Western I ndonesia National Roads I mprovement Project 4 - 18
13. Monitoring Report of the LARAP Package No. 13
: Sp. Rukis Tj. Kemuning
Province : Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation.
• Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank.
• World Bank issued on August 18, 2015 No Objection Letter NOL on the Monitoring Report No.1.
• World Bank issued on October 13, 2015 No Objection Letter NOL on the Monitoring Report No.2.
B. Pending Issues, Concern and Actions a Monitoring Report No.3 for compensation payments of 193 PAPs in Kab. Kaur to be
prepared and submitted to WB. C. Update during this reporting month of December 2015
a Compensation payments for the remaining PAP is being done by Satker PJN II Bengkulu. b A Monitoring Report for 193 PAPs is under submission to WB
14. Monitoring Report of the LARAP Package No. 14
: Painan - Kambang Province
: Sumatera Barat
A. Previous Status : •
World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents. •
LARAP s signed action plan was given No Objection Letter NOL by World Bank. B. Pending Issues, Concern and Actions
a Inventory of affected assets and measurement by Land Acquisition Committe of the Local Government are completed. Appraisal to be done as soon as possible.
C. Update during this reporting month of November 2015 a Appraisal process of affected assets is underway.
15. Monitoring Report of the LARAP Package No. 15
: Sibolga Bts. Tapsel
Province : Sumatera Utara
A. Previous Status : •
World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction.
• Monitoring Report No.1 for 40 of the remaining 1554 PAPs was given No Objection Letter NOL
on November 16, 2015 by the World Bank. B. Pending Issues, Concern and Actions
a 1.129from total 1.554 PAP is under negotiationcompensation process. C. Update during this reporting month of December 2015
a Compensation payment for 425 from 1554 PAPs already paid. The payment of the remaining PAPs is under process.
b Monitoring Report-2 for the compensation payment for 72 from total 1.514 PAPs already submission to WB
Western I ndonesia National Roads I mprovement Project 4 - 19
16. Monitoring Report of the LARAP Package No.16
: Seblat - Ipuh Province
: Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation.
• World Bank issued No Objection Letter NOL on Monitoring Report No.1 and 2 for LARAP
implementation. •
Monitoring Report for 102 of the remaining 120 PAPs was given No Objection Letter NOL by World Bankon November 26, 2015.
B. Pending Issues, Concern and Actions a LARAP documents for this Package covers only land acquisition for the road link. If there are
land acquisition for the bridge site, a separate LARAP documents need to be prepared. b LARAP Implementation is underway for the remaining 120 PAP be allocated 2015 national
budget and schedule to be settled on Dec 2015. C. Update during this reporting month of December 2015
a All of the total 259 PAPs already paid by Satker PJN I Bengkulu. b Data of the payments to the 18 PAP Balance from 259 PAPs are under preparation
17. Monitoring Report of the LARAP Package No.17
: Sp. Gunung Kemala Pg. Tampak
Province : Lampung
A. Previous Status : •
World Bank approved the corrected LARAP documents on November 12, 2013 •
Monitoring Report for 154 of the total 2.273 PAPs was given No Objection Letter NOL on October 13, 2015.
• Monitoring Report for 735 of the remaining 2.119 PAPs was given No Objection Letter NOL on
November 26, 2015 B. Pending Issues, Concern and Actions
a Monitoring Report for the compensation payments for the remaining 1.384 PAPs has to be submitted to World Bank.
C. Update during this reporting month of December 2015 a Compensation payments for the remaining 2.220 from 2.273 PAP have been already
released. And payment for the remaining 53 PAP is under process b PMU waiting data of payment progress from Satker PJN II Lampung
18. Monitoring Report of the LARAP Package No.18
: Mukomuko Bts. Sumbar
Province : Bengkulu
The sub-project is proposed to be deleted from the WINRIP Program.