C. Update during this reporting month of August 2015 a Inventory of affected assets and measurements by Land Acquisition Committeof
the Local Government are completed.
15. Monitoring Report of the LARAP Package No. 15
: Sibolga Bts. Tapsel
Province : Sumatera Utara
A. Previous Status : •
World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction.
B. Pending Issues, Concern and Actions a 1065 from total 1448 PAP is under negosiationcompensation process.
b Monitoring Report No.1 for LARAP implementation for compensation of 40 out of the 1448 PAP still to be prepared by SATKER RIN North Sumatra.
C. Update during this reporting month of August 2015 a 40 from total 1448 PAP already received compensation payment from Satker PJN
North Sumatera.
16. Monitoring Report of the LARAP Package No.16
: Seblat - Ipuh Province
: Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation.
• World Bank issued No Objection Letter NOL on Monitoring Report No.1 for LARAP
implementation. B. Pending Issues, Concern and Actions
a LARAP documents for this Package covers only land acquisition for the road link. If there are land acquisition for the bridge site, a separate LARAP documents need to
be prepared. b LARAP Implementation is underway for the remaining 311 PAP be allocated 2015
national budget and schedule to be settled on August 2015. C. Update during this reporting month of August 2015
a No update this period. b Payment negotiation of the PAP is on-going.
17. Monitoring Report of the LARAP Package No.17
: Sp. Gunung Kemala Pg. Tampak
Province : Lampung
A. Previous Status : •
World Bank approved the corrected LARAP documents on November 12, 2013 B. Pending Issues, Concern and Actions
a Appraisal results under disclosure process by Land Acquisition Committee to the PAP.
Western I ndonesia National Roads I mprovement Project 4 - 19
C. Update during this reporting month of August 2015 a Compensation payments for 989 PAP from total 2,277 have been already released.
Payments of the other PAP s are on-going.
18. Monitoring Report of the LARAP Package No.18
: Mukomuko Bts. Sumbar
Province : Bengkulu
The sub-project is proposed to be deleted from the WINRIP Program.
19. Monitoring Report of the LARAP Package No.19
: Lais - Bintunan Province
: Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2014 No Objection Letter NOL on the revised LARAP documents for implementation
• World Bank issued No Objection Letter NOL on Monitoring Report No.1 for the LARAP
implementation. B. Pending Issues, Concern and Actions
a Remaining 108 PAP and additional 180 PAP, payments are under finalization. C. Update during this reporting month of August 2015
a No update this period.
20. Monitoring Report of the LARAP Package No. 20
: Lubuk Alung - Sicincin Province
: Sumatera Barat
A. Previous Status : •
World Bank issued NOL to LARAP documents on December 19, 2014. B. Pending Issues, Concern and Actions
a LARAP implementation to be implemented by Local Government. C. Update during this reporting month of August 2015.
a Payment of Compensation to PAP is scheduled for September 2015.
21. Monitoring Report of the LARAP Package No. 21
: Lubuk Alung - Kurataji Province
: Sumatera Barat
A. Previous Status : •
World Bank issued NOL to LARAP documents on December 19, 2014. B. Pending Issues, Concern and Actions
a LARAP implementation to be implemented by Local Government. C. Update during this reporting month of August 2015
a Payment of Compensation to PAP is scheduled for September 2015.