Civil Works Implementation WINRIP DOC MPR CTC MPR No.32 2015 08 20150831 00281

Western I ndonesia National Roads I mprovement Project 4 - 4 Table 4.2 Program Contract Package Contractor Name of Road Target Progress Schedule Ending August 2015 Actual Progress Accomplished Slippage Time Elapsed Remaining Time AWP-1 1 PT. Jaya Konstruksi Manggala Pratama Tbk Biha - Krui

84.21 55.51

-28.70 92.81 46 CD 2 PT. Jaya Konstruksi Manggala Pratama Tbk Padang Sawah Sp.Empat incl.Air Gadang

81.03 71.36

-9.67 81.64 134 CD 3 PT. Jaya Konstruksi Manggala Pratama Tbk Manggopoh Padang Sawah

82.69 54.37

-28.32 81.64 134 CD 4 PT. Waskita Karya and PT. Mulya Turangga JO Ipuh - Bantal 89.47

46.28 -43.19

81.10 138 CD

AWP-2 5 PT. Nusa Konstruksi Enjiniring Sp. Rampa - Poriaha

3.89 1.09

-2.80 12.59 472 CD 6 PT. Waskita Karya Tbk Ps. Pedati - Kerkap

8.17 2.27

-5.90 37.11 283 CD 11 PT. Hutama Karya PT. DMT Mukomuko - Bantal

14.17 11.28

-2.89 25.42 537 CD 13 PT. Waskita Karya Persero Tbk Sp. Rukis Tj. Kemuning

0.18 0.36

+0.18 4.72 686CD AWP-3 19 PT. Rodatekindo Purajaya Lais - Bintunan

53.77 33.01

-20.76 55.67 133 CD At the end of this reporting month of August 2015, all the four 4 contract packages being implemented under the AWP-1 were still lagging farther behind schedule. The situation remains the same as in the previous months with no sign in sight to attain substantial progresses to catch- up with the target dates of contract completion. As time is fast approaching toward the contract completion dates, it is doubtful that three 3 of the four 4 contract packages can be completed on the target dates of completion due to huge percentage of unfinished works. It is only Contract PackageNo.2 that the all works can still be completed on time as the construction of Air Gadang Bridge which contributed greatly to the work delays in the previous months is now on-going construction since June 2015. For the five 5 newly started contracts, the Contractors are still concentrated on their mobilization. Roadwork items such as earthworks, drainage and structures have been started. Package No. 1 : Biha Krui As the period ended and based on the proposed revised S-Curve Schedule , the overall actual physical work progress is only 55.51 against the scheduled progress of 84.21 toward the end of the month. As the contract period is about to end in a month time on October 9, 2015, the remaining 44.49 of the works is not possible for the Contractor to finish the Contract in such a short period of time period. Some of the major problems that greatly contributed to the delays were inadequate cash flow, shortage of labor for drainage works and insufficient supply of aggregates for base and asphalt mix. Western I ndonesia National Roads I mprovement Project 4 - 5 Unless a justified time extension with valid reasons is granted to the Contractor the successful completion of the project will not be attained. During the recently concluded joint site inspection and meeting held in the middle of this reporting month, the Contractor informed that they intend to submit request for six 6 month time extension. However, as of this waiting a copy of the request letter is not yet forwarded either to PMU or CTC. A more detailed status of this Package is presented in ANNEX P-I Executive Summary Report. While Attachment No.1 presents the Action Plan from the Contractor to attain timely completion of the Contract Package. Package No. 2 : Padang Sawah Sp. Empat Including Air Gadang Bridge As of end of this month the total overall work progress is 71.3 against the revised scheduled progress of 81.03 . To date, the delayed work is still on a manageable level, but it is still a bit of concern that unless the current problems are addressed immediately, the project cannot be handed over on the target date of completion on January 5, 2016. As of end of this period August 2015 based on the revised schedule, there are still 29 remaining works which are to be completed within the remaining four 4 months of the contract time. As mentioned earlier, high level meeting was held wherein the Contractor committed to complete the sub-project within the stipulated contract period and presented an Action Plan to be implemented. The Action Plan is shown in Attachment No.1. At the rate the Contractor executes the works and considering that the major problems the Contractor are experiencing are resolved on time and strictly implement the Action Plan, most likely the Project could be completed within the contract period. ANNEX P-2 Executive Summary Report present a more detailed status of the Contract Package. Package No. 3 : Manggopoh Padang Sawah Based on the revised work schedule, the current overall work progress of only 54.37 against scheduled progress of 82.69 since the works commenced 20 months ago is of much concern due to the very limited remaining contract time left which is only 4 months till the target date of completion. As of end of this month, the remaining contract time is only 19 or 134 calendar days with still 46 of the works to be completed. For the Contractor to deliver the completion of the contract package on the target date of completion on January 5, 2016, a per month progress of minimum 11.50 shall be attained for the last four 4 months remaining contract time. With the huge projected progress output of 11.50 per month for the last four 4 months contract time for the project to be handed over on time, it is doubtful the completion date can be met, unless the Contractor address all the current problems. As Contractor of this package is the same Contractor of Packages 1 and 2, commitments and