Current Implementation Situation Civil Works

Western I ndonesia National Roads I mprovement Project 1 - 3 Length Ction Km Period J N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Core Team Consultant CTC 40 mth IMPLEMENTATION Time extension for sevices Design Supervision Cslt DSC 42 mth IMPLEMENTATION Time extension for sevices TA for Dev.of Sl ope Sta bi l i za ti on, Desi gn M a na gement IMPLEMENTATION 1 Krui - Biha 25,00 21 mth 8 Jan14 2 Padang Sawah - Sp.Empat 40,90 24 mth 6 Jan14 3 M anggopoh - Padang Sawah 32,00 24 mth 6 Jan14 4 Ipuh - Bantal 42,40 24 mth 10 Jan14 5 SIMPANG RAMPA - PORIAHA 11,10 18 mth 18 Jun15 20 Jul17 11 BANTAL - MUKOMUKO 50,10 24 mth 23 Feb15 26 May17 13 SP RUKIS - TJ KEMUNING 56,30 24 mth 10 Jul17 17 Sp.Gn.KEMALA - Pg. TAMPAK 36,80 24 mth 04 Sep15 23 Agt17 6 PS. PEDATI - KERKAP 25,00 15 mth 11 Mar15 28 Jan17 19 LAIS - BINTUNAN 11,60 10 mth 11 Mar15 CONSTRUCTION 300+125+53 days 30 Jun 16 15 SIBOLGA - BATAS TAPSEL 36,00 27 mth 20 Nov15 7 INDRAPURA - TAPAN 19,50 21 mth 10 Dec15 30 Agt17 8 BTS.Kt PARIAMAN-MANGGOPOH 46,80 24 mth PROC 23 Mar16 10 SIMPANG EMPAT - SP.AIR BALAM 61,70 24 mth 12 KAMBANG - INDRAPURA 55,20 24 mth 14 PAINAN KAMBANG 31,50 21 mth PROC 13 Aug16 16 SEBLAT IPUH 34,50 21 mth 08 Nov16 30 Jul18 20 LUBUK ALUNG SICINCIN 14,60 18 mth 1 Sep16 21 LUBUK ALUNG KURAITAJI 16,80 18 mth 1 Sep16 Original target : 715,60 km ENVIRONMENT SOCIAL SAFEGUARD 1st Revised target : 640,00 km Prequalification Detail Eng Design LARAP Study 2nd Revised target : 586,10 km Road Safety Owners Estimate Appraisal Public Consultation Procurement Sign Contr Bid Document LARAP Implementation Preparation for Commencement of Work Standard Biding Document 31-Des-17 31-Des-17 PROC PROC to be canceled CONSTRUCTION 720 - 71 days Rev-DED RS Rev-DED RS Rev-DED RS 31-Des-17 PROCUREMENT 31-Des-17 31-Des-17 CONSTRUCTION 450+90 days CONSTRUCTION 540 - 53 days CONSTRUCTION 540 - 53 days CONSTRUCTION 630 - 114 days CONSTRUCTION 31-Des-17 31-Des-17 31-Des-17 31-Des-17 6-Nov-12 19-Jun-13 PROC PROC DED Rev-DED RS ICB ICB NCB NCB DED PROC CONSTRUCTION 720 days ICB ICB ICB ICB PROC CONSTRUCTION 810 - 37 days DED CONSTRUCTION 630 days 23-Mei-16 CONSTRUCTION 720 - 132 days NCB NCB NCB Review DED RS Review DED RS SBD OE + BD RSA REVISED DED OE BD DED RSA REVISED DED OE BD SBD OE + BD DED RSA REVISED DED OE BD DED ICB RSA REVISED DED OE BD Review DED RS SBD OE + BD PQ RS Proc COW SBD DED OE BD DED NCB NCB DED Pack PACKAGE NAME 2012 2013 2014 2015 2016 2017 2018 ICB ICB ICB ICB ICB CONSTRUCTION 640 + 93 days 14-Apr-16 PROC 17-Mar-16 CONSTRUCTION 540 + 224 days CONSTRUCTION 730 + 105 days CONSTRUCTION 730 + 75 days CONSTRUCTION 730 + 90 days 31-Mei-16 Review DED RS PQ Review DED RS PQ PQ Review DED RS Review DED RS PROC CONSTRUCTION 720 days CONSTRUCTION 720 days 22-Jul-15 PQ PROC Actual Implementation Timeline of WINRIP Western I ndonesia National Roads I mprovement Project 2 - 1 REF 1.25 0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00 Month Co m pl et e Actual Expenditure USD 112.48 mil 44.99 WINRIP ACTUAL PROGRESS UP TO MAY 2017 AND FORECAST UP TO JUNE 2018 ACTUAL May 2017 Original Forecast Forecast Expenditure Rev USD 98.33 mil 39.33 Forecast May 2017 Deviation = + 5.66

