Current Implementation Situation Civil Works

Western I ndonesia National Roads I mprovement Project 1 - 3 Revised : 5 Jan 2016 Length Ction Km Period J N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D 1 Krui - Biha 25,00 21 mth 8 Jan14 2 Padang Sawah - Sp.Empat 40,90 24 mth 6 Jan14 3 Manggopoh - Padang Sawah 32,00 24 mth 6 Jan14 4 Ipuh - Bantal 42,40 24 mth 10 Jan14 5 SIMPANG RAMPA - PORIAHA 11,10 18 mth 18 Jun15 11 Feb17 11 BANTAL - MUKOMUKO 50,10 24 mth 23 Feb15 11 Feb17 13 SP RUKIS - TJ KEMUNING 56,30 24 mth 11 Feb17 17 Sp.Gn.KEMALA - Pg. TAMPAK 36,80 24 mth 04 Sep15 23 Agt17 6 PS. PEDATI - KERKAP 25,00 15 mth 11 Mar15 02 Jun16 19 LAIS - BINTUNAN 11,60 10 mth 11 Mar15 CONST RUCT ION 300+125 days 08 May16 15 SIBOLGA - BATAS TAPSEL 36,00 27 mth 20 Nov15 06 Feb18 7 INDRAPURA - TAPAN 19,50 21 mth 10 Dec15 30 Agt17 8 BTS.Kt PARIAMAN-MANGGOPOH 46,80 24 mth 10 SIMPANG EMPAT - SP.AIR BALAM 61,70 24 mth 12 KAMBANG - INDRAPURA 55,20 24 mth 14 PAINAN KAMBANG 31,50 21 mth 16 SEBLAT IPUH 34,50 21 mth 20 LUBUK ALUNG SICINCIN 14,60 18 mth 21 LUBUK ALUNG KURAITAJI 16,80 18 mth 9 RANTAU TIJANG-KOTA AGUNG 42,00 The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIPs work program 18 MUKOMUKO-BTS SUMBAR 25,80 The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIPs work program Original target : 715,60 km ENVIRONMENT SOCIAL SAFEGUARD Revised target : 647,80 km Prequalification Detail Eng Design LARAP Study Road Safety Owners Estimate Appraisal Public Consultation Procurement Sign Contr Bid Document LARAP Implementation Preparation for Commencement of Work Standard Biding Document COW CONSTRUCTION Rev-DED RS Rev-DED RS Rev-DED RS ICB ICB ICB NCB NCB NCB NCB COW PROC COW PROC PROC PROC PROC CONSTRUCTION CONSTRUCTION CONSTRUCTION DED CONSTRUCTION PQ Rev-DED RS PROC CONST RUCT ION 720 days ICB ICB ICB ICB NCB NCB NCB Review DED RS Review DED RS SBD OE + BD CONST RUCT ION 810 days CONST RUCT ION 630 days 22-Jul-15 PQ RS Proc COW SBD CONST RUCT ION 730 + 105 days CONST RUCT ION 730 + 75 days CONST RUCT ION 730 + 90 days DED RSA REVISED DED OE BD DED RSA REVISED DED OE BD DED OE BD Review DED RS PROC PROC PROC Review DED RS CONSTRUCTION Review DED RS PQ PROC Review DED RS PQ DED SBD OE + BD DED DED RSA REVISED DED OE BD DED RSA REVISED DED OE BD DED Review DED RS CONSTRUCTION CONST RUCT ION 450 days SBD OE + BD CONST RUCT ION 720 days CONST RUCT ION 720 days PROC Pack PACKAGE NAME 2012 2013 2014 2015 2016 2017 2018 PQ ICB ICB ICB ICB ICB 10-Jan-16 CONST RUCT ION 640 + 93 days 19-Apr-16 20-Mar-16 08-Apr-16 CONST RUCT ION 540 days Actual Implementation Timeline of WINRIP Western I ndonesia National Roads I mprovement Project 1 - 4 REF 1.25 0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00 Month C om pl e te Actual Expenditure USD 48.27 mil 19.31 WINRIP ACTUAL PROGRESS UP TO DECEMBER 2015 AND FORECAST UP TO DECEMBER 2017 ACTUAL December 2015 Forecast December 2015 Forecast Expenditure USD 130.63 mil 52.25 Deviation = 32.94

