Detailed Design Preparation WINRIP DOC MPR CTC MPR No.32 2015 08 20150831 00281

Western I ndonesia National Roads I mprovement Project 4 - 3 Table 4.1 Program Contract Package Contractor Name of Road Province Contract Signed Commen cement of Work Contract Time Completion Date AWP-1 1 PT. Jaya Konstruksi Manggala Pratama Tbk Biha - Krui Lampung Nov 25, 2013 Jan 8, 2014 640 CD Oct 9, 2015 2 PT.Jaya Konstruksi Manggala Pratama Tbk Padang Sawah Sp. Empat including Air Gadang West Sumatera Dec 6, 2013 Jan 6, 2014 730 CD Jan 5, 2016 3 PT. Jaya Konstruksi Manggala Pratama Tbk Manggopoh Padang Sawah West Sumatera Dec 6, 2013 Jan 6, 2014 730 CD Jan 5, 2016 4 PT. Waskita Karya and PT. Mulya Turangga JO Ipuh - Bantal Bengkulu Nov 14, 2013 Jan 10, 2014 730 CD Jan 9, 2016 AWP-2 5 PT. Nusa Konstruksi Enjiniring Tbk. Sp. Rampa - Poriaha North Sumatera March 17, 2015 June 18, 2015 540 CD Dec 8, 2016 6 PT. Waskita Karya Persero Tbk. Ps. Pedati - Kerkap Bengkulu Feb 27, 2015 Mar 11, 2015 450 CD Jun 2, 2016 11 PT. Hutama KaryaPT. Daya Mulya J.O. Bantal Mukomuko Bengkulu Dec 18, 2014 Feb 23, 2015 720 CD Feb 11, 2017 13 PT. Waskita Karya Persero Tbk. Sp. Rukis TJ. Kemuning Bengkulu Dec 18, 2014 July 22, 2015 720 CD July 10, 2017 AWP-3 15 PT. Pembangunan Perumahan Persero Sibolga Bts. Tapsel North Sumatera July 13, 2015 Still to be issued 810CD Still to be determined 17 PT. Jaya Konstruksi Manggala Pratama Tbk Sp. Gunung Kemala Pugung Tampak Lampung Nov 17, 2014 Still to be issued 720 CD Still to be determined 19 PT. Roda Tekindo Purajaya Bintunan - Lais Bengkulu Feb 27, 2015 Mar 11, 2015 300CD Jan 4, 2016

4.4 Civil Works Progress

To date, nine 9 sub-project are currently on-going construction implementation by different Contractors. Four 4 contracts are under AWP-1, four 4 are in AWP-2 and one 1 is covered by AWP-3. Activities done during this month were repair and restoration of deteriorated existing pavements, roadway excavation, embankment formation, spreading of granular pavement for roadway widening, asphalt paving, structural works, construction of stone masonry side ditches, stockpiling of raw material, production of crush aggregates, other minor works, construction of Air Gadang Bridge and mobilization of the newly started contract package. Progress status of the nine 9 on-going civil work contracts as of this reporting period are shown in Table 4.2.