1.2 Disbursement

Loan Allocation and Percent Disbursement To Date The total disbursement summary from the loan by The World Bank to the end of May 2017 was USD 112,475,095.62 equivalent to approximately 44.99 of the loan funds. The following table summarizes the individual disbursements as calculated by CTC but retaining the total disbursement from Client Connection at the end of May 2017. Appendix A shows the Overall Loan Progress Status. Category Description Loan Restructuring Amount US Disbursement This Period Previous Disbursement Totals Disbursed to End May 2017 in US Disbursed 1 Part 1 Betterment and Capacity Expansion of National Roads. 220,400,000.00 3,374,172.25 102,310,817.54 105,684,989.79 46.42 2 Part 2 Implementation Support 17,000,000.00 6,790,105.83 6,790,105.83 39.94 3 Part 3 Road Sector Institutional Development 4 Part 4 Contingency for Disaster Risk Response Unallocated 12,600,000.00 Original Loan Amount 250,000,000.00 3,374,172.25 109,100,923.37 112,475,095.62 44.99 Breakdown of amount disbursed during the period May 2017 are for Statement of Work Accomplished for the following civil works contract package : • Package No.01 : Escalation USD 472,165.21 • Package No.08 : IPC Nos. 09 USD 955,332.99 • Package No.13 : IPC Nos. 07 USD 599,121.35 • Package No.15 : IPC Nos. 05 USD 636,159.96 • Package No.17 : IPC Nos. 19 USD 487,774.27 • Package No.21 : MC Nos. 06 - 07 USD 223,618.47 The Ending balance for Special Account end of May 2017 USD 222,230.35 Include Follow up on BPK audit findings for FY 2014 USD 11,765.00. Western I ndonesia National Roads I mprovement Project 2 - 2

1.3 World Bank Implementation Review Mission and Site Visit

Not performed for this month.

1.4 Procurement of Civil Works Contract Under Category 1 of the Loan Agreement

As of end this reporting month, nineteen 19 contract packages are already procured and are either completed, seven 7 packages had been took over to the employer, eleven 11 packages under construction and the remaining one 1 package is proposed to be cancelled Package No. 10 Sp. Empat Sp. Air Balam is proposed to be cancelled, because the road is still relatively in the good condition and widening is not needed immediately. 1.5 Procurement of Consultancy Package under Category 2 of the Revised Loan Agreement Reallocation. Technical Assistance for Development of Slope Stabilization, Design and Management The Technical Assistance for Disaster Risk Reduction was canceled based on the results of meeting between DGH and the WB on October 12, 2015. It was decided to cancel the Technical Assistance and replaced by a Technical Assistance for Development of Slope Stabilization, Design and Management under Loan Category- 2. The World Bank had issued No Objection Letter for RFP and Shortlisted Consultant respectively on September 23, 2016 and October 27, 2016. The Final Revised of Technical Evaluation Report TER was sent to the World Bank on April 5, 2017 and respond by Bank with issued No Objection Letter on April 7, 2017 for the determination of the technical score of the consultant in this revised TER. The opening of financial was held on April 20, 2017. From three firms who have submitted the proposals, only two financial proposals from the firm who have attained the minimum technical score were opened. One financial proposal from the firm whose technical proposals did not passed the minimum technical score will be returned to him unopened after the signature of the contract. The Procurement Committee POKJA had finalized the Financial Evaluation Report and Award Recommendation on April 27, 2017. This report had sent formally to the World Bank for information on May 15, 2017. The next step, contract negotiation had commenced on May 9, 2017 with the proposed award consultant. Minute of Contract Negotiation and Draft Contract then were sent to the World Bank on May 19, 2017. Review from the World Bank had received on May 29, 2017 which is state in the letter still need some revisions for draft contract and some clarifications from POKJA regarding to justification of replacement professionals for two positions. Related to this selection of consultant, the proposal validity period had extended until June 6, 2017 with NOL from the World Bank and hope the selection process will be completed on the extended proposal validity. Western I ndonesia National Roads I mprovement Project 2 - 3 2 PROJECT DESCRIPTION

2.1 Background

The Government of Indonesia wishes to continue strengthening of the National Road system in Indonesia while the Eastern Indonesia National Roads Improvement Project EINRIP which is assisted by AusAID through the Australian Indonesia Partnership or AIP, is providing support program of National road and bridge improvement works in Eastern Indonesia. The Western Indonesia National Road Improvement Project WINRIP will provide similar support for National road and bridge in the Sumatera region of Indonesia. The focus of WINRIP will be roads administered directly by the National Government, including those currently classified as Provincial, Kabupaten District or non-status roads which are in process of being reclassified as National roads. In addition, provision will be made for major bridge repair works, rehabilitation, duplication and replacement as necessary to complement road betterment works.

2.2 Project Development

The loan effectiveness date for the WINRIP is 12 March 2012 and key project data is shown in the following detail. Key Project Data WINRIP Loan No. 8043-ID Project Cost US350 million Original Loan Amount US250 million Revised Loan Amount NA Board Approval Date 26 May 2011 Loan Signing Date 14 December 2011 Effectiveness Date 12 March 2012 Disbursement as of May 31, 2017 US 112,475,095.62 million 44.99