1.2 Disbursement

Loan Allocation and Percent Disbursement To Date The total disbursements from the loan to the end of December 2015 was USD 48,269,952.38 equivalent to approximately 19.31 of the loan funds. The following table summarizes the individual disbursements as calculated by CTC but retaining the total disbursement from Client Connection at the end of December 2015. Appendix A shows the Overall Loan Progress Status. Category Description Loan Restructuring Amount US Disbursement This Period Previous Disbursement Totals Disbursed to End December in US Disbursed 1 Part 1 Betterment and Capacity Expansion of National Roads. 220,400,000.00 10,529,052.88 33,456,018.67 43,985,071.55 19.96 2 Part 2 Implementation Support 16,000,000.00 4,284,880.83 4,284,880.83 26.78 3 Part 3 Road Sector Institutional Development 1,000,000.00 4 Part 4 Contingency for Disaster Risk Response Unallocated 12,600,000.00 Original Loan Amount 250,000,000.00 10,529,052.88 37,740,899.50 48,269,952.38 19.31 Breakdown of amount disbursed during the period December 2015 are the payments for Statement of Work Accomplished for the following civil works contract packages : • Package No. 1 : MC Nos. 22, 23 and 24 USD 1,430,504.09 • Package No. 2 : MC No. 23 USD 1,838,979.81 • Package No. 3 : MC No. 23 USD 1,114,853.21 • Package No. 4 : MC No. 23 USD 1,232,489.93 • Package No. 6 : MC Nos. 1 up to 9 USD 655,904.82 Western I ndonesia National Roads I mprovement Project 1 - 5 • Package No. 7 : Advance Payment USD 1,005,277.15 • Package No. 11 : MC Nos. 8 and 9 USD 1,405,748.47 • Package No. 13 : MC Nos. 1 up to 6 USD 1,328,071.39 • Package No. 17 : MC Nos. 1 and 2 USD 105,972.89 • Package No. 19 : MC Nos. 7, 8 and 9 USD 411,251.12 Total USD 10,529,052.88 The ending balance for Special Account as of end of December 2016 is USD 69,582.70.

1.3 World Bank Implementation Review Mission and Site Visit

During the period December 2015 there was no implementation review, mission nor site visit. However, the regular monthly meeting to review the implementation progress and monitoring the key activities on the Agreed Key Action Plans was held on December 16, 2015.

1.4 Procurement of Civil Works Contract Under Category 1 of the Loan Agreement

The current status of Contract Packages which are under final procurement stage are as follows :

1. Package No.7 Indrapura - Tapan AWP-2

The sub-project is to be implemented under implementation schedule AWP-2. The Project road length covers 19.50 kilometers and is located in the Province of Sumatera Barat. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB method using the Full e-Procurement System using the Full e-Procurement System. Notice To Proceed to commence the work has been issued on December 10, 2015.

2. Package No.8 Bts. Kota Pariaman - Manggopoh AWP-2

This sub-project is under implementation schedule AWP-2. The project roadline is located in the Province of Sumatera Barat having an approximate length of 46.80 kilometers. The Contract Package is procured thru the post qualification and International Competitive Bidding ICB procurement method using the Full e-Procurement System. The Revised Bid Evaluation Report BER based on further clarification by World Bank on their letter of October 12, 2015, has been concured with the issuance of No Objection Letter to award the Contract subject for approval by the Ministry of Public Works and Housing MPWH

3. Package No.10 Sp. Empat

Sp. Air Balam AWP-2 This sub-project is under implementation schedule AWP-2. The project roadline is located in the Province of Sumatera Barat having an approximate length of 61.70 kilometers. The Contract Package is procured thru the post qualification and International Competitive Bidding ICB procurement method using the Full e-Procurement System. The Revised Bid Evaluation Report BER is still under final evaluation and review by PMU prior to resubmission to World Bank for request of issuance of No Objection Letter NOL to award the Contract. Western I ndonesia National Roads I mprovement Project 1 - 6

4. Package No.12 Kambang - Indrapura AWP-2

This sub-project is under implementation schedule AWP-2. The project roadline is located in the Province of Sumatera Barat having an approximate length of 55.20 kilometers. The Contract Package is procured thru the post qualification and International Competitive Bidding ICB procurement method using the Full e-Procurement System. During the period December 2015, refinement of contract documents in preparation to contract signing between the GOI and the winning responsive bidder, PT. Lancar Jaya M.A. PT. LTA JO has been under finalization. It is expected that the contract signing by both parties will be executed during the middle part of January 2016.

5. Package No.16 Seblat-Ipuh AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road length covers 34.50 kilometers and is located in the Province of Bengkulu. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB method using the Full e-Procurement System. Bid Evaluation and preparation of Bid Evaluation Report BER is on-going.

6. Package No.14 Painan - Kambang AWP-3

The Subject is to be implemented under implementation schedule AWP-3. The Project road lenght covers 31.50 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. The sub-project is under procurement procceeding with bid submissions and opening scheduled on January 5, 2016 at Padang.

7. Package No.20 Lubuk Alung - Sicincin AWP-3

The Subject is to be implemented under implementation schedule AWP-3. The Project road lenght covers 14.60 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. The sub-project is under procurement procceeding with bid submissions and opening scheduled on January 5, 2016 at Padang

8. Package No.21 Lubuk Alung - Kuraitaji AWP-3

The Subject is to be implemented under implementation schedule AWP-3. The Project road lenght covers 16.80 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. The sub-project is under procurement procceeding with bid submissions and opening scheduled on January 5, 2016 at Padang