Western I ndonesia National Roads I mprovement Project 37

6.8 Quality Assurance

The Quality Assurance Engineer has not yet been mobilized. The activity for project quality assurance will be reported soon after he is in charged. 6.9 Project Risks and Mitigation Measures 6.9.1 Risks Related to Delays Since the detailed engineering design DED is under responsibility of the Design and Supervision Consultant DSC, delay on DSC establishment affected to the procurement of AWP-2 and AWP-3 sub-projects. As discussed previously above, in parallel with the instruction to speed up the process, detailed engineering design DED of some subprojects of WP-2 and WP-3 were prepared and completed by respective P2JN. Considering the WINRIP procurement plan, the Highway Engineer has started Technical Design Review in advance. Package No.5 Sp.Rampa – Poriaha is reviewing.

6.9.2 Financial Risks

The following factors will be monitored during implementation of the loan project. • Loan Amount • Actual Tender Prices • Price Adjustment • Currency Fluctuation • Current Estimated Situation No risk was detected until preparation of this report since the main program of the loan civil works implementation has not yet been started with contract sign.

6.9.3 Risks Related to Quality

The quality of work is inherently tied to the competence of the Contractors and the diligence of the Supervision Teams. The competence or otherwise of contractors shall be considered at the time of bid evaluation and prior to the award of any contract. The quality of supervision however is influenced by the following factors: • Ensuring that supervision staff levels are fully manned with competent, honest, qualified and experienced personnel. • The provision of properly equipped laboratories with properly trained operators for each package. Package supervision comes under the responsibilities of the immediate supervision teams and the relevant DSC but the Quality Assurance Engineer from CTC, when mobilized, will periodically monitor their performance. Western I ndonesia National Roads I mprovement Project 38 7 ISSUES and RECOMMENDATIONS

7.1 Current Situation

The main issue during January 2013 is the procurement of four 4 packages under AWP-1. Prolong discussion on the Application Evaluation Reports AERs will have potentially delay on the tender. The tender could not be started until the AERs are approved by the Bank even the Bidding Documents are ready to be issued. In the mean time, the existing road conditions of the four packages under AWP-1, which are predicted being deteriorated rapidly by the traffic during almost a year, shall be properly anticipated. Another issue is establishment of the Design and Supervision Consultant DSC. It is required to expedite the DSC recruitment process. The DEDs for AWP-2 and AWP-3 packages shall be completed soonest and the procurement can be started immediately.

7.2 Action Required

The project managers PPKs are required to carefully investigate current condition of the existing roads to find out whether the DED is needed to revise or not. It is hopefully that the Bank will be soon approving the proposed consultants rank based on the Technical Evaluation Report submitted by DGH on 20 December 2012. The opening of Financial Proposal will be conducted by the DGH’s Procurement Committee after the Bank’s approval on the report.