Monitoring Report of the LARAP Package No. 12

Western I ndonesia National Roads I mprovement Project 4 - 19

16. Monitoring Report of the LARAP Package No.16

: Seblat - Ipuh Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. • World Bank issued No Objection Letter NOL on Monitoring Report No.1 and 2 for LARAP implementation. • Monitoring Report for 102 of the remaining 120 PAPs was given No Objection Letter NOL by World Bankon November 26, 2015. B. Pending Issues, Concern and Actions a LARAP documents for this Package covers only land acquisition for the road link. If there are land acquisition for the bridge site, a separate LARAP documents need to be prepared. b LARAP Implementation is underway for the remaining 120 PAP be allocated 2015 national budget and schedule to be settled on Dec 2015. C. Update during this reporting month of December 2015 a All of the total 259 PAPs already paid by Satker PJN I Bengkulu. b Data of the payments to the 18 PAP Balance from 259 PAPs are under preparation

17. Monitoring Report of the LARAP Package No.17

: Sp. Gunung Kemala Pg. Tampak Province : Lampung A. Previous Status : • World Bank approved the corrected LARAP documents on November 12, 2013 • Monitoring Report for 154 of the total 2.273 PAPs was given No Objection Letter NOL on October 13, 2015. • Monitoring Report for 735 of the remaining 2.119 PAPs was given No Objection Letter NOL on November 26, 2015 B. Pending Issues, Concern and Actions a Monitoring Report for the compensation payments for the remaining 1.384 PAPs has to be submitted to World Bank. C. Update during this reporting month of December 2015 a Compensation payments for the remaining 2.220 from 2.273 PAP have been already released. And payment for the remaining 53 PAP is under process b PMU waiting data of payment progress from Satker PJN II Lampung

18. Monitoring Report of the LARAP Package No.18

: Mukomuko Bts. Sumbar Province : Bengkulu The sub-project is proposed to be deleted from the WINRIP Program. Western I ndonesia National Roads I mprovement Project 4 - 20

19. Monitoring Report of the LARAP Package No.19

: Lais - Bintunan Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2014 No Objection Letter NOL on the revised LARAP documents for implementation • World Bank issued No Objection Letter NOL on Monitoring Report No.1 for the LARAP implementation. • Monitoring Report for 208 of the remaining 290 PAPs was given No Objection Letter NOL on November 26, 2015. B. Pending Issues, Concern and Actions a Remaining 82 PAP, payments are under finalization. C. Update during this reporting month of December 2015 a Satker PJN I Bengkulu already paid the remaining 82 PAPs b PMU waiting data of payment progress from PPKSatker PJN I Bengkulu as to be submitted to WB.

20. Monitoring Report of the LARAP Package No. 20

: Lubuk Alung - Sicincin Province : Sumatera Barat A. Previous Status : • World Bank issued NOL to LARAP documents on December 19, 2014. B. Pending Issues, Concern and Actions a LARAP implementation to be implemented by Local Government. C. Update during this reporting month of December 2015. a Payment of Compensation to PAP is scheduled for 2016.

21. Monitoring Report of the LARAP Package No. 21

: Lubuk Alung - Kurataji Province : Sumatera Barat A. Previous Status : • World Bank issued NOL to LARAP documents on December 19, 2014. B. Pending Issues, Concern and Actions a LARAP implementation to be implemented by Local Government. C. Update during this reporting month of December 2015 a Payment of Compensation to PAP is scheduled for 2016.