Western I ndonesia National Roads I mprovement Project 6 - 1
6 PROJECT PERFORMANCE
6.1 World Bank and GOI Compliance
6.1.1 World Bank Missions
A World Bank supervision mission for implementation review took place on April 25, 2017 with the kick off and wrap up meetings, respectively.
6.1.2 Agreed Key Actions and Mission Plans during Recent World Bank Mission
Lists of the key actions monitored during the period are listed below.
No. Action
By Whom Update Status
April 25, 2017 New Deadline
25 April 2017
1. Send to the World Bank WB the contract modification
request for package 03 for additional stone masonry World Bank will only approve it if TFAC findings for
packages 2 and 3 are followed upcontractor complies with his defect liability.
PMU and CTC. After the follow-up by
the contractor of the TFAC findings of
packages 3 and 4
2. Send to the WB the request for contract modification
and time extension for package 05. PMU and CTC.
Beginning of June 2017
3. Stop works for 1.59 km where the roads crosses the
protected forest until the IPPKH is obtained. PMU and CTC.
Immediately 4.
Send to the WB the information on the alternative road sections, length and traffic to redo the economic
analysis for package 05. PMU and CTC.
Done
5. Inform the WB about the possibility use ABPN money to
construct the additional drainage under package 06 to avoid that water enters into a housing area.
PMU, CTC and DSC.
May 5, 2017 6.
Provide feedback on the design changes in package 15. WB
After WB field visit in early May
7. Send to the WB report with the results of the
investigation conducted by the Inspectorate General regarding the problem of the undue invoice under
package 14 and the follow up by Bina Marga. PPK, PMU and
CTC May 20, 2017
8. Inform the WB about the outcome of the third show
case for package 12 PT LMA and PT. CTA and the measures to be taken if it fails.
PMU and CTC. 3
rd
Show Cause Meeting conducted.
May 17, 2017
9. Send WB the DSC report with analysis that shows that
the solution is adequate given the deterioration of the pavement cracking one year after overlay for biking
event- possible problems underneath in package 20. DSC, PMU and
CTC. Mid-May 2017.
10. Inform the WB about the results of the second show
case meeting and the actions that will be taken in case it fails for package 21 cash flow problem, not sufficient
capacity for concrete drainage, etc.. DSC.
2
nd
Show Cause Meeting conducted.
May 17, 2017
11. Package 8 may need a variation order for a second lane
for part of the section. No deadline yet
provided 12.
Send to WB request for variation order of Package 17 include 2 new sections.
Mid-May 2017 13.
Submit to the WB the request for final no-objection to the contract for the slope stabilization, design, and
PMU and CTC. Mid-May 2017
Western I ndonesia National Roads I mprovement Project 6 - 2
management. 14.
Submit to the WB formally the procurement plan. PMU and CTC.
Done 15.
Send to the WB the 2
nd
DSC contract modification for price escalation.
PMU and CTC. July 2017
July 2017 16.
Send to the WB formally the request for NOL to CTC contract amendment No. 5.
PMU and CTC. Done
17. Send to the WB the information on how the inundated
spots on the road of package 7 will be fixed. PMU and CTC.
Mid-May 2017 18.
Re-send to the WB the revised environmental management and monitoring plan RKPPL for package
12, including info on AMP and stone crasher licenses. •
Package 12: Done 20 March 2017
• Done submit to WB
29 May 2017
19. Re-send to the WB the revised environmental
management and monitoring plan RKPPLs for package 21 with missing information.
• Packages 21: Done
20 March 2017 •
Done submit to WB 29 May 2017
20. Re-send to the WB the revised environmental
management and monitoring plans RKPPLs for packages 14 and 20 or the documentation showing that
the licensing process was carried out correctly. •
Packages 14 and 20: Done
28 Feb 2017 •
Done submit to WB 29 May 2017
21. Send to the WB environmental management and
monitoring plans RKPPLs for package 16. •
Done CTC submit to PMU on 2 June
2017 under process to WB
22. Revise RKPPLs monitoring reports to include all
necessary information, especially for packages 7 and 12 and send to the Bank.
