Socialization of HIV-AIDs Campaign Comments and Recommendations During WB Mission on 2 to 6 November 2015

Western I ndonesia National Roads I mprovement Project 4 - 15 a No more issue. C. Update during this reporting month of December 2015 a On-going construction. b LARAP implementation is completed

4. Monitoring Report of the LARAP Package No. 4

: Ipuh Bantal Province : Bengkulu A. Previous Status : • LARAP documents approved by World Bank on December 10, 2012 • Monitoring Report No.1, 2 and 3 already approved and No Objection Letter NOL were issued by World Bank B. Pending Issues, Concern and Actions a No more issue. C. Update during this reporting month of December 2015 a On-going construction. b LARAP implementation is completed.

5. Monitoring Report of the LARAP Package No. 5

: Sp. Rampa Poriaha Province : Sumatera Utara A. Previous Status : • LARAP documents approved by World Bank on September 16, 2013. • World Bank accepted the revised LARAP documents and issued No Objection Letter on November 12, 2013 to the action plan implementation of the LARAP. B. Pending Issues, Concern and Actions a Still to be submitted is the implementation report from Satker of the completed relocation of the kiosk. b Existing ROW is not adequate to accommodate the Detailed Engineering Design for Roadway cross sections. WB request Additional LARAP for this package. C. Update during this reporting month of December 2015 a Monitoring Report for the LARAP implementation of the completed relocation of the kiosk still to be prepared for submission to World Bank. b Additional LARAP is under submission to WB.

6. Monitoring Report of the LARAP Package No. 6

: Pasar Pedati - Kerkap Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2015 a No Objection Letter on the revised LARAP documents for implementation. • Monitoring Report concerning the compensation payment for 546 out of 602 PAP was given No Objection Letter NOL on March 23, 2015. Western I ndonesia National Roads I mprovement Project 4 - 16 • Monitoring report regarding compensation payment for 91 of the remaining 91 PAPs was given No Objection Letter NOL on November 26, 2015. B. Pending Issues, Concern and Actions a No more issue. C. Update during this reporting month of December 2015 a On-going construction. b No update this period.

7. Monitoring Report of the LARAP Package No. 7

: Indrapura - Tapan Province : Sumatera Barat A. Previous Status : • LARAP documents approved by World Bank on October 14, 2014. • Implementation action plan of the LARAP was issued No Objection Letter NOL on March 17, 2015 by the World Bank. B. Pending Issues, Concern and Actions a Socialization of the Appraisal result to PAPs. b Implementation cost of LARAP was included by Local Government in the 2015 budget. c Monitoring Report for the compensation payments of the 314 PAPs still to be prepared and submit to World Bank. C. Update during this reporting month of December 2015 a Compensation payment for 314 from total 476 PAPs already paid by Satker PJN II West Sumatera Province.

8. Monitoring Report of the LARAP Package No. 8

: Bts. Pariaman - Manggopoh Province : Sumatera Barat A. Previous Status : • LARAP documents submitted to World Bank on August 7, 2014. • LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions a Compensation payment for this package being done by Local Government of West Sumatera Province. b Implementation cost of LARAP to be paid from APBD Province and APBN 2015. C. Update during this reporting month of December 2015 a 1.210 of the total 1.575 PAP already paid by Local Government. A monitoring report of the payment for 840 PAP already submitted to WB. b PPKSatker PJN I West Sumatera and Local Governmant are being paid the remaining PAP.

9. Monitoring Report of the LARAP Package No. 9

: Rantau Tijang Kota Agung Province : Lampung The sub-project is proposed to be deleted from the WINRIP Program.