Disbursement WINRIP DOC MPR CTC MPR No.43 2016 7 20160729 00432

Western I ndonesia National Roads I mprovement Project 1 - 6 The Director of Road Network Development, the World Bank and the Procurement Committee POKJA held a special meeting June 21, 2016 to address the issues in order to avoid further delay on the implementation of the Works. It was agreed that POKJA will conduct further re-evaluation of the bids. As of end of this period the outcome of the results of procurement is still under thorough evaluation prior to rendering the final decision.

3. Package No.14 Painan - Kambang AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road length covers 31.50 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As mentioned in last month progress report, Contract Agreement has been executed between Pejabat Pembuat Komitmen 14 PPK on behalf of the Government of Indonesia GOI, the Employeer and PT. Yasa Patria Conbloc, the Contractor, for a contract amount of Rp. 214,327,429,680 and contract time of 630 calendar days and 730 calendar days defects liability period. World Bank issued too, the Form 384 for disbursement. Notice To Proceed NTP to commence the Works is still to be issued subject to clearance of LARAP implementation.

4. Package No.20 Lubuk Alung - Sicincin AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road length covers 14.60 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As mentioned in last month progress report, Contract Agreement has been executed between Pejabat Pembuat Komitmen 6 PPK 6 on behalf of the Government Of Indonesia GOI as the Employeer and PT. Nindya Karya Persero Wilayah I, the Contractor, for a contract amount of Rp. 113,818,300,000 and contract period of 540 calendar days and 730 calendar days defects liability period. World Bank issued too, the Form 384 for disbursement. Notice To Proceed NTP to commence the Works is still to be issued subject clearance of LARAP implementation.

5. Package No.21 Lubuk Alung - Kuraitaji AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road lenght covers 16.80 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As Mentioned in last month progress report, Contract Agreement has been executed between Pejabat Pembuat Komitmen 10 PPK on behalf of the Government of Indonesia GOI, the Employeer and PT. Multi Structure, the Contractor, for a contract Western I ndonesia National Roads I mprovement Project 1 - 7 amount of Rp. 126,301,990,000 and contract time of 540 calendar days and 730 calendar days defects liability period. World Bank issued too, the Form 384 for disbursement. Notice To Proceed NTP to commence the Works is still to be issued subject clearance of LARAP implementation. 1.5 Procurement of Consultancy Package Under Category 2 of the Revised Loan Agreement Reallocation. Technical Assistance for Development of Slope Stabilization, Design and Management The Technical Assistance for Disaster Risk Reduction was canceled based on the results of meeting between DGH and the WB on October 12, 2015. It was decided to cancel the Technical Assistance and replaced by a Technical Assistance for Development of Slope Stabilization, Design and Management under Loan Category- 2. Request for Expression of Interest REOI and the proposed procurement schedule has been issued no objection by the Bank and as scheduled, the REOI was published in UNDB on July 15, 2016 for registration of interested consulting firms. The deadline for submission of Expression of Interest will be on August 4, 2016. Corrections or resivisions were made on the Terms of Reference TOR with respect to cost estimates as the mode of payments of the contract has been changed from Lump Sum to Time Based Contract . The revised TOR has been submitted to World Bank for request issuance of No Objection Letter NOL.