• Done submit to WB
29 May 2017
23. Implement action plan on how to avoid spills in base
camps and improve base camp management in all packages with problems
• May
31 July 2017 On process
24. Cary out HIVAIDS workshops.
PMUCTC DSC.
• Packages 08, 20,
and 21: Done •
Packages 16: May 2017
• Done on 15 May
2017
25. Provide us with a list of the package with base camp
management issues oil spills, inadequate drainage, specifying the main
PMUCTC Done email to WB on
2 May 2017
26. training on base camp management for contactors,
DSC, PPK WB
Done on 11, 18 22 May 2017
27. PMUCTC will instruct DSC to send a letter to DSC
asking to take the necessary measures among others based on 1. above to improve base camp management
by a certain date and will ask to include photos PMUCTC
On Process CTC email draft letter to PMU on
5 June 2017
28. CTC will do some control visits and report to the Bank
PMUCTC Mid of June 2017
29. CTC will have to figure out what role BLH and the
environmental department of Bina Marga can play to improve performance since this is against the local laws
as well Subdit
LKJPMUCTC Is being coordinated
30. Letter to the contractors informing them that they are
violating the rules DGHPMUCTC
Done the list of letters email to WB on 6 June
2017
31. Send to the WB the final LARAP document for package
05 signed by the relevant Government authority. PMU and CTC.
Done March 10, 2017
Western I ndonesia National Roads I mprovement Project 6 - 3
32. Send to the WB the permission letter from the Forestry
Department for package 05. PMU and CTC.
Under administration process in Forestry
Department. Early of Sep 2017
33. Contract the appraisal team for package 08, 20, and 21
to reassess the affected assets. PMU and CTC.
Done 34.
Request the additional budget necessary to carry out all LARAPs compensation payments in 2017.
PMU. Done
35. Submit to the WB LARAPs monitoring reports for
packages 07, 08, 12, 13, 14, 15, 17, 20, and 21. PMU and CTC.
• Package 13: End
April 2017 •
Packages 14: Mid- May 2017
• Packages 07, 08, 12:
End May 2017 •
Packages 15, 17, 20, 21: No date
provided yet 36.
Send to the WB the LARAP implementation report for the remedial action in package 05.
PMU and CTC. Delayed
• End of May 2017
37. Completely follow up on the FY2015 audit findings, and
send report to the WB. PMU and CTC.
Done 38.
Submit to the WB the 2016 financial audit report. PMU and CTC.
June 27, 2017 •
June 27, 2017 39.
Submit to the WB the quarterly IFR for the period October to December 2016.
PMU. Done
March 20, 2017 40.
Submit to the WB the quarterly IFR for the period January to March 2017.
PMU. May 15, 2017
• May 15, 2017
41. Request additional counterpart funds for the 2017
implementation. PMU.
Done 42.
Send to the WB the TFAC response for packages 20, 21, 14
PMUDSC CTC.
• Package 20: June
1, 2017 •
Packages 21 and 14: June 15, 2017
43. Inform the WB when we will receive the follow up to
TFAC findings for packages 3 never received a feedback - concrete drainage broken, asphalt start waving,
and 2 asphalt already broken. •
Mid-May 2017.
44. Send to the WB the TFAC response for packages 05, 06,
08, 13, 15, and 17. PMUDSC
CTC. •
Package 05: Done March 31, 2017
• Package 06: Done
March 20, 2017 •
Package 08: Done March 31, 2017
• Package 13: Done
March 20, 2017 •
Package 15: Done March 31, 2017
• Package 17: Done
March 20, 2017 45.
Send to the WB informally the draft restructuring proposal.
PMUCTCWB. •
June 2017 46.
Next supervision mission document progress in terms of cancelled component C
WB •
August 2017 47.
Submit regularly to the WB the quarterly progress reports.
PMU. This activity must be
carried out every calendar quarter.
48. Update the newsletter quarterly, including the list of
contracts, implementation progress, project related workshops, and number, typology and status of
PMU. This activity must be
carried out every calendar quarter.