Document Library System, used to record all information of document and
Western I ndonesia National Roads I mprovement Project 6 - 2
No. Action
By Whom Status and Target dates
12. Package 2: Accelerate the processing of the necessary
contact modification, which needs to cover all accesses to property and any time extension and send it to the
Bank if it is above 15 PMU
• Mid of July 2015
13. Package 3:
• Send draft amendment for package 3 19 for
prior Bank no-objection, which needs to cover all accesses to property and DSC needs to push
contractor to submit soft drawing of cross section to propose variation order
PMU •
End of July 2015
14. Report back to the Bank on how DGH has implemented
the recommendations of the auditors in the auditing report of the 2012 and 2013 financial statements
partial response at least while waiting for feedback from the Balai
PMU •
Mid of July 2015
15. Accelerate work progress of packages 6, 11, and 19 to
be able to meet the target PMU
• Starting from Mid of
June 2015 16.
Follow up on the meeting with the Inspectorate General of MPW on the financial and technical audits
Bank team •
End of August 2015 17.
Send to the Bank a request for modification of the contract with CTC
PMU •
End of July 2015 18.
Respond to the Bank s comments on the modification of the contract with DSC
PMU •
Mid of July 2015 19.
Regularly submit the quarterly progress reports to the Bank INCLUDE DETAILED INFORMATION ON THE
IMPLEMENTATION OF THE RKPPLs PMU
• July 2015
20. Send restructuring request to the Bank Director
General of Highway has sent a letter to respond some questions of the Minister on May 25, 2015. DirGen of
Highway explained the reason of the cancelation of packages 9 and 18, and the additional budget for the
capacity building on disaster from USD 1 million to USD 1.5 million
Ministry of Finance
• End of September
2015
21. •
Send the response to the Bank on the TFAC reports for packages 2 and 3 and the supervision mission
report for package 1 Response in format similar to EINRIP project
• Send the response to the Bank on the supervision
mission report for package 1 Response in format similar to EINRIP project
PMU •
Mid of July 2015
• Early August 2015
22. Send to Bank monthly supervision reports for packages
with problematic issues PMU
• End of July 2015
23. Have evaluation meeting on LARAP after meeting of
Bank and Director General of Highway Bank and PMU
• August 2015
24. Have internal meeting to evaluate progress of packages
1, 2, 3, and 4 Bank
• August 2015
Western I ndonesia National Roads I mprovement Project 6 - 3