to World Bank for final review and issuance of the Objection Letter NOL. Other associated
bidding documents are under final preparation.
-
Package No.21 Lubuk Alung - Kuraitaji AWP-3
Revised DED drawings and Owner s Estimate were finalized and submitted to World Bank for final review and issuance of the Objection Letter NOL. Other associated
bidding documents are under final preparation
1.5
Procurement of Three 3 Consultancy Packages Under Category 3 of the Loan Agreement, Part 3: Road Sector Institutional Development