Western I ndonesia National Roads I mprovement Project 4 - 3
4.4 Civil Works Progress
Activities done during this month on the on-going construction packages were repair and restoration of deteriorated existing pavements, roadway excavation, embankment formation, spreading of granular
pavement for roadway widening, asphalt paving, structural works, construction of stone masonry side ditches, stockpiling of raw material, production of crush aggregates, other minor works, bridge construction,
finalization of Field Engineering surveys and mobilization of resources of the newly started contract package.
The four 4 contract packages under implementation program AWP-1 were already completed and now under defects liability period for two 2 since the issuance of TOCs.
Under the implementation program AWP-2 and AWP-3, there are currently nine 9 contract packages that are on-going construction implementation and one 1 package on AWP-3 is already completed. Physical
progress of four 4 of the packages are lagging far behind schedule with negative slippages ranging from -17.36 to -42.93 while progress for the other five 5 packages are still slightly on or behind schedule.
Progress status of the on-going civil works contracts as of this reporting period are shown in Table 4.2.
Following are brief status of the on-going construction contract packages :
Package No. 1 : Biha Krui
The contract package is completed on January 20, 2016 and provisionally handed over to the Employeer and currently under Defects Notification Period until after two 2 years reckoned from the issuance of the
TOC.
A more detailed previous status during the whole duration of the contract implementation of this Package is presented in ANNEX P-I Executive Summary Report.
Package No. 2 : Padang Sawah Sp. Empat Including Air Gadang Bridge
The contract package is completed on April 19, 2016 and provisionally handed over to the Employeer and currently under Defects Notification Period until after two 2 years reckoned from the issuance of the
TOC.
ANNEX P-2 Executive Summary Report present a more detailed status during the whole duration of the contract implementation of the Contract Package.