Monitoring Report of the LARAP Package No. 7

Western I ndonesia National Roads I mprovement Project 4 - 18

13. Monitoring Report of the LARAP Package No. 13

: Sp. Rukis Tj. Kemuning Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. • Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank. • World Bank issued on August 18, 2015 No Objection Letter NOL on the Monitoring Report No.1. • World Bank issued on October 13, 2015 No Objection Letter NOL on the Monitoring Report No.2. B. Pending Issues, Concern and Actions a Monitoring Report No.3 for compensation payments of 193 PAPs in Kab. Kaur to be prepared and submitted to WB. C. Update during this reporting month of December 2015 a Compensation payments for the remaining PAP is being done by Satker PJN II Bengkulu. b A Monitoring Report for 193 PAPs is under submission to WB

14. Monitoring Report of the LARAP Package No. 14

: Painan - Kambang Province : Sumatera Barat A. Previous Status : • World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents. • LARAP s signed action plan was given No Objection Letter NOL by World Bank. B. Pending Issues, Concern and Actions a Inventory of affected assets and measurement by Land Acquisition Committe of the Local Government are completed. Appraisal to be done as soon as possible. C. Update during this reporting month of November 2015 a Appraisal process of affected assets is underway.

15. Monitoring Report of the LARAP Package No. 15

: Sibolga Bts. Tapsel Province : Sumatera Utara A. Previous Status : • World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction. • Monitoring Report No.1 for 40 of the remaining 1554 PAPs was given No Objection Letter NOL on November 16, 2015 by the World Bank. B. Pending Issues, Concern and Actions a 1.129from total 1.554 PAP is under negotiationcompensation process. C. Update during this reporting month of December 2015 a Compensation payment for 425 from 1554 PAPs already paid. The payment of the remaining PAPs is under process. b Monitoring Report-2 for the compensation payment for 72 from total 1.514 PAPs already submission to WB