Western I ndonesia National Roads I mprovement Project 25
4.7.5 Third Party Monitoring TPM
All WINRIP packages are designed to have external parties involved in conducting an independent assessment of the project throughout construction.
Project information is accessible through the WINRIP website under construction, project information booth which is normally maintained in the PPKSatkerDinas
office or, project announcement billboard at each site. ACAP requires a third party, from outside the project, to independently monitor the progress of construction work of
each link and these personnel are provided by universities nearby each package.
It was decided that the best method of recruitment for TPM was through the universities closest to each package and PMU mailed invitations asking them to
express their interest in forming independent monitoring teams of Third Party Monitors. This concept is based on the fact that UniversitiesTechnical Faculties
have the engineers available for recruitment and Universities could use this opportunity to be involved in public service. It is hoped that this concept will be more
effective and more efficient in getting legitimate, competent, independent Third Party Monitoring TPM.
The duties of a TPM included:
a
Report to the PPK for his intended package and obtain copies of all drawings and contract documentation.
b
Make at least three 3 separate visits to site, with each visit up to four 4 days long, and ascertain that the works are being carried out in compliance
with the drawings and documentation.
c
Prepare and submit a report for the PMU following each visit with their last report post PHO.
4.8 Road Safety Audit
As stipulated in the TOR, the CTC shall conduct independent Road Safety Audits RSA for all sub-projects. This task is under responsibility of the Senior Road Safety Audit
Engineer. The RSA for AWP-1 shall be conducted one time during construction. The RSA for AWP-2 and AWP-3 shall be conducted each one time during design and each
one time during construction, and make sure that some initial RSA action have to be incorporated in the design for AWP-2 and 3. The purpose of the RSA is to identify the
road safety weaknesses in design during the design and actual construction and make recommendations for realistic improvements which can be handled within the scope of
the construction works of the project. The CTC shall compile all the road safety recommendations in the Road Safety Audit Reports which shall be part of the technical
reports. The RSA report has to be disseminating in particular to the audited packages.
Western I ndonesia National Roads I mprovement Project 26
5 FINANCIAL MANAGEMENT INFORMATION SYSTEMS
5.1 Draw Downs and Future Costs
Details of the disbursements already made from the loan are listed in the following sub section.
5.2 Disbursement
The total disbursement from the loan to the end of January 2013 was USD 800,000.00 equivalent to approximately 0.32 of the loan funds. No disbursement during
the month of January 2013.
The total expenditure to date measured in the term of the World Bank commitment, not including the Special Account advance, is shown in Appendix C. The following
table summarizes the individual disbursements as calculated by CTC but retaining the total disbursement from Client Connection at the end of January 2013.
Category Description
Loan Amount in US
Totals Disbursed to
End March in US
Disbursed
1
Part 1 Betterment
and Capacity Expansion of
National Roads. 220,400,000.00
2
Part 2
Implementation Support
16,000,000.00 674,177.03
4.21
3
Part 3
Road Sector Institutional
Development 1,000,000.00
4
Part 4
Contingency for Disaster Risk
Response Unallocated
12,600,000.00 LN 8043 DA-A
125,822.97
Original Loan Amount
250,000,000.00 800,000.00
0.32
5.3 Management Information System 5.3.1 General Overview
The Management Information System tasks will include the followings:
1 Information System
a. Develop and manage a database system to store soft copy documents into a file storage server.
b. Establish a Document Management System DMS to provide: