Western I ndonesia National Roads I mprovement Project 38
7 ISSUES and RECOMMENDATIONS
7.1 Current Situation
The main issue during January 2013 is the procurement of four 4 packages under AWP-1. Prolong discussion on the Application Evaluation Reports AERs will have
potentially delay on the tender.
The tender could not be started until the AERs are approved by the Bank even the Bidding Documents are ready to be issued. In the mean time, the existing road
conditions of the four packages under AWP-1, which are predicted being deteriorated rapidly by the traffic during almost a year, shall be properly anticipated.
Another issue is establishment of the Design and Supervision Consultant DSC. It is required to expedite the DSC recruitment process. The DEDs for AWP-2 and AWP-3
packages shall be completed soonest and the procurement can be started immediately.
7.2 Action Required
The project managers PPKs are required to carefully investigate current condition of the existing roads to find out whether the DED is needed to revise or not.
It is hopefully that the Bank will be soon approving the proposed consultants rank based on the Technical Evaluation Report submitted by DGH on 20 December 2012. The
opening of Financial Proposal will be conducted by the DGH’s Procurement Committee after the Bank’s approval on the report.
Western Indonesia National Roads Improvement Project
Appendix A Overall Loan Progress
Exchange Rate : 1 equal to IDR 9,750
31 January 2013
Estimated Contractors or
Total Est. Budget
Starting Completion
Consultants Man-Month
WB + GOI Remarks
Date Date
Name Excl. the
PIP
Original Revised
Physical Man-Month
Physical Man-Month
Physical Man-Month
Supp. Staff
USD, Excl.VAT Excl. VAT
Excl. VAT
MM MM
MM
1 Betterment and Capacity
314,900,000.00 Expansion of National
Roads
1.A AWP-1
ICB DGH
81,630,000.00 Procurement process prequalification.
1.B AWP-2 and AWP-3
ICB NCB DGH
227,100,000.00 Detailed Engineering Design preparation.
1.C Contingency
- DGH
6,170,000.00
2 Implementation Support
6,000,000.00 2.A
Core Team Consultants CTC QCBS
DGH 6-Nov-12
15-Feb-16 PT. Perentjana Djaja
556 5,000,000.00
1,276,700.00 6.791
37.76 3.914
21.76 -2.878
-16.00 Ongoing
Joint Venture with Rp21,415,400,000.00
Yongma Engineering Co.Ltd. Or US equivalent total :
PT. Epadascon Permata 3,473,151.28
2.B Design Superv. Consultants
QCBS DGH
Recruitment process.
2.C Incremental Operating Cost
Varies PMU
1,000,000.00
Including Technical Audits 3
Road Sector Institutional 1,000,000.00
Development 3.A
Capacity Building for NCB
DGH 350,000.00
Preparation of TOR.
Disaster Risks Reduction 3.B
Capacity Building for NCB
DGH 350,000.00
Preparation of TOR.
Environmental Management 3.C
Capacity Building for NCB
DGH 300,000.00
Preparation of TOR.
Road Safety 4
Contingency for Disaster -
DGH -
Risk Response 5
Unallocated -
DGH 18,100,000.00
Total 340,000,000.00
3,473,151.28 6.791
37.76 3.914
21.76 -2.878
-16.00
Appendix - A
OVERALL PROGRESS STATUS
Description
WESTERN INDONESIA NATIONAL ROADS IMPROVEMENT PROJECT WINRIP IBRD LOAN No. 8043-ID
Proc. Method
Category Planned
Actual Balance
PROGRESS
Respon- sibility
Contract ValueBudget Total WB + GOI
CTC
30-Nov-12 31-Dec-12
31-Jan-13 28-Feb-13
31-Mar-13 30-Apr-13
31-May-13 30-Jun-13
31-Jul-13 31-Aug-13
30-Sep-13 31-Oct-13
30-Nov-13
Team Leader 25-Mar-13
0.25 1.25
2.25 3.25
4.25 5.25
6.25 7.25
8.25 Senior Highway
1-Feb-13 1.00
2.00 3.00
4.00 5.00
6.00 7.00
8.00 9.00
10.00 Senior Proc
Senior Road Sft 1-May-13
1.00 2.00
3.00 4.00
5.00 6.00
7.00 Ass. TL
19-Nov-12 0.33
1.33 2.33
3.33 4.33
5.33 6.33
7.33 8.33
9.33 10.33
11.33 12.33
Highway Eng 19-Nov-12
0.33 1.33
2.33 3.33
4.33 5.33
6.33 7.33
8.33 9.33
10.33 11.33
12.33 Qualty Ass. Eng
1-Jul-13 1.00
2.00 2.82
3.82 4.82
Financial 19-Nov-12
0.33 1.33
2.33 3.33
4.33 5.33
6.33 7.33
8.33 9.33
10.33 11.33
12.33 Enviro
17-Dec-12 0.45
1.45 2.45
3.45 4.45
5.45 6.45
7.45 8.45
9.27 10.27
11.27 Socio
19-Nov-12 0.33
1.33 2.33
3.33 4.33
5.33 6.33
7.33 8.33
9.33 10.33
11.33 12.33
Proc. Speclt-1 Proc. Speclt-2
19-Nov-12 0.33
1.33 2.33
3.33 4.35
5.35 6.35
7.35 8.35
9.35 10.35
11.35 12.35
MIS 1-May-13
1.00 2.00
3.00 4.00
5.00 6.00
7.00 Comm.Devlp.
3-Jan-13 1.00
2.00 3.00
4.00 5.00
6.00 7.00
8.00 9.00
10.00 11.00
Total Prof 1.65
7.10 14.10
22.10 30.37
39.37 50.36
61.36 73.36
85.36 97.00
109.00 121.00
Ass. Highway Ass. Financial
19-Nov-12 0.33
1.33 2.33
3.33 4.33
5.33 6.33
7.33 8.33
9.33 10.33
11.33 12.33
Ass. EnvSocio 19-Nov-12
0.33 1.33
2.33 3.33
4.33 5.33
6.33 7.33
8.33 9.33
10.33 11.33
12.33 Ass. MIS
3-Jan-13 1.00
2.00 3.00
4.00 5.00
6.00 7.00
8.00 9.00
10.00 11.00
Ass. Comm. Dev 1-Feb-13
1.00 2.00
3.00 4.00
5.00 6.00
7.00 8.00
9.00 10.00
Ass. Proc-1 3-Jan-13
1.00 2.00
3.00 4.00
5.00 6.00
7.00 8.00
9.00 10.00
11.00 Ass. Proc-2
3-Jan-13 1.00
2.00 3.00
4.00 5.00
6.00 7.00
8.00 9.00
10.00 11.00
Total Sub Prof 0.66
2.66 7.66
13.66 19.66
25.66 31.66
37.66 43.66
49.66 55.66
61.66 67.66
Grand Total 2.31
9.76 21.76
35.76 50.03
65.03 82.02
99.02 117.02
135.02 152.66
170.66 188.66
Mobilized
Total Manmonth